OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT - Trang chủ | Vinaconex

EN

OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT

Thu , 18/05/2023, 14:00:00 (GMT+7)

Due to the significant impact of the COVID-19 epidemic and certain external factors, there has been an increase in the price of materials compared to the time of bidding. However, through relentless efforts to overcome all obstacles, Vinaconex and the contractor joint venture have managed to maintain the progress of the Ialy hydropower project. In fact, several project items are currently ahead of schedule by 1-3 months in comparison to the approved plan.

The project includes several essential items, such as the headrace tunnel with a diameter of 7 meters and a length of over 3km, as well as upper surge tank, lower surge tank, vertical shaft, penstock, etc. The construction contractors involved in the project are the joint venture of Lung Lo Construction Corporation, Truong Son Construction Corporation (Ministry of Defense), Song Da Corporation, and Vietnam Import-Export and Construction, LILAMA 10 JSC, and numerous equipment suppliers.  

OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT
The expanded Ialy hydropower plant is constructed in the area of Ya Tang commune, Sa Thay district, Kon Tum province and Ia Mo Nong, IaKreng communes, Ialy township  Chu Pah district, Gia Lai province.

As of now, the joint venture of contractors has finished installing a 14T tower crane for the water inlet and completed the concrete bottom slab up to a height of 474 meters, meeting 100% of the planned progress and adhering to the construction schedule. An important achievement was made on February 14, as Vinaconex successfully opened the headrace tunnel 90 days ahead of schedule. This was one of the most challenging items of the project. 

OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT
The units participating in the project witnessed the moment when Vinaconex broke-through the headrace tunnel of expanded Ialy hydropower plant 

The water tunnel, ranging from Km0+000 to Km0+830 (the scope of work of Vinaconex), presented numerous difficulties due to its steep slope, unfavorable geology, and multiple faults. As a result, the water flow through the large tunnel averages 50-100 liters/minute, and sometimes reaches 100-200 liters/minute in certain locations. To address this issue, General Contractor Vinaconex mobilized a large number of workers, machinery, supplies, and equipment, dividing them into two construction sectors and operating in three continuous shifts, 24 hours a day. 

OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT
The water tunnel ranging from Km0+000 to Km0+830 (the cope of work of Vinaconex), has a steep slope, poor geology, and numerous faults, causing difficulties in construction work.

The water tunnel, spanning a length of 3,308.52 meters and with a diameter exceeding 8m, posed additional complications due to the low-lying area of the Iatran stream, which exhibited unfavorable geology and numerous faults. This increased the potential risks associated with the construction work. While previous projects relied on experts from the Russian Federation, this time, Vinaconex engineers and workers undertook the entirety of this project. 
Taking into account the intricate nature of the aqueduct's geology since its early stages of construction, Vinaconex has employed numerous innovative construction techniques to tackle challenging issues, such as the utilization of machinery and equipment, combining both reinforcement and tunneling work in every tunneling sector.

OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT
Vinaconex officials and engineers have implemented advanced tunneling technologies to overcome obstacles during the construction of the Expanded Ialy Hydropower Plant. 

Alongside the ongoing construction tasks, several items have already been completed as scheduled, including the auxiliary and access tunnels, sub-tunnel 1, sub-tunnel 2, sub-tunnel 2A, sub-tunnel 2B, sub-tunnel 3, sub-tunnel 3A, water intake dyke, operation tunnel, lower and upper surge tank, T1 training walls, plant foundation pit, retaining wall TC2.

OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT
Vinaconex mobilized a large number of workers, machinery, supplies, and equipment, dividing them into two construction sectors and operating in three continuous shifts, 24 hours a day. 
OVERCOME HURDLES, AHEAD OF CONSTRUCTION SCHEDULE OF IALY HYDROPOWER PLANT EXTENSION PROJECT
Vinaconex's employees and engineers diligently carry out and oversee these items to ensure the project's quality and progress.

In addition to the project progress, quality is also of paramount importance that Vinaconex  utilizes the geological treatment options by employing modern techniques. 
Despite the challenges posed by epidemics and severe weather, the Ialy Hydropower project has now reached 60% of its output. It is anticipated that unit 1 will begin generating electricity in the second quarter of 2024, followed by unit 2 in the third quarter of the same year, with the entire project scheduled for completion by December 2024. 

 

The expanded Ialy hydropower project consists of 2 units with a total installed capacity of 360MW, and a total investment of about VND 6,398 billion. Once finalized, the project will enhance the southern region's ability to meet electricity demand, particularly during peak hours. Furthermore, it will contribute to optimizing the power system's operational efficiency and reducing production costs. Additionally, when operational, the project will alleviate the workload on existing units, thus prolonging the equipment's lifespan and reducing maintenance and repair expenses.


 

Loading...