VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT - Trang chủ | Vinaconex

EN

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

Mon , 03/10/2022, 14:10:00 (GMT+7)

The Vung Ang II thermal power BOT project is implemented by the main constructor -  Doosan Heavy Industries and Construction Co., Ltd. Having been honored to engage as a construction contractor, Vinaconex has overcome all obstacles, sticking to the progress, ensuring the safety and quality of the project's items under Vinaconex’s responsibility.
Vung Ang II Thermal Power is a build–operate–transfer (BOT) project with a total investment of $2.2 billion and Vung Ang II Thermal Power Company Limited (VAPCO) as the main contractor. The project has a total capacity of 1330 MW, consisting of 2 machine units. It’s located in Hai Phong village, Ky Loi commune, Ky Anh town, Ha Tinh province, next to the existing Vung Ang I thermal power plant. According to the plan, the project, including the main plant, coal unloading jetty, ash and slag disposal areas, and related ancillary works, would be completed and put into commercial operation in the third quarter of 2025.

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Vung Ang II Thermal Power Plant, one of the key projects, is built next to Vung Ang I Thermal Power Plant.

With outstanding competence and experience in construction of key national and international projects, particularly in the field of industrial construction, petrochemical project, Vinaconex is honored to have been chosen by the main constructor – Doosan Company (Korea), as a contractor for items of Package B (including central control building and technical infrastructure), with a value of about VND 453 billion (excluding VAT), and an approx 25-month implementation period (from April 2022 to April 2024). 

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Vinaconex constructor always be on schedule.

Despite all obstacles, Vinaconex is moving forward with the concurrent construction of the package's items, including the CCB, Turbine House, Chimney Foundation, Transformers, etc., and is striving to finish and hand over the entire package by April 2024 in line with the committed schedule.
The CCB operator is currently preparing to pour concrete for the third floor (expected on October 21) after finishing the rough construction, floor, and beams on the 1st & 2nd floors.

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Erecting the steel structure, preparing to pour concrete on the CCB’s third floor
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Completing the rough construction with formwork and cover mesh to ensure safety – sanitation.

As for Turbine House: In Turbine #1, finished concreting foundations MF1 (Cep pit), MF2, and particularly STG1 with a concrete volume of 2500 m3. Executing the erection, concrete pouring of the cable pit and excavation work for turbine #2’s foundation.

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Concrete pouring Discharge foundation: 900 m3
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Concrete pouring CEP Pit foundation: 700 m3

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Concrete pouring STG foundation: 2500 m3

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Erecting a steel foundation for the cable trench: 300 m3
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Mounting anchor foundation bolts and concrete pouring pedestal
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Erecting the steel foundation of Transformer #1 and excavating the foundation of Transformer #2
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Erecting the steel foundation of Transformer #1
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Ground filling in Transformer #2
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Formwork and reinforcement of Chimney’s foundation. It’s expected that Vinaconex contractor would pour concrete Chimney’s foundation in early October with a volume of 4000 m3

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Erecting the steel foundation and pouring concrete for the Chimney’s foundation with a volume of 4000 m3

 

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Erecting the steel foundation and concrete pouring for Factory, Warehouse with volume of 3000m3
VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Training in Safety, Sanitation & Fire Protection is carried out regularly and is compulsory on the construction site before each shift.

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT
Employees and workers get training on Safety, Sanitation & Fire Protection before working the night shift.
With thousands of projects in the fields of civil and industrial construction, technical and traffic infrastructure, urban areas, and social security works over 34 years of building and development, Vinaconex has contributed to the industrialization and modernization of Vietnam. Regarding important industrial works in the country, Vinaconex is honored to be the contractor working on the Dung Quat Refinery and Petrochemical Plant Construction Investment Project, the Nghi Son Refinery and Petrochemical Complex, the Southern Petrochemical Complex, etc.

 

Transformer 1

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

 Transformer 2

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

Turbine house

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

Chimney

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

CCB

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

VINACONEX STICKS TO THE CONSTRUCTION SCHEDULE OF VUNG ANG II THERMAL POWER PLANT PROJECT

Loading...