VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE

Fri , 05/04/2024, 18:00:00 (GMT+7)

On April 5, the Vietnam Electricity Corporation (EVN) delegation, led by Mr. Nguyen Duc Cuong - Member of ENV's Member Board and Mr. Pham Hong Phuong, Deputy General Director, paid a visit to inspect the construction work and held a Progress Conference in the first quarter of 2024 on the construction site of Ialy Hydropower Plant Extension Project.

The delegation included controllers, professional departments of EVN, leaders from Power Project Management Board No. 2 (EVNPMB2), contractors, and consulting, monitoring, and equipment supply units.

Representing Vinaconex – contractor of project construction was Mr. Pham Thai Duong, Director of Project Management Board No. 1.

During the conference, Deputy Director of EVNPMB2 Nguyen Duc Minh reported that thanks to the diligent supervision and efforts of the contractors, many construction items have been completed to date, meeting and even surpassing the schedule.

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE
Deputy Director of EVNPMB2 Nguyen Duc Minh provided a report on the construction progress of the project

By the first quarter of 2024, key items such as headrace tunnel, penstock, water intake excavation and reinforcement, have been completed as scheduled, following the operation process of Ialy Hydropower reservoir. The equipment supply remains on track.

Mr. Pham Thai Duong, Director of Project Management Board No. 1 representing Vinaconex contractor, reported progress on the package no. 37 “Construction and installation of Ialy Hydropower Plant Extension project”. During the first quarter of 2024, significant progress was achieved on Excavation faces no. 1 and 2 (from Water intake to Km0+830) reinforced concrete construction items, including Reinforced concrete work on the tunnel shell reaching 236 md/171 md, exceeding schedule by 38%; Reinforced concrete work on the headrace tunnel completed at 830 md/830 md; consolidation grouting along the entire route reaches 5340 md/5628 md, equal to 95% completion; curtain grouting reaches 513 md/830 md, equal to 62% completion. For the second quarter, Vinaconex aims to complete the remaining grouting works, resolve legal issues, and finalize completed construction items.

Vinaconex has fully deployed human and material resources at the construction site, operating in three shifts with four crews, ensuring round-the-clock progress toward completing the project as scheduled.

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE
Vinaconex Contractor is determined to speed up progress and complete the package and project on schedule.
Furthermore, the contractors outlined the challenges and proposed solutions to accelerate construction and installation processes to meet the investor's timeline. Acknowledging the efforts of EVNPMB2 and the participating contractors, the delegation requested the equipment installation unit to allocate sufficient manpower at the construction site for timely installation, as well as requested close collaboration between the supervision team and Project Management Board for equipment acceptance and installation, etc.
VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE
EVN Deputy General Director Pham Hong Phuong and the working group evaluated the construction progress at the headrace tunnel.

To commission 2 power units by the end of 2024, Power Project Management Board 2 must continue prioritizing guidance, operation, and contractor coordination to expedite essential project components' construction according to the schedule. It's imperative to effectively coordinate on-site forces to ensure the execution of safety, fire prevention, natural disaster prevention, and environmental protection tasks.

To meet the target of generating 2 power units by the end of 2024, EVNPMB2 shall persist in prioritizing contractor guidance, operation, and coordination for timely construction of crucial components of the project. Besides, it is necessary to coordinate and direct on-site forces for the efficient execution of safety, fire prevention, natural disaster prevention, and environmental protection tasks.

VINACONEX'S COMMITMENT: DELIVERING IALY HYDROPOWER PLANT PROJECT AHEAD OF SCHEDULE
Vinaconex engineers and workers are committed to ensuring labor and technical safety during the construction process, in order to complete the package and project on schedule.
Funded by Vietnam Electricity Corporation (EVN) with an investment of nearly VND 6.4 trillion, Ialy Hydropower Plant Extension Project spans Ya Tang commune, Sa Thay district, Kon Tum province, and Ia Mo Nong commune, Ia Kreng commune, Ialy town, Chu Pah district, Gia Lai province.
The project, comprising 2 units with a total capacity of 360MW (each unit at 180MW), commenced construction in June 2021, aiming to start generating electricity by the fourth quarter of 2024. Managed by main contractors Vinaconex, Lung Lo Construction Corporation, Truong Son Construction Corporation, Song Da Corporation, LILAMA 1 JSC, the project engages over 700 employees and modern machinery and equipment working round-the-clock in 3 shifts and 4 crews, all committed to achieving timely project completion.

Latest news

Phó Chủ tịch UBND TP Hà Nội chúc Tết công nhân thi công Vành đai 4

Kinhtedothi - Sáng 24/11, Phó Chủ tịch UBND TP Hà Nội Dương Đức Tuấn đã đến kiểm tra tiến độ, thăm, chúc Tết và tặng quà động viên các công nhân viên, người lao động đang làm việc trên công trường Dự án đường Vành đai 4 tại Hà Nội.

Phó Chủ tịch UBND TP Hà Nội chúc Tết công nhân thi công Vành đai 4

10 DẤU ẤN NỔI BẬT CỦA VINACONEX TRONG NĂM 2024

Bước sang năm 2024, năm bản lề, chuyển mình của giai đoạn mới, dưới sự chỉ đạo, lãnh đạo toàn diện của Đảng uỷ TCT, sự quyết liệt trong công tác quản trị, điều hành của HĐQT và Ban Tổng giám đốc, VINACONEX xác định đẩy mạnh hơn nữa công tác nghiên ...

10 DẤU ẤN NỔI BẬT CỦA VINACONEX TRONG NĂM 2024

Tổng kết hoạt động SXKD năm 2024 và định hướng triển khai nhiệm vụ năm 2025

Năm 2024, đối mặt với vô vàn thách thức, VINACONEX vẫn vững vàng vượt khó, tăng trưởng quy mô và duy trì hoạt động hiệu quả trên cả ba trụ cột là Xây dựng – Bất động sản – Đầu tư tài chính, tích cực đóng góp nhiều hơn nữa vì cộng đồng.

Tổng kết hoạt động SXKD năm 2024 và định hướng triển khai nhiệm vụ năm 2025

Hội nghị tổng kết công tác Đảng, Công đoàn, Đoàn thanh niên Tổng công ty năm 2024; triển khai nhiệm vụ trọng tâm năm 2025

Ngày 17/01/2025, Tổng công ty đã tổ chức Hội nghị Tổng kết công tác Đảng, hoạt động Công đoàn, Đoàn Thanh niên năm 2024 và triển khai nhiệm vụ trọng tâm năm 2025. Đ/c Đồng chí Đào Ngọc Thanh, Bí thư Đảng ủy chủ trì, điều hành hội nghị.

Hội nghị tổng kết công tác Đảng, Công đoàn, Đoàn thanh niên Tổng công ty năm 2024; triển khai nhiệm vụ trọng tâm năm 2025
Loading...