Sat , 09/04/2022, 01:00:00 (GMT+7)
The ceremony was attended by:
On the side of local leaders, there are:
On the VINACONEX side, there are:
Together with supervision consulting units, construction contractors…
Vinaconex - Trung Nam E&C consortium is honored to be the unit implementing the XL-14 package for construction of the section Km318+000 - Km337+478.11 (including survey, construction drawing design) with a value of nearly 2,500 billion VND; implementation period 24 months. The bidding package has a segment length of 19.49km passing through 5 districts and cities of Thanh Hoa province, including: Thieu Hoa district, Dong Son district, Trieu Son district, Nong Cong district, Thanh Hoa city.
Do mountain bridge crosses the Chu river, the section crosses the territory of Thieu Hoa district, Thanh Hoa province
Located in the overall, Nui Do Bridge is a bridge spanning the Chu River, more than 1,646 m long and the longest bridge in the Mai Son - National Highway 45 expressway project.
According to the design, the main bridge girder uses continuous prestressed reinforced concrete beams constructed by the balanced cantilever method; The bridge's cross section is 23.5m, including 4 lanes and has a median and safety strip.
Do mountain bridge has a total length of 1,646.9m and is the longest bridge on the Mai Son - National Highway 45 highway.
With a high sense of responsibility for the meaning and importance of the project, Vinaconex - Trung Nam E&C Joint Venture has made great efforts to overcome difficulties, complete the construction of items outside the river to overcome the flood of the Chu River as planned. and conduct Hop Long main span on April 9, 2022 (21 days ahead of schedule).
Speaking at the ceremony, Mr. Ho Ngoc Loan, Deputy Director of Thang Long Project Management Board - Ministry of Transport congratulated Vinaconex - Trung Nam E&C contractor consortium on completing the final span of Nui Do Bridge and the bridge. the largest section of Mai Son - National Highway 45, creating a premise for the Joint Venture to complete the bridge in particular and the package in general as planned. The Deputy Director requested the relevant units to closely coordinate and control the quality of the works so that the XL14 package in particular and the entire Mai Son - National Highway 45 project can be completed with the right quality and schedule, meeting the plan set by the Ministry of Finance. Transport proposed.
Mr. Ho Ngoc Loan, Deputy Director of Thang Long PMU - Ministry of Transport spoke at the ceremony
Vinaconex - Trung Nam E&C contractor consortium joins the main span of Nui Do bridge 21 days ahead of schedule
Concrete batches are pumped to combine the longest bridge on Mai Son highway - National Highway 45
Attendees took souvenir photos at the project
From the time the project was started and until now by means of speeding up measures such as overtime, increasing working hours, engineers and workers at the project have been constructing through holidays, adjusting progress, increasing equipment and machinery and constantly improving construction technology.
Hoping the main span of Nui Do bridge ahead of schedule is a great effort of Vinaconex - Trung Nam E&C contractor consortium.
Quality assurance and progress are prerequisites for the package to arrive on schedule
On the side of the construction unit at the project, Vinaconex - Trung Nam E&C Joint Venture commits to continue its efforts and accelerate the completion of the remaining items on the main route in order to meet the schedule and ensure communication conditions. technical vehicles as planned on September 30, 2022; while enhancing the brand reputation of Vietnamese contractors and Vinaconex in particular in the field of modern and large-scale expressway construction.