Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi - Trang chủ | Vinaconex

EN

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Sat , 26/02/2022, 00:00:00 (GMT+7)

In the first days of the Lunar New Year, hundreds of construction workers of the Vinh Tuy 2 bridge project (Hanoi) across the Red River with an investment of about 2,538 billion VND are still rushing to work day and night to ensure progress.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Vinh Tuy 2 bridge construction project (Vinh Tuy bridge phase 2) was started from January 2021 with a total investment of over 2,500 billion VND; Completion is expected in 2023.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

The bridge has the same design as Vinh Tuy 1 bridge with a total length and path of more than 3.4km.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

The bridge has a cross section of 19.25m (with 4 lanes); the static height of the bridge is 11m; The starting point is at Km0+840 (intersection with Nguyen Khoai and Minh Khai streets), the end point at Km4 + 312.62 (intersection with Long Bien - Thach Ban and Co Linh streets).

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Equipment and machinery are busy at the construction site in the first days of the Lunar New Year.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Currently, contractors are working on creating a steel frame, pumping water, drilling piles to then pour concrete on the bridge piers in the Red River bed.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Some spans of the bridge on the side of Long Bien district have completed the construction of the pillars, the contractors are carrying out beams, iron knitting, concrete pouring...

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Currently on the site there are 11 construction units with 11 stitches, mobilizing hundreds of employees, working 3 shifts, 4 crews, 24/24 hours to ensure the progress of the work in the coming year.

Vinaconex - Trung Chinh joint venture is the main contractor in charge of the largest work item and has the highest technical requirements at Vinh Tuy 2 bridge project.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Vinh Tuy 2 bridge project belongs to the list of key works of Hanoi city, aiming to complete the entire Ring Road 2; increase circulation between the two banks of the Red River and meet the increasing transport demand between the center of the capital and the north and northeast of the capital.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Hundreds of workers rush to create a mold for the bridge girder of the Vinh Tuy 2 bridge project.

Hundreds of workers hustle on the great construction site of 2,500 billion VND in Hanoi

Vinh Tuy 2 Bridge is permanently designed with reinforced concrete and prestressed reinforced concrete, withstands earthquakes of grade 8. The project is expected to solve the pressure for the area, especially to reduce the load on the bridge. Thanh Tri on Ring Road 3 is often overloaded.

According to Tienphong.vn

Tin mới nhất

Ra quân đầu Xuân tại dự án xây dựng Khu công nghiệp sạch tỉnh Hưng Yên

Hoàn thành 72% tổng tiến độ, tương đương 770 tỷ đồng trong năm 2023 là mục tiêu phấn đấu của Liên danh nhà thầu KYERYONG – VINACONEX tại dự án xây dựng cơ sở hạ tầng Khu công nghiệp sạch tỉnh Hưng Yên.

Ra quân đầu Xuân tại dự án xây dựng Khu công nghiệp sạch tỉnh Hưng Yên

Nhà thầu "dàn trận" đẩy nhanh tiến độ đại công trường dự án sân bay Long Thành

Dự án sân bay Long Thành khởi công ngày 5/1/2021 do Tổng công ty Cảng hàng không Việt Nam ACV làm chủ đầu tư. Giai đoạn 1 của dự án sân bay Long Thành có diện tích 5.000ha, tổng mức đầu tư hơn 109.000 tỷ đồng, đạt chuẩn cảng hàng không quốc tế cấp ...

Nhà thầu

VINACONEX: 10 Điểm sáng 2022

Năm 2022, với chỉ đạo sát sao của Chính phủ, sự nỗ lực của cộng đồng, dịch bệnh từng bước được kiểm soát, công tác đẩy mạnh phục hồi SX – KD được coi là nhiệm vụ trọng tâm hàng đầu trên toàn quốc Với Vinaconex, năm qua cũng là khoảng thời gian Tổng ...

VINACONEX: 10 Điểm sáng 2022

Quà Tết Xuân Quý Mão dành tặng đoàn viên công đoàn, người lao động Vinaconex

Triển khai các hoạt động chăm lo đời sống vật chất và tinh thần cho đoàn viên công đoàn dịp Tết Nguyên đán Quý Mão 2023, ngày 12/1, Công đoàn Tổng công ty tổ chức chương trình “tiếp nhận và tặng quà Tết nhân dịp Xuân Quý Mão 2023 cho Đoàn viên công ...

Quà Tết Xuân Quý Mão dành tặng đoàn viên công đoàn, người lao động Vinaconex
Loading...