The starting point at Km405+000 connecting to package no. XL02 (at Km389+900 – Km405+00) in Quynh Luu district, Nghe An province.
The ending point at Km419+600 connection to package no. XL04 (at Km419+600 – Km430+00) in Yen Thanh district, Nghe An province.
Contract value (joint venture): VND 1,266,466,753,190
Contract value (VINACONEX in charge): VND 886,707,774,148
At the complete stage, the section would have six lanes with a design speed of 100-120kph; During Phase 1: the section would have fours lanes with a design speed of 80kph
The section is 14.6 kilometers long in total.