Construction time
2019 - 2022

1. Bid Package No. DH1.7: Construction of rainwater, wastewater and tertiary sewers in Duc Ninh commune. Coastal Cities Sustainable Environment Project - Dong Hoi City Subproject.
- Project scale: Construction of rainwater, wastewater and tertiary sewers in Duc Ninh commune.
- Project location: Duc Ninh commune, Dong Hoi city, Quang Binh province.
- Construction time: from June 2019 to December 2022.

2. Bid Package No. DH1.8: Construction of rainwater, wastewater and tertiary sewers in Dong Son and Bac Nghia wards. Coastal Cities Sustainable Environment Project - Dong Hoi City Subproject.
- Project scale: Construction of rainwater, wastewater and tertiary sewers in Dong Son and Bac Nghia wards.
- Project location: Dong Son and Bac Nghia wards, Dong Hoi city, Quang Binh province.
- Construction time: from July 2019 to December 2022.

3. Bid Package No. PR-1.2: Coastal Cities Sustainable Environment Project - Phan Rang Thap Cham City Subproject.
- Project scale: “Project PR-1.2 is the construction of canals and sewers to drain rainwater and wastewater, including:
Rehabilitation of Tan Tai canal (section TT5).
Construction of Dong Nam canal.
Construction of secondary sewers in the streets of Thong Nhat - Vo Thi Sau - Ngo Gia Tu - Hai Thuong Lan Ong.
Construction of culverts along Tan Tai canal (section TT5).
Construction of pumping stations, combined sewer overflows, pressure culverts.”
- Project location: Phan Rang Thap Cham city, Ninh Thuan province.
- Construction time: from December 2020 to December 2022.
- Joint venture of Viet Nam Construction Joint Stock Company No. 12 and VINACONEX Corporation.