In the final days of 2025, construction activity at the Tuyen Quang - Ha Giang Expressway project has entered its peak phase. VINACONEX is mobilizing maximum manpower and equipment, accelerating progress to meet the target of technical opening on December 19, in line with Government directives.
The Tuyen Quang - Ha Giang Expressway is a vital link in the national transport network, helping complete the corridor connecting Hanoi with the northern border region.
At Package No.03-XL (from Km0 to Km12+500), passing through Vinh Tuy Town and the communes of Vinh Hao, Hung An and Quang Minh in Ha Giang Province, construction works are being carried out at full pace.
Package No.03-XL are being carried out at full pace
Roadbed works for K95 and K98 layers have been completed. Contractors are now focusing on laying crushed stone base course Type 1, cement-treated base, and final pavement structure. To date, nearly 6 out of 12.5 kilometers have been asphalt-paved, marking a major milestone for the package.
Roadbed works for K95 and K98 layers have been completed
Crushed stone base course Type 1, cement-treated base, and final pavement structure are now being implemented
In parallel, ancillary works such as underpass extensions and box culverts along both sides of the route are being executed simultaneously, ensuring overall progress remains synchronized and stable.
Ancillary works such as underpass extensions and box culverts are being executed at the same time
Currently, nearly 350 engineers and workers, together with more than 400 machines and pieces of equipment, are operating continuously, maintaining a high and uninterrupted construction tempo.
Nearly 350 personnel and over 400 machines are deployed around the clock to keep construction on track.
After prolonged disruption caused by severe flooding, the arrival of the dry season has facilitated the construction works. VINACONEX is making full use of time and resources to accelerate progress, demonstrating strong determination to achieve the planned technical opening.
VINACONEX workers operate in continuous shifts to meet the project schedule.
Technical staff discuss construction plans directly at the site.
The Tuyen Quang - Ha Giang Expressway plays a crucial role in promoting socio-economic development, strengthening national defense and security, enhancing regional connectivity, and gradually completing transport infrastructure in Vietnam’s northern mountainous areas.
VINACONEX is in charge of Package No.03-XL (from Km0 to Km12+500), passing through Vinh Tuy Town and the communes of Vinh Hao, Hung An and Quang Minh in Ha Giang Province
VINACONEX’s proactive and decisive engagement in this project continues to demonstrate its strong capability in delivering substantial infrastructure projects, commitment to working alongside the Government in advancing development in remote and disadvantaged regions.