EN

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Fri , 10/01/2025, 08:28:00 (GMT+7)

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

In early 2025, work began on installing the roof of the Long Thanh airport passenger terminal construction site.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

To date, approximately three spans of the roof, covering 1,500 square meters, have been completed. The project is on track to finish two months ahead of schedule, with the terminal roof expected to be completed by the third quarter of 2025.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

At the terminal wing under construction by Vinaconex, workers diligently install roof panels at a height of tens of meters above ground. Each step—drilling, screwing, and joining—is executed with precision and care. 

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Engineers explained that the roof comprises five layers, each designed to meet exacting technical standards. During installation, each layer undergoes rigorous inspections for flatness, tightness, and weather resistance. “Every layer is vital for insulation, waterproofing, and surface protection, ensuring the roof's durability, etc. After each layer is placed, precise measurements and alignments are verified before moving to the next,” said Nguyen Van Tam, a roofing contractor.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

As observation of reporters, workers at the site, operating at significant heights, are equipped with safety belts and non-slip footwear. Before every shift, they thoroughly inspect their tools and safety gear to ensure optimal working conditions. (Photo: Construction staff captured the moment of installing the first roof panels.)

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

“Working at heights in challenging conditions of heat and wind requires utmost precision and caution. We are racing to meet deadlines while prioritizing the safety of ourselves and our colleagues," said Nguyen Van Tuan (the one on the right), a worker at the site.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL
A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Many workers involved in roofing the terminal noted that safety officers conduct regular inspections, offer reminders, and promote safety practices during construction. Those who fail to adhere to safety protocols will be immediately reminded and penalized.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

In addition to roofing, the construction team is advancing work on the steel roof structure, foundations for boarding bridges, corridor staircases, elevators and so on. (Photo: workers assembling the steel structure of the central terminal roof.)

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

The Long Thanh airport passenger terminal features a central area and three wings, with distinct zones for departures and arrivals. The terminal spans a ground floor and three additional levels, reaching a roof height of over 45 meters and a total floor area of approximately 376,000 sqm. With a total investment of VND 35 trillion, terminal construction commenced in 2023 and is slated for completion by 2025.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Mr. Duong Quang Dien, Permanent Deputy Director of the Long Thanh Project Management Board, stated that the terminal’s roof will require approximately 36,000 tons of steel. The steel materials are being imported and processed domestically for the installation, which began in August 2024 and is expected to be completed by the third quarter of 2025.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

The installation of the terminal roof and steel roof structure requires workers to operate at significant heights under challenging and hazardous conditions, often working through the day and night. To ensure safety, the Project Management Board and associated units have intensified inspections and supervision, mandating strict compliance with safety protocols. (Photo: workers are cleaning large steel panels in preparation for installation.) 

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

According to Mr. Dien, in addition to the passenger terminal, several other items on the construction site are being constructed simultaneously. Nearly 10,000 workers and pieces of construction machinery have been deployed by the joint venture of contractors to work around the clock, accelerating progress toward completion.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Long Thanh Airport, spanning a vast 5,000-hectare site, has a total estimated investment of approximately VND 336,630 billion. The first phase of the airport is designed to accommodate 25 million passengers annually, with subsequent phases aiming to increase capacity to 100 million passengers per year. Once completed, the airport is expected to serve as a major international hub for Vietnam and the region. Currently, key components, including the passenger terminal, runway, and T1 and T2 access roads, are progressing ahead of schedule.

Source: baogiaothong

 

Latest news

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

38 năm hình thành và phát triển là hành trình được tạo nên bởi bản lĩnh, trí tuệ, sự bền bỉ và tinh thần đoàn kết của nhiều thế hệ người lao động VINACONEX. Từ những giá trị được vun đắp qua năm tháng, Tổng công ty hôm nay tiếp tục đổi mới, nâng cao ...

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

Tổng công ty CP VINACONEX vừa tiếp nhận lô thiết bị máy khoan cọc nhồi SANY SR235 và SANY SR285R, bổ sung nguồn lực thiết bị hiện đại, góp phần nâng cao năng lực thi công nền móng và tăng tính chủ động trong triển khai các dự án quy mô lớn.

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

KHỞI CÔNG CỤM CÔNG NGHIỆP SƠN ĐÔNG - Không gian sản xuất mới phía Tây thủ đô

Hướng tới chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX, ngày 17/9/2026, Cụm công nghiệp Sơn Đông đã chính thức được khởi công tại xã Đoài Phương, TP. Hà Nội, mở thêm không gian sản xuất tập trung, hiện đại phía Tây Thủ đô.

KHỞI CÔNG CỤM CÔNG NGHIỆP SƠN ĐÔNG - Không gian sản xuất mới phía Tây thủ đô

Ánh trăng ước mơ 2026: Trao yêu thương – Gửi gắm ước mơ

Sân khấu rộn ràng, những tiết mục xiếc đặc sắc, tiếng cười trong trẻo cùng những phần quà ý nghĩa đã tạo nên một mùa Trung thu đáng nhớ cho các em thiếu niên, nhi đồng trong đại gia đình VINACONEX.

Ánh trăng ước mơ 2026: Trao yêu thương – Gửi gắm ước mơ
Loading...