VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2 - T...

EN

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2

Thu , 13/02/2025, 18:00:00 (GMT+7)

The joint venture of 7 construction contractors including Lung Lo Construction Corporation, Song Da Corporation, Truong Son Construction Corporation, VINACONEX (VCG), LILAMA 10 (L10), SCI E&C (SCI), and Construction Joint Stock Company 47 has just secured the main construction package at the first pumped storage hydropower project in Vietnam, with a total package value of more than VND 4,300 billion.

On February 13, 2025, the contract signing ceremony for Package 02XL-BA of the Bac Ai Pumped Storage Hydropower Plant Project Phase 2 (Stage 1) was held at the headquarters of Vietnam Electricity (EVN). 
The event brought together representatives from Commission for the Management of State Capital at Enterprises, the Ministry of Industry and Trade, EVN leadership, Vietnam Electricity Power Projects Management Board No.3 leadership and the joint venture of contractors for package No. 02XL-BA.

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
EVN and the joint venture of contractors signed the construction contract for the Bac Ai pumped storage hydropower plant - phase 2, stage 1
VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2

Following an open domestic bidding process conducted online, a joint venture of leading construction contractors including Lung Lo Construction Corporation, Song Da Corporation, LILAMA 10 Joint Stock Company, SCI E&C Joint Stock Company, Construction Joint Stock Company 47, Truong Son Construction Corporation, and Vietnam Construction and Import-Export Joint Stock Corporation (VINACONEX), secured the contract for Package No. 02XL-BA, valued at VND 4,334 billion. 

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
Overview of the contract signing ceremony

These are all experienced contractors in implementing many key energy projects in Vietnam, particularly Song Da Corporation, a key player in major hydropower developments, including Son La Hydropower - the largest hydropower project in Southeast Asia, Hoa Binh HPP, Lai Chau HPP, etc. Besides, Lung Lo Construction Corporation has also established itself as a vital force in hydropower and irrigation, with approximately 55% of its annual revenue from these critical sectors. Regarding VINACONEX, as a contractor, investor and manager - operator, has successfully executed several hydropower projects, including Cua Dat HPP (Thanh Hoa), Buon Kuop HPP, Buon Tua Sha HPP, Ngoi Phat HPP (Lao Cai), Dak Ba HPP (Quang Ngai).
Package No. 02XL-BA is the main construction package of the project with key components of the project include the construction and installation of pressure tunnels, upstream surge tank, underground powerhouse, 500kV switchyard, discharge tunnel, lower surge tank, and lower valve chamber; underground tunnels and adits; access roads for construction and operation; 22kV power supply system, water supply system for construction and domestic use; auxiliary facilities, worker camps and offices.
The contract implementation period is about 81 months, in which Unit No. 1 is scheduled to begin operations in December 2029, followed by Unit No. 2 in April 2030, Unit No. 3 in August 2030, Unit No. 4 in December 2030 and the entire contract is expected to be completed in May 2031.

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
According to EVN Deputy General Director Pham Hong Phuong, the Bac Ai Pumped Storage Hydropower Plant is the first pumped storage hydropower project to be built in Vietnam and is one of EVN's key projects to be implemented in 2025

Located in Ninh Thuan province, it has a planned capacity of 1,200 MW, featuring 4 turbine/pump-generator/engine units, each generating 300 MW. The total investment of the Bac Ai pumped storage hydropower project is about VND 21,100 billion, sourced from loans and EVN’s allocated funds.

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
Director of Vietnam Electricity Power Projects Management Board No.3 spoke at the ceremony

According to the representative of EVN, the project, backed by the Government, the Ministry of Industry and Trade, Commission for the Management of State Capital at Enterprises and local authorities in Ninh Thuan, has received unwavering support at every stage—from meticulous planning and contractor selection to the enforcement of safety, progress and quality standards. 

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
Chairman of VINACONEX’s Board of Directors - Mr. Nguyen Huu Toi and representatives of contractors attended the signing ceremony
VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
The representative of the Contractor joint venture committed to delivering the Bac Ai HPP on schedule, meeting quality standards, safety and efficiency.

Expressing honor at being entrusted with this nationally significant project, the representative of the joint venture pledged to mobilize all necessary resources to meet the project timeline and support Vietnam’s sustainable energy goals.

VINACONEX AND THE JOINT VENTURE SECURE VND 4,300 BILLION CONSTRUCTION CONTRACT FOR BAC AI HYDROPOWER PROJECT PHASE 2
The Contractor Consortium committed to constructing the package to ensure safety, quality and progress, contributing to the project's completion on schedule.

As the first pumped storage hydropower plant in Vietnam, the Bac Ai HPP holds both economic and strategic importance. Designed to store and regulate energy, it will help stabilize the national power grid, mitigate electricity shortages during peak demand periods, and strengthen energy security. The project is a cornerstone of Vietnam’s renewable energy strategy, playing a vital role in advancing the country’s transition toward a more sustainable and resilient energy future. 

Latest news

Công đoàn Xây dựng Việt Nam trao quà động viên người lao động tại dự án mở rộng nhà ga quốc tế T2 Nội Bài

Hưởng ứng Tháng Công nhân và Tháng Hành động về An toàn, vệ sinh lao động năm 2025, đoàn công tác của Công đoàn xây dựng Việt Nam đã tới thăm hỏi, động viên và trao quà cho người lao động VINACONEX tại dự án mở rộng nhà ga quốc tế T2 Nội Bài

Công đoàn Xây dựng Việt Nam trao quà động viên người lao động tại dự án mở rộng nhà ga quốc tế T2 Nội Bài

Vành đai 4 – Vùng Thủ đô: Phấn đấu hoàn thành đường song hành vào cuối năm 2025

Tiến độ thi công tổng thể các dự án thành phần đường song hành dự án đầu tư xây dựng Vành đai 4 – Vùng Thủ đô đến nay cơ bản bám sát kế hoạch đã đề ra. Các đơn vị chủ đầu tư và nhà thầu phấn đấu hoàn thành phần đường song hành vào tháng 10 năm 2025, ...

Vành đai 4 – Vùng Thủ đô: Phấn đấu hoàn thành đường song hành vào cuối năm 2025

VINACONEX đồng hành cùng Viettel tại dự án Trung tâm dữ liệu lớn nhất Việt Nam

Sáng ngày 21/4/2025, Tổng công ty CP VINACONEX đã tổ chức thành công Đại hội đồng cổ đông thường niên năm 2025. Với sự đồng thuận rất cao, Đại hội đã thông qua kết quả SXKD năm 2024 và kế hoạch SXKD năm 2025 với các chỉ tiêu doanh thu, lợi nhuận dự ...

VINACONEX đồng hành cùng Viettel tại dự án Trung tâm dữ liệu lớn nhất Việt Nam

CẢNH GIÁC TRƯỚC CHIÊU TRÒ GIẢ MẠO THƯƠNG HIỆU VINACONEX ĐỂ LỪA ĐẢO CHIẾM ĐOẠT TÀI SẢN (KHUYẾN CÁO LẦN 5)

Trong thời gian vừa qua, Tổng công ty cổ phần Xuất nhập khẩu và Xây dựng Việt Nam “VINACONEX” đã phát hiện và tiếp tục nhận được nhiều phản hồi thông tin về hành vi của các đối tượng xấu giả mạo VINACONEX hoặc nhân viên của VINACONEX để thực hiện ...

CẢNH GIÁC TRƯỚC CHIÊU TRÒ GIẢ MẠO THƯƠNG HIỆU VINACONEX ĐỂ LỪA ĐẢO CHIẾM ĐOẠT TÀI SẢN (KHUYẾN CÁO LẦN 5)
Loading...