LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD - Trang chủ | Vinaconex

EN

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD

Sat , 01/11/2025, 10:28:00 (GMT+7)

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
Perspective Rendering of the Ring Road 3.5 - Thang Long Boulevard Interchange

The project to construct the grade-separated interchange between Ring Road 3.5 and Thang Long Boulevard (An Khanh Commune) was approved by the Hanoi People’s Committee, with a construction timeline scheduled for 2022-2026. By late February 2025, the project officially broke ground after site clearance had been completed.
Designed as a key component of the Capital Region’s ring-road network, the Ring Road 3.5 - Thang Long Boulevard interchange serves as a “backbone” corridor, expanding urban development space, reducing pressure on the city center, and driving westward urban growth.

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD

After more than eight months of construction, the initial shape of the grade-separated interchange has begun to emerge. The vast construction site is operating at full capacity, accelerating progress to meet the project’s delivery milestones.

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD

The project has a total investment of approximately VND 2.384 trillion and is managed by the Hanoi Project Management Board of Civil Construction Investment. At Package No. 28, one of the project’s most critical components, VINACONEX and the Thang Long Joint Venture are responsible for preparing detailed construction drawings (including complete BIM application, executing all transportation and technical infrastructure works, and procuring and installing project equipment - excluding the relocation of existing utilities).

In particular, the comprehensive Building Information Modeling (BIM) system is being applied to coordinate design, progress, and quality management, enabling seamless planning, preventing conflicts and overlaps between work items, and maintaining the construction schedule.
VINACONEX and the Joint Venture have achieved significant progress across all work categories. Specifically:
Road and technical infrastructure works completed 100% of cement-deep mixing (CDM) ground improvement piles. Earth excavation and K95 sand embankment for the roadbed have reached 25% and 60% completion, respectively.

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
Bridge Construction: VINACONEX and the contractor joint venture are accelerating progress across the entire route. Bored piling and abutment construction (Phase 1) have reached 65% and 32% completion, respectively.
LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
 
LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
As for the tunnel works, VINACONEX and the contractor joint venture are increasing output on reinforced concrete pile casting, pile driving, and tunnel excavation.

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
 

LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
The direct underpass connecting Hoang Tung Street through Thang Long Boulevard to National Highway 32 is gradually taking shape. On the National Highway 32 side, the open-cut tunnel section is designed to be 157.5 meters long, with 200 meters of retaining walls. The remaining wheel-guard sections are also beginning to reveal their initial structural form.
LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
Ring Road 3.5 project Phase 3 is now entering its final construction stages. Once completed, it will seamlessly connect to the interchange with Thang Long Boulevard.
LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
To proactively prevent risks during the rainy and storm seasons, throughout the project implementation, the contractor has reinforced pumping stations, improved the drainage system, and ensured safe, efficient construction without flooding. With the highest commitment, VINACONEX and the joint venture aim to complete the major components in 2025, targeting early technical traffic opening ahead of schedule.
LATEST PROGRESS UNVEILED AT THE MEGA INTERCHANGE AT RING ROAD 3.5 - THANG LONG BOULEVARD
When the first vehicles run through the Ring Road 3.5 - Thang Long Boulevard underpass, it will not only improve traffic flow but also be a pivotal milestone in Western Hanoi's infrastructure landscape. 


 


 

Loading...