A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL - Trang chủ | Vinaconex

EN

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Fri , 10/01/2025, 08:28:00 (GMT+7)

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

In early 2025, work began on installing the roof of the Long Thanh airport passenger terminal construction site.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

To date, approximately three spans of the roof, covering 1,500 square meters, have been completed. The project is on track to finish two months ahead of schedule, with the terminal roof expected to be completed by the third quarter of 2025.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

At the terminal wing under construction by Vinaconex, workers diligently install roof panels at a height of tens of meters above ground. Each step—drilling, screwing, and joining—is executed with precision and care. 

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Engineers explained that the roof comprises five layers, each designed to meet exacting technical standards. During installation, each layer undergoes rigorous inspections for flatness, tightness, and weather resistance. “Every layer is vital for insulation, waterproofing, and surface protection, ensuring the roof's durability, etc. After each layer is placed, precise measurements and alignments are verified before moving to the next,” said Nguyen Van Tam, a roofing contractor.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

As observation of reporters, workers at the site, operating at significant heights, are equipped with safety belts and non-slip footwear. Before every shift, they thoroughly inspect their tools and safety gear to ensure optimal working conditions. (Photo: Construction staff captured the moment of installing the first roof panels.)

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

“Working at heights in challenging conditions of heat and wind requires utmost precision and caution. We are racing to meet deadlines while prioritizing the safety of ourselves and our colleagues," said Nguyen Van Tuan (the one on the right), a worker at the site.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL
A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Many workers involved in roofing the terminal noted that safety officers conduct regular inspections, offer reminders, and promote safety practices during construction. Those who fail to adhere to safety protocols will be immediately reminded and penalized.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

In addition to roofing, the construction team is advancing work on the steel roof structure, foundations for boarding bridges, corridor staircases, elevators and so on. (Photo: workers assembling the steel structure of the central terminal roof.)

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

The Long Thanh airport passenger terminal features a central area and three wings, with distinct zones for departures and arrivals. The terminal spans a ground floor and three additional levels, reaching a roof height of over 45 meters and a total floor area of approximately 376,000 sqm. With a total investment of VND 35 trillion, terminal construction commenced in 2023 and is slated for completion by 2025.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Mr. Duong Quang Dien, Permanent Deputy Director of the Long Thanh Project Management Board, stated that the terminal’s roof will require approximately 36,000 tons of steel. The steel materials are being imported and processed domestically for the installation, which began in August 2024 and is expected to be completed by the third quarter of 2025.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

The installation of the terminal roof and steel roof structure requires workers to operate at significant heights under challenging and hazardous conditions, often working through the day and night. To ensure safety, the Project Management Board and associated units have intensified inspections and supervision, mandating strict compliance with safety protocols. (Photo: workers are cleaning large steel panels in preparation for installation.) 

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

According to Mr. Dien, in addition to the passenger terminal, several other items on the construction site are being constructed simultaneously. Nearly 10,000 workers and pieces of construction machinery have been deployed by the joint venture of contractors to work around the clock, accelerating progress toward completion.

A CLOSER LOOK AT THE 5-LAYER ROOF CONSTRUCTION OF LONG THANH AIRPORT TERMINAL

Long Thanh Airport, spanning a vast 5,000-hectare site, has a total estimated investment of approximately VND 336,630 billion. The first phase of the airport is designed to accommodate 25 million passengers annually, with subsequent phases aiming to increase capacity to 100 million passengers per year. Once completed, the airport is expected to serve as a major international hub for Vietnam and the region. Currently, key components, including the passenger terminal, runway, and T1 and T2 access roads, are progressing ahead of schedule.

Source: baogiaothong

 

Latest news

Hội nghị sơ kết công tác Công đoàn 6 tháng đầu năm, triển khai nhiệm vụ 6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác

Ngày 31/7, Công đoàn Tổng công ty tổ chức Hội nghị sơ kết công tác công đoàn 6 tháng đầu năm, triển khai nhiệm vụ trọng tâm 6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác. Đồng chí Âu Thị Định, Phó Chủ tịch Công đoàn XDVN đã tham dự và phát ...

Hội nghị sơ kết công tác Công đoàn 6 tháng đầu năm, triển khai nhiệm vụ  6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác

Tập Huấn An Toàn – Vệ Sinh Lao Động và khám sức khoẻ tại Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long

Nhằm tăng cường tuân thủ các quy định pháp luật và nâng cao hiệu quả thi công, ngày 28/7/2025, tại Văn phòng Ban QLDA Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long đã diễn ra buổi Huấn luyện An toàn lao động ...

Tập Huấn An Toàn – Vệ Sinh Lao Động và khám sức khoẻ tại Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

At the construction site of the Phu Thu Interchange Ninh Binh Province , over 100 engineers, technicians, and workers from the VINACONEX–Trung Chinh joint venture are working around the clock, through holidays, striving to complete the project by ...

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

VINACONEX CORPORATION’S “BACK TO THE ROOTS” JOURNEY

In celebration of the successful 6th Party Congress of VINACONEX Corporation for the 2025–2030 term, and in commemoration of the 78th War Invalids and Martyrs Day July 27, 1947 – July 27, 2025 , the VINACONEX Trade Union organized a “Back to the ...

VINACONEX CORPORATION’S “BACK TO THE ROOTS” JOURNEY
Loading...