"ALL-NIGHT SHIFTS" AT THE CONSTRUCTION SITE OF RING ROAD NO. 4 - CAPITAL REGION

Thu , 23/05/2024, 15:00:00 (GMT+7)

At the construction site of Ring Road No. 4’s Package 9, a section running through Hoai Duc district (Hanoi), reporters from VTC News observed a hectic and high-intensity working scene, with workers pushing forward on the project even late into the night. 

Nguyen Hoang Hai, the general site manager of Package No. 9 under Vinaconex contractor, explained that recent heavy rains in Hanoi had slowed progress. As soon as the weather cleared, the team ramped up efforts, working overtime through the night to make up for lost time.

Package No. 9 covers a 23-km section passing through Dan Phuong and Hoai Duc districts and has reached approximately 24% completion.

With a steady supply of sand for filling, the site now operates in three shifts around the clock to accelerate progress.

Currently, Vinaconex contractor has deployed around 200 machines and 300 workers, working continuously to meet the project’s deadlines. 

According to workers, night shifts usually run from 5 PM to 11 PM daily but can extend until 2 AM the next morning when necessary.

Many workers live on-site, eating and resting there to maintain productivity.

Nguyen Hoang Hai, the general site manager, set a goal of completing the project about six months ahead of schedule.

Numerous workers remained at the construction site, not going back home for several months.

Around 9 PM, Le Huy Hoang, the deputy commander of Package No.9’s second team, signaled a break for the workers for supper.

Workers gathered at the newly leveled construction site for a quick meal

The quick meal of bread and milk recharged the night’s labor.

Dao Quy Tham, a road roller driver, noted that while working in the cooler nighttime hours, his productivity increased, making the overtime shifts more manageable. “It’s just a small contribution, but I feel proud seeing this key project for the capital take shape,” he said.

A rare moment of rest for a worker at the construction site.

After only nine months since the groundbreaking ceremony, the shape of Hanoi’s Ring Road 4 is becoming visible. The construction team knows many more sleepless nights lie ahead as they push toward the project’s completion 6 months ahead of schedule.

The 112-kilometer Ring Road No. 4 in the Capital Region passes through Hanoi, Hung Yen, and Bac Ninh, beginning at the Hanoi - Lao Cai Expressway and ending at the Noi Bai - Ha Long Expressway. 

With a total investment exceeding VND 85,000 billion, the project broke ground in June 2023 and is scheduled for completion by 2026, with operations set to begin in 2027.

The project has seven component packages, each implemented independently. In which, Hanoi implements three component projects: Compensation, support, and resettlement; construction of parallel urban roads and investment in building a highway system under a public-private partnership (PPP) model.

Once completed, Ring Road No.4 will ease traffic congestion, enhance connectivity between provinces, and open new development opportunities for Hanoi, Hung Yen, Bac Ninh, and the broader Capital Region.

Source:  vtcnews.vn

Latest news

Hội nghị tập huấn nhận diện thương hiệu, an toàn lao động và vệ sinh môi trường năm 2026

Hưởng ứng Tháng Công nhân, Tháng hành động về An toàn, Vệ sinh lao động năm 2026, ngày 30/5/2026, VINACONEX tổ chức Hội nghị tập huấn nhận diện thương hiệu, an toàn lao động và vệ sinh môi trường năm 2026 theo hình thức trực tiếp và trực tuyến.

Hội nghị tập huấn nhận diện thương hiệu, an toàn lao động và vệ sinh môi trường năm 2026

Đẩy mạnh chuyển đổi số, tăng tốc thi công tại dự án cảng HKQT Long Thành

Cùng với việc kiểm tra thực địa và tháo gỡ khó khăn cho các đơn vị thi công, Chủ tịch HĐQT Tổng công ty yêu cầu đẩy mạnh chuyển đổi số trong công tác quản lý, điều hành dự án, xem đây là giải pháp trọng tâm để nâng cao năng suất, tối ưu nguồn lực và ...

Đẩy mạnh chuyển đổi số, tăng tốc thi công tại dự án cảng HKQT Long Thành

VIWASEEN khánh thành nhà máy nước sạch Đình Vũ

Sáng ngày 02/6/2026, tại Khu công nghiệp Đình Vũ, thành phố Hải Phòng, Tổng công ty Đầu tư Nước và Môi trường Việt Nam – CTCP VIWASEEN đã tổ chức Lễ Khánh thành Nhà máy nước sạch Đình Vũ, công suất 10.000 m³/ngày đêm.

VIWASEEN khánh thành nhà máy nước sạch Đình Vũ

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT

On May 23, 2026, Politburo member and Permanent Deputy Prime Minister Pham Gia Tuc conducted an inspection of major projects in southern Vietnam, including Long Thanh International Airport, the Ho Chi Minh City - Long Thanh - Dau Giay Expressway, and ...

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Loading...