EN

PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED

Fri , 21/03/2025, 09:00:00 (GMT+7)

On the afternoon of March 20, Prime Minister Pham Minh Chinh conducted an on-site inspection of several key transportation infrastructure projects, including Long Thanh International Airport. This marks the 7th time the PM has personally pushed for progress on the airport, emphasizing that any delays would result in leadership changes.
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
For the seventh time, PM Chinh inspected the construction site, removed obstacles, and pushed for progress of Long Thanh International Airport.
Accompanying him were Deputy Prime Minister Ho Duc Phoc, Minister of Construction Tran Hong Minh, and officials from various central and local government agencies. 
This is the 7th time that PM Pham Minh Chinh has inspected the site, identified ongoing challenges, and urged swift solutions to keep Long Thanh International Airport’s construction on track.
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
The Prime Minister emphasized the aim of essentially completing the airport by December 31, 2025, at the latest.
During the visit, Deputy Minister of Construction Pham Minh Ha reported that investors and contractors are making every effort to accelerate the construction timeline.
The PM inspected key construction items of the airport, including the passenger terminal (Package No. 5.10) and the synchronized lifting and installation of the primary steel roof structure. As of now, the package has achieved 35.36% completion.
VINACONEX, one of the contractors contributing to the terminal's construction, has been working diligently to speed up the progress. So far the main steel structure installation is 100% and 91% completed in the central and wing areas, respectively. Roof construction: 100% completion of the steel sheet roofing, with additional layers currently being installed. Skylight installation has reached 30%. Facade construction: Glass panel fabrication is at 10%, while smoke vent and aluminum louver installation stand at 18%. In March 2025, VINACONEX plans to continue installing the steel structure for the central area, constructing walls and the terminal roof, and assembling the facade system for the terminal wings.
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
The PM ordered all units involved in the project to accelerate construction at full speed, work in extra shifts, and ensure no delays in any contract package.
For Component Project No.1, the Airport Authority headquarters, customs office, immigration management department, and local police headquarters are all under construction and scheduled for operation by December 2025. The animal quarantine office is set to begin construction before May 2025, with completion expected by December 2025. 
Component Project No.2 includes the Air Traffic Control Tower and specialized facilities. The Air Traffic Control Tower has completed its structural framework, and steel structures are currently being installed at the top. It is scheduled for completion by April 30, 2025. All construction work will be finalized by June 2025, followed by the installation of specialized equipment from June to September 2025. Trial operations will be conducted from October to December 2025, with full operation expected by December 2025.
Regarding Component Project No.3, which covers civil works and equipment installation, 3 out of 14 contract packages have been completed, while 8 out of the remaining 11 are under construction. The remaining 3 packages are in the contractor selection process.
For Component Project No.4, which includes cargo terminals, warehouses, aircraft sanitation areas, ground support maintenance zones, and in-flight catering facilities, investors have already been selected, and all units have committed to completing construction by December 2025. 
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
With the highest level of commitment, the VINACONEX staff pledged to ensure safety, quality, and progress in the construction process.
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
With the highest level of commitment, the VINACONEX staff pledged to ensure safety, quality, and progress in the construction process.
Addressing the issue of construction materials (stone, sand, gravel), the PM instructed relevant ministries and local authorities to resolve the matter within the next week. He also reaffirmed that no component of the project would be delayed.  
Concluding the working session, PM Chinh emphasized the need for all units to accelerate construction at maximum speed, increase work shifts, and strive to complete the core project by December 31, 2025. 
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
The passenger terminal, symbolizing the national flower and serving as the heart of the project, is now taking clear shape. 
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
VINACONEX is honored to be responsible for constructing the eastern wing and part of the central terminal area.  
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
VINACONEX has completed 100% of the structured steel roofing and is currently installing additional roofing layers, including skylight glass panels. VINACONEX is also pioneering the installation of the terminal’s facade system.  
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
VINACONEX is the pioneer in installing facades at the project.
PRIME MINISTER ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
In March 2025, VINACONEX will continue erecting steel structures in the central area, building walls, installing the terminal roof, and assembling facade systems for the wing zones.


 

Latest news

Vinaconex chung tay hỗ trợ đồng bào miền Trung khắc phục hậu quả thiên tai, lũ lụt

Tiếp nối truyền thống tương thân tương ái của dân tộc và thực hiện trách nhiệm xã hội của doanh nghiệp, VINACONEX đã phối hợp với Ủy ban MTTQ Việt Nam tổ chức chuỗi hoạt động hỗ trợ, kịp thời sẻ chia khó khăn với người dân các tỉnh miền Trung chịu ...

Vinaconex chung tay hỗ trợ đồng bào miền Trung khắc phục hậu quả thiên tai, lũ lụt

LỄ KHỞI CÔNG KHÁNH THÀNH ĐỒNG LOẠT CÁC CÔNG TRÌNH TRỌNG ĐIỂM CHÀO MỪNG ĐẠI HỘI ĐẠI BIỂU TOÀN QUỐC LẦN THỨ XIV CỦA ĐẢNG - 19/12/2025

Sáng 19/12, đúng dịp kỷ niệm 79 năm ngày Toàn quốc kháng chiến 19/12/1946-19/12/2025 và tiến tới chào mừng Đại hội đại biểu toàn quốc lần thứ XIV của Đảng, đã diễn ra lễ khởi công, khánh thành, thông xe kỹ thuật đồng loạt 234 công trình hạ tầng ...

LỄ KHỞI CÔNG KHÁNH THÀNH ĐỒNG LOẠT CÁC CÔNG TRÌNH TRỌNG ĐIỂM CHÀO MỪNG ĐẠI HỘI ĐẠI BIỂU TOÀN QUỐC LẦN THỨ XIV CỦA ĐẢNG - 19/12/2025

VACC THÚC ĐẨY HỢP TÁC TRONG LĨNH VỰC XÂY DỰNG VỚI CÁC NHÀ THẦU HÀN QUỐC

Trong bối cảnh Việt Nam đẩy mạnh phát triển hạ tầng và mở rộng hội nhập quốc tế, Hiệp hội các Nhà thầu Xây dựng Việt Nam VACC đã tổ chức chương trình giao lưu, hợp tác với Hiệp hội Các Nhà thầu Hàn Quốc SCAK , tạo diễn đàn kết nối doanh nghiệp hai ...

VACC THÚC ĐẨY HỢP TÁC TRONG LĨNH VỰC  XÂY DỰNG VỚI CÁC NHÀ THẦU HÀN QUỐC

CAO TỐC TUYÊN QUANG – HÀ GIANG TĂNG TỐC VỀ ĐÍCH MỐC 19/12

Những ngày cuối năm 2025, trên công trường dự án cao tốc Tuyên Quang – Hà Giang, không khí thi công đang bước vào giai đoạn cao điểm. VINACONEX đang huy động tối đa nhân lực, vật lực, nỗ lực đẩy nhanh tiến độ nhằm hoàn thành mục tiêu thông xe kỹ ...

CAO TỐC TUYÊN QUANG – HÀ GIANG TĂNG TỐC VỀ ĐÍCH MỐC 19/12
Loading...