Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi - Trang chủ | Vinaconex

EN

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Sat , 26/02/2022, 00:00:00 (GMT+7)

In the first days of the Lunar New Year, hundreds of construction workers of the Vinh Tuy 2 bridge project (Hanoi) across the Red River with an investment of about 2,538 billion VND are still rushing to work day and night to ensure progress.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Vinh Tuy 2 bridge construction project (Vinh Tuy bridge phase 2) was started from January 2021 with a total investment of over 2,500 billion VND; Completion is expected in 2023.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

The bridge has the same design as Vinh Tuy 1 bridge with a total length and path of more than 3.4km.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

The bridge has a cross section of 19.25m (with 4 lanes); the static height of the bridge is 11m; The starting point is at Km0+840 (intersection with Nguyen Khoai and Minh Khai streets), the end point at Km4 + 312.62 (intersection with Long Bien - Thach Ban and Co Linh streets).

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Equipment and machinery are busy at the construction site in the first days of the Lunar New Year.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Currently, contractors are working on creating a steel frame, pumping water, drilling piles to then pour concrete on the bridge piers in the Red River bed.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Some spans of the bridge on the side of Long Bien district have completed the construction of the pillars, the contractors are carrying out beams, iron knitting, concrete pouring...

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Currently on the site there are 11 construction units with 11 stitches, mobilizing hundreds of employees, working 3 shifts, 4 crews, 24/24 hours to ensure the progress of the work in the coming year.

Vinaconex - Trung Chinh joint venture is the main contractor in charge of the largest work item and has the highest technical requirements at Vinh Tuy 2 bridge project.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Vinh Tuy 2 bridge project belongs to the list of key works of Hanoi city, aiming to complete the entire Ring Road 2; increase circulation between the two banks of the Red River and meet the increasing transport demand between the center of the capital and the north and northeast of the capital.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Hundreds of workers rush to create a mold for the bridge girder of the Vinh Tuy 2 bridge project.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Vinh Tuy 2 Bridge is permanently designed with reinforced concrete and prestressed reinforced concrete, withstands earthquakes of grade 8. The project is expected to solve the pressure for the area, especially to reduce the load on the bridge. Thanh Tri on Ring Road 3 is often overloaded.

According to Tienphong.vn

Latest news

Vinaconex Phát Động Thi Đua Tại Dự Án Cảng Hàng Không Quốc Tế Long Thành

Với quyết tâm đẩy nhanh tiến độ, hoàn thành Dự án đúng kế hoạch, đảm bảo chất lượng, an toàn vệ sinh, môi trường, ngày 14/4, Tổng công ty đã tổ chức Lễ phát động thi đua tại Dự án Cảng HKQT Long Thành. Đồng chí Nguyễn Thanh Tùng, Ủy viên BCH ...

Vinaconex Phát Động Thi Đua Tại Dự Án Cảng Hàng Không Quốc Tế Long Thành

Tiến độ thi công Dự án Đường Vành đai 4 - Vùng Thủ đô

Cập nhật tiến độ thi công đến tháng 04/2024. Vinaconex vinh dự được lựa chọn là nhà thầu thực hiện gói thầu 09/TP2 – XL có chiều dài lớn nhất của dự án khoảng 23 km thuộc Dự án thành phần 2.1 Xây dựng đường song hành đường đô thị địa phận thành ...

Tiến độ thi công Dự án Đường Vành đai 4 - Vùng Thủ đô

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE

On April 5, the Vietnam Electricity Corporation EVN delegation, led by Mr. Nguyen Duc Cuong - Member of ENV's Member Board and Mr. Pham Hong Phuong, Deputy General Director, paid a visit to inspect the construction work and held a Progress ...

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE

HANOI APPROVES INVESTMENT LICENSE FOR CONSTRUCTION INVESTMENT AND INFRASTRUCTURE BUSINESS OF DONG ANH INDUSTRIAL PARK

On April 1, the Hanoi People's Committee convened a conference chaired by Vice Chairman Nguyen Manh Quyen to grant the Investment Registration Certificate for the Dong Anh Industrial Park infrastructure development and business investment project in ...

HANOI APPROVES INVESTMENT LICENSE FOR CONSTRUCTION INVESTMENT AND INFRASTRUCTURE BUSINESS OF DONG ANH INDUSTRIAL PARK
Loading...