PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED - Trang chủ | Vinaconex

EN

PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED

Fri , 21/03/2025, 09:00:00 (GMT+7)

On the afternoon of March 20, Prime Minister Pham Minh Chinh conducted an on-site inspection of several key transportation infrastructure projects, including Long Thanh International Airport. This marks the 7th time the PM has personally pushed for progress on the airport, emphasizing that any delays would result in leadership changes.

PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
For the seventh time, PM Chinh inspected the construction site, removed obstacles, and pushed for progress of Long Thanh International Airport.

Accompanying him were Deputy Prime Minister Ho Duc Phoc, Minister of Construction Tran Hong Minh, and officials from various central and local government agencies. 

This is the 7th time that PM Pham Minh Chinh has inspected the site, identified ongoing challenges, and urged swift solutions to keep Long Thanh International Airport’s construction on track.

PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
The Prime Minister emphasized the aim of essentially completing the airport by December 31, 2025, at the latest.

During the visit, Deputy Minister of Construction Pham Minh Ha reported that investors and contractors are making every effort to accelerate the construction timeline.

The PM inspected key construction items of the airport, including the passenger terminal (Package No. 5.10) and the synchronized lifting and installation of the primary steel roof structure. As of now, the package has achieved 35.36% completion.

VINACONEX, one of the contractors contributing to the terminal's construction, has been working diligently to speed up the progress. So far the main steel structure installation is 100% and 91% completed in the central and wing areas, respectively. Roof construction: 100% completion of the steel sheet roofing, with additional layers currently being installed. Skylight installation has reached 30%. Facade construction: Glass panel fabrication is at 10%, while smoke vent and aluminum louver installation stand at 18%. In March 2025, VINACONEX plans to continue installing the steel structure for the central area, constructing walls and the terminal roof, and assembling the facade system for the terminal wings.

PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
The PM ordered all units involved in the project to accelerate construction at full speed, work in extra shifts, and ensure no delays in any contract package.

For Component Project No.1, the Airport Authority headquarters, customs office, immigration management department, and local police headquarters are all under construction and scheduled for operation by December 2025. The animal quarantine office is set to begin construction before May 2025, with completion expected by December 2025. 

Component Project No.2 includes the Air Traffic Control Tower and specialized facilities. The Air Traffic Control Tower has completed its structural framework, and steel structures are currently being installed at the top. It is scheduled for completion by April 30, 2025. All construction work will be finalized by June 2025, followed by the installation of specialized equipment from June to September 2025. Trial operations will be conducted from October to December 2025, with full operation expected by December 2025.

Regarding Component Project No.3, which covers civil works and equipment installation, 3 out of 14 contract packages have been completed, while 8 out of the remaining 11 are under construction. The remaining 3 packages are in the contractor selection process.

For Component Project No.4, which includes cargo terminals, warehouses, aircraft sanitation areas, ground support maintenance zones, and in-flight catering facilities, investors have already been selected, and all units have committed to completing construction by December 2025. 

PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
With the highest level of commitment, the VINACONEX staff pledged to ensure safety, quality, and progress in the construction process.
PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
With the highest level of commitment, the VINACONEX staff pledged to ensure safety, quality, and progress in the construction process.

Addressing the issue of construction materials (stone, sand, gravel), the PM instructed relevant ministries and local authorities to resolve the matter within the next week. He also reaffirmed that no component of the project would be delayed.  

Concluding the working session, PM Chinh emphasized the need for all units to accelerate construction at maximum speed, increase work shifts, and strive to complete the core project by December 31, 2025. 

PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
The passenger terminal, symbolizing the national flower and serving as the heart of the project, is now taking clear shape. 
PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
VINACONEX is honored to be responsible for constructing the eastern wing and part of the central terminal area.  
PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
VINACONEX has completed 100% of the structured steel roofing and is currently installing additional roofing layers, including skylight glass panels. VINACONEX is also pioneering the installation of the terminal’s facade system.  
PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
VINACONEX is the pioneer in installing facades at the project.
PM ORDERS LONG THANH AIRPORT COMPLETION BY DEC 31, 2025— LEADERSHIP CHANGES IF DELAYED
In March 2025, VINACONEX will continue erecting steel structures in the central area, building walls, installing the terminal roof, and assembling facade systems for the wing zones.


 

Latest news

VINACONEX lọt Top 500 doanh nghiệp lớn nhất Đông Nam Á năm 2025

Trong số 76 đại diện Việt Nam được ghi danh tại bảng xếp hạng Fortune Southeast Asia 500 năm 2025 Fortune SEA 500 , Tổng công ty CP Xuất nhập khẩu và Xây dựng Việt Nam – VINACONEX HOSE VCG lần đầu tiên góp mặt, đánh dấu bước tiến quan trọng trong ...

VINACONEX lọt Top 500 doanh nghiệp lớn nhất Đông Nam Á năm 2025

VINACONEX & SACOMBANK KÝ KẾT HỢP TÁC TÀI TRỢ TÍN DỤNG – MỞ RỘNG CƠ HỘI AN CƯ, ĐẦU TƯ TẠI VERA DIAMOND CITY

Ngày 9/7/2025, Tổng công ty CP Xuất nhập khẩu và Xây dựng Việt Nam VINACONEX và Ngân hàng TMCP Sài Gòn Thương Tín Sacombank đã chính thức ký kết thỏa thuận hợp tác tài trợ tín dụng dành cho khách hàng mua nhà tại Vera Diamond City, khu đô thị ...

VINACONEX & SACOMBANK KÝ KẾT HỢP TÁC TÀI TRỢ TÍN DỤNG – MỞ RỘNG CƠ HỘI AN CƯ, ĐẦU TƯ TẠI VERA DIAMOND CITY

VINACONEX được vinh danh Top 10 Doanh nghiệp ESG - Việt Nam Xanh 2025

Ngày 27/6/2025, tại Hà Nội, trong khuôn khổ Lễ công bố và vinh danh các doanh nghiệp ESG – Việt Nam Xanh 2025, VINACONEX tự hào được góp mặt trong Top 10 Doanh nghiệp ESG – nhóm Tổng thầu xây dựng

VINACONEX được vinh danh Top 10 Doanh nghiệp ESG - Việt Nam Xanh 2025

Khánh thành công trình Bệnh viện Đa khoa Nam Định

Ngày 25/6, tỉnh Nam Định tổ chức Lễ khánh thành công trình Bệnh viện Đa khoa Nam Định, đánh dấu bước phát triển quan trọng trong lộ trình hiện đại hóa hệ thống khám chữa bệnh, nâng cao chất lượng chăm sóc sức khỏe cho nhân dân trong và ngoài tỉnh.

Khánh thành công trình Bệnh viện Đa khoa Nam Định
Loading...