PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE - Trang chủ | Vinaconex

EN

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE

Tue , 13/02/2024, 16:00:00 (GMT+7)

On February 13, Prime Minister Pham Minh Chinh, accompanied by Deputy Prime Minister Tran Hong Ha and leaders from various central and Dong Nai provincial ministries and departments, inspected the Long Thanh airport project.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
PM Pham Minh Chinh inspected the runway item (photo: LE LAM)

During the inspection, PM Chinh inspected two pivotal components of the project—the passenger terminal and the runway. Initiated on August 31, 2023, these are the two largest, most important, and most complex items in phase 1.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Extending New Year greetings to contractors (photo: LE LAM)

Reporting to PM Chinh, leaders of the Airports Corporation of Vietnam (ACV - Investor) stated that the runway spans 4,000 meters in length and 75 meters in width, with the taxiway system (including parallel taxiways, rapid exit taxiways, and connecting taxiways) measuring 44 meters wide.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Prime Minister gave lucky money to engineers and workers at the construction site (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Runway and passenger terminal at Long Thanh Airport project (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
PM Pham Minh Chinh inspected the runway construction project (photo: LE LAM)

Immediately following the groundbreaking ceremony, the contractor joint venture swiftly mobilized thousands of personnel, along with a plethora of equipment and machinery, to expedite the project's construction. Even during the Lunar New Year, the contractors maintained a workforce of nearly 300 personnel on-site.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
The Prime Minister encouraged and motivated the staff working on the construction site (photo: LE LAM)

In the interview with Thanh Nien newspaper, Mr. Nguyen Hoai Giang, General Director of Vietnam Construction Investment Development Joint Stock Company (VINADIC), a key member of the contractor joint venture, stated that they have allocated all resources, including experts, technical staff, workers, machinery, and equipment, to meet and exceed the project schedule required by the investor.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
The runway work is going to be completed by June 2025, as stated in the plan. (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
The lotus-shaped design of the passenger terminal has gradually emerged. (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Lotus-shaped design of Long Thanh airport terminal (photo: LE LAM)

In the project, 24 tower cranes are working non-stop to handle all the materials & equipment transfers throughout the entire project site.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
PM Pham Minh Chinh visited the passenger terminal to encourage contractors and workers (photo: LE LAM).

ACV and the Contractor Joint Venture have strived to finish all construction by December 2025, completed facade installation by March 2026, and installed trial operation equipment starting in early 2026.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Deputy Prime Minister Tran Hong Ha gave lucky money to engineers and workers at the construction site of Long Thanh Airport’s passenger terminal.

The airport spans 5,000 hectares in Long Thanh district, Dong Nai province, and its phase 1 construction began in January 2021. It is expected that Long Thanh Airport would be operational by 2026, able to cater to 25 million passengers and handle 1.2 million tons of cargo each year.

(Source: thanhnien.vn)


 

Latest news

Vinaconex Phát Động Thi Đua Tại Dự Án Cảng Hàng Không Quốc Tế Long Thành

Với quyết tâm đẩy nhanh tiến độ, hoàn thành Dự án đúng kế hoạch, đảm bảo chất lượng, an toàn vệ sinh, môi trường, ngày 14/4, Tổng công ty đã tổ chức Lễ phát động thi đua tại Dự án Cảng HKQT Long Thành. Đồng chí Nguyễn Thanh Tùng, Ủy viên BCH ...

Vinaconex Phát Động Thi Đua Tại Dự Án Cảng Hàng Không Quốc Tế Long Thành

Tiến độ thi công Dự án Đường Vành đai 4 - Vùng Thủ đô

Cập nhật tiến độ thi công đến tháng 04/2024. Vinaconex vinh dự được lựa chọn là nhà thầu thực hiện gói thầu 09/TP2 – XL có chiều dài lớn nhất của dự án khoảng 23 km thuộc Dự án thành phần 2.1 Xây dựng đường song hành đường đô thị địa phận thành ...

Tiến độ thi công Dự án Đường Vành đai 4 - Vùng Thủ đô

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE

On April 5, the Vietnam Electricity Corporation EVN delegation, led by Mr. Nguyen Duc Cuong - Member of ENV's Member Board and Mr. Pham Hong Phuong, Deputy General Director, paid a visit to inspect the construction work and held a Progress ...

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE

HANOI APPROVES INVESTMENT LICENSE FOR CONSTRUCTION INVESTMENT AND INFRASTRUCTURE BUSINESS OF DONG ANH INDUSTRIAL PARK

On April 1, the Hanoi People's Committee convened a conference chaired by Vice Chairman Nguyen Manh Quyen to grant the Investment Registration Certificate for the Dong Anh Industrial Park infrastructure development and business investment project in ...

HANOI APPROVES INVESTMENT LICENSE FOR CONSTRUCTION INVESTMENT AND INFRASTRUCTURE BUSINESS OF DONG ANH INDUSTRIAL PARK
Loading...