Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

Thu , 10/02/2022, 00:00:00 (GMT+7)

On the morning of February 8, Mr. Chu Ngoc Anh, Chairman of the Hanoi People's Committee, inspected the construction site of a number of key traffic projects in the city, including the Vinh Tuy bridge project - phase 2.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

At the construction site of Vinh Tuy bridge - phase 2, a representative of the Traffic Construction Investment Project Management Board (PMU) of Hanoi said that by February 2022, the contractors had completed 558 /562 bored piles; pouring concrete to seal the bottom of pillars T19HL, T23HL, T24HL, T25HL; cast 234/396 Super T beam slabs; pouring concrete of hollow slab beams cast on scaffolding 2/6 segments.

According to the PMU, the total contract value is VND 2,068 billion. Accumulated disbursement to date is 983,875 billion dong.

It is expected that the project will basically complete the spans leading to Long Bien in 2022; complete the main spans by April 30, 2023 and complete the whole project in June 2023.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

The construction site of Vinh Tuy bridge project phase 2 is the first project that the Chairman of the Hanoi People's Committee came to inspect and issue orders at the beginning of the year.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

After visiting and wishing New Year to the officials, engineers and workers at the project, the Chairman of the Hanoi People's Committee went up the bridge leading to the construction site and poured the main bridge piers in the middle of the Red River.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

Package 1 construction of the most complex item crossing the Red River with 4 piers crossing the river, constructed by the contractor Vietnam Construction and Import-Export Joint Stock Corporation (Vinaconex), has kept abreast of the schedule. , overcome the difficulties of the complex geological situation of the river bed to successfully overcome floods.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

Although the atmosphere of the 2022 Lunar New Year is still overwhelming throughout the country, Vinaconex contractor has concentrated human resources, machinery and construction equipment in 3 consecutive shifts, speeding up the progress.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

In order to construct the main bridge across the river and ensure technical requirements, Vinaconex contractor must use many heavy-duty barges as floating systems to drill and construct large-diameter bored piles D2000 in the river bed, then drive the piles. piles around the pier construction area.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

Through the actual inspection and assessment at the construction site, the contractor Vinaconex is performing well and meeting the set schedule. In addition, the prevention of COVID-19 epidemic is strictly implemented.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

At the construction site, leaders of Hanoi highly appreciated the efforts of the investor, consulting units, contractors and local authorities. Faced with the impact of the COVID-19 epidemic, the city wishes the relevant units to overcome difficulties, speed up the progress, and complete the project soon.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

The President of Hanoi City gave gifts and encouraged to visit Vinaconex officials and employees at Vinh Tuy bridge construction site - phase 2.

Chairman of Hanoi People's Committee highly appreciated the contractor's efforts at Vinh Tuy 2 bridge project

Vinh Tuy bridge construction project - phase 2 has particularly important significance in completing the transport infrastructure system; increase the circulation capacity between the two banks of the Red River; creating a premise for the formation of an urban chain north of the capital...

At the construction investment project of Vinh Tuy Bridge (phase 2), Vinaconex was honored to be selected as a participant in Package 05/VT2 - XL for construction of bridges and roads on Long Bien side, implementation time 18 month; Package 01/VT2 - XL for construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.


 