STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY

Wed , 20/03/2024, 14:00:00 (GMT+7)

That is the commitment of Vinaconex contractor at the inspection conducted on the morning of March 20 by Deputy Minister of Transport Nguyen Duy Lam and his working delegation.
Accompanying the Deputy Minister were Pham Chien Thang, Executive Director of the Bai Vot - Ham Nghi Expressway Project (managed by Thang Long Project Management Board), representatives from construction units and other related parties.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
Deputy Minister of Transport Nguyen Duy Lam inspected the progress of the North-South expressway, the section passing through Ha Tinh province
Representing Vinaconex, the contractor participating in the project construction was Director of Project Management Unit No.1 Pham Thai Duong.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
Deputy Minister of Transport Nguyen Duy Lam oversaw the construction progress at Bai Vot - Ham Nghi expressway.
After over a year of urgent construction, the units have excavated 1.0/1.6 million m3 of the main road base, which is 65% complete; K95 soil embankment has reached 1.1/4.6 million m3 (24% complete); The project has finished installing wick drains in all relevant sections, completed 72% of sand drain installations, and reached 75% completion for soil-cement column treatments. Besides, work is progressing at 24 out of 25 bridge locations, 28 out of 48 culverts and underpasses along the route. Bored pile construction for bridges is nearly finished, with simultaneous work on beam casting, component assembly, and substructure.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
The contractor strives to complete the construction before schedule, ensuring that the National Highway no. 8A intersection opens in June 2024
Vinaconex contractor has recently deployed a maximum number of human resources, equipment, and machinery, in an attempt to speed up the construction progress of the National Highway 8A intersection adjacent to the Dien Chau - Bai Vot expressway project, which is expected to open to traffic in June 6.
“So far, Vinaconex is confident in completing the intersection's items before June 30; completing the main route by April 2024, and ensuring traffic opening by June 4” - said Mr. Pham Thai Duong, Director of PMU 1.
Deputy Minister Nguyen Duy Lam and the delegation commended the project investors and contractors for their dedication. Despite initial obstacles, the project has begun speeding up, aiming to expedite progress by 3 to 6 months compared to the contract. Contractors are urged to intensify efforts, mobilizing additional human and equipment resources while implementing efficient construction methods to ensure progress across all packages of the project. 
The Bai Vot - Ham Nghi project has a total length of 35.28 kilometers, starting at Km479+117.18 in Thanh Binh Thinh commune, Duc Tho district, Ha Tinh province, and ending at Km514+441.33 in Thach Xuan commune, Thach Ha district, Ha Tinh province. With a total investment of VND7,643 billion, the project commenced on January 1, 2023, implemented by a joint venture of Vietnam Construction and Import-Export Corporation (Vinaconex) and 319 Corporation Ministry Of National Defence. 

Latest news

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

38 năm hình thành và phát triển là hành trình được tạo nên bởi bản lĩnh, trí tuệ, sự bền bỉ và tinh thần đoàn kết của nhiều thế hệ người lao động VINACONEX. Từ những giá trị được vun đắp qua năm tháng, Tổng công ty hôm nay tiếp tục đổi mới, nâng cao ...

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

Tổng công ty CP VINACONEX vừa tiếp nhận lô thiết bị máy khoan cọc nhồi SANY SR235 và SANY SR285R, bổ sung nguồn lực thiết bị hiện đại, góp phần nâng cao năng lực thi công nền móng và tăng tính chủ động trong triển khai các dự án quy mô lớn.

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

KHỞI CÔNG CỤM CÔNG NGHIỆP SƠN ĐÔNG - Không gian sản xuất mới phía Tây thủ đô

Hướng tới chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX, ngày 17/9/2026, Cụm công nghiệp Sơn Đông đã chính thức được khởi công tại xã Đoài Phương, TP. Hà Nội, mở thêm không gian sản xuất tập trung, hiện đại phía Tây Thủ đô.

KHỞI CÔNG CỤM CÔNG NGHIỆP SƠN ĐÔNG - Không gian sản xuất mới phía Tây thủ đô

JICA và FiinGroup thăm và làm việc tại VINACONEX

Sáng 11/9/2026, Đoàn công tác Cơ quan Hợp tác Quốc tế Nhật Bản JICA và Công ty Cổ phần FiinGroup Việt Nam đã đến thăm và làm việc tại Tổng công ty CP VINACONEX, trao đổi về các cơ chế hỗ trợ tài chính và khả năng hợp tác trong thời gian tới.

JICA và FiinGroup thăm và làm việc tại VINACONEX
Loading...