VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE - Trang chủ | Vinaconex

EN

VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE

Thu , 04/08/2022, 23:26:00 (GMT+7)

Yen My lake overpass, with a length of about 1 km, is part of Package XL 03 - a component project of investment construction of the Nghi Son section under National Highway 45, which is being hastened by the contractor joint venture to get the works done on schedule.

Yen My lake overpass belongs to Package XL 03, a component project of the investment construction of the Nghi Son section under National Highway 45, which is implemented by the joint venture of Mien Trung Construction Group and Vietnam Construction and Import - Export Joint Stock Corporation (Vinaconex) as contractors. Particularly, Vinaconex is in charge of the 995.8-meter-long bridge's construction.

The component project of the National Highway 45-Nghi Son section under the Eastern North-South expressways passing through Nong Cong district and Nghi Son town (Thanh Hoa province), has a total length of 43.28 km with a total investment of VND 5,534,472 billion.

VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
The bridge spanning the freshwater lake bed of Yen My lake for 995.8 meters.

 

Yen My lake bridge was designed with 24 piers, 2 abutments, and 25 Super-T girders (each girder is 40 m long).

 

Due to the complex terrain, and lack of a convenient access road, the construction can only be executed from one side. Vinaconex has to carry out work including drilling piles, pouring concrete beams, pouring concrete abutments, etc. right on the lake surface using floating buoy structures.
VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
Material gathering and construction can only be done from one side.
VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
Construction work can be carried out right on the lake surface by floating buoy structures.

Since the bridge was built over Yen My Lake, one of the biggest freshwater lakes in Thanh Hoa province, which is part of the Yen My eco-tourism area (in the territory of Nong Cong district - Thanh Hoa province), environmental conservation and occupational safety have always been top priorities.

VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
The bridge has 24 piers, 2 abutments, and 25 Super-T spans (each span is 40m long).

Overcoming all obstacles, Vinaconex has attempted to organize all the human resources and equipment working on five construction sections in 24/7 shift work to accelerate the progress.

So far, the contractor Vinaconex has completed 42.7% of the required workload with a product of 103 out of 240 billion VND and has attempted to finish the bridge by June 2023.

VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
Hundreds of employees on the construction site working in shifts to speed up the project's completion.
VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
Environmental conservation and occupational safety have always been top priorities.
VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
Erecting a steel structure for concrete pouring at the project.
Once completed, the Yen My Lake Bridge would be a highlight on the entire expressway thanks to the vast lake surface and crystal-clear water, not only creating one of the most beautiful sections but also completing the architectural planning of the Yen My Lake Ecotourism Area.
VINACONEX SPEEDING UP BRIDGE CONSTRUCTION OVER YEN MY LAKE
The bridge has been the sole bridge and highlight in the Yen My eco-tourism area and Expressway project until now.
Loading...