- Value of implementation: 71,825,048,749 VND
- Location: Ninh Hoa town, Khanh Hoa province
- Time to start and end: 11/2011-05/2013
- Details: Construction of Ninh Hoa Town Water Supply System Belongs to the project of developing small and medium-sized cities - the central region - Ninh Hoa sub-project is implemented under contract H5/A/10/ICB Civil works and equipment for water supply system in Ninh Hoa town.
The scale of the project includes: Raw water pumping station, raw water pipeline, sedimentation treatment cluster, conveying pipeline, and distribution pipeline with the total length of the pipeline from D 100 to D 300 is 30,835 meters. Design capacity 4.130m3/day/night. Total value of construction and installation is 71 billion VND (of phase I).
Construction items include:
- Construction of raw water pumping station at the foot of Da Ban dam.
- Construction of raw water pipeline from Da Ban lake to treatment station, total length of 5 km.
- Build a clean water treatment station of 4,000 m3/day.
- Clean water distribution and transmission pipeline with a total length of 26.6km