INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL

Fri , 30/08/2024, 10:03:00 (GMT+7)

The joint venture of contractors is currently working on the steel frame roof for Phase 1 of Long Thanh International Airport, a critical component of the Long Thanh Airport project, which has the largest amount of capital funding in Vietnam. Nhan Dan Newspaper reporters captured the bustling construction activity at the Long Thanh Airport mega construction site today, August 29. 

INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
According to a representative from the Airports Corporation of Vietnam (ACV), the steel roof structure for the passenger terminal is valued at around VND 3.5 trillion, accounting for approximately 10% of the total contract value for the terminal project.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The construction requires about 32,000 tons of steel for the roof frame of Long Thanh Airport passenger terminal phase 1.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Workers and engineers lifted steel structures to install the roof of the Long Thanh Airport passenger terminal.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Workers carried out the assembly process after the steel components had been transported to the roof site.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Installation is progressing on the steel frame for the terminal's two wings, with completion of the main roof structure expected by this September. 
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The passenger terminal is considered the “heart” of Long Thanh Airport Phase 1. In addition to the steel roof installation, the construction units are constructing the terminal's concrete floor and main pillars.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Meanwhile, Package no.4 & 6, which covers the runway runway and the aircraft parking lot is under construction of the finishing concrete layer.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Long Thanh Airport runway package is expected to be completed by April 30, 2025, three months ahead of schedule.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Control Tower project, part of Component No. 2 and invested by the Vietnam Air Traffic Management Corporation, is also under accelerated construction.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
According to ACV, the first phase of Long Thanh International Airport is expected to be completed and enter trial operations before August 31, 2026, and is scheduled to welcome its first commercial flight on September 2, 2026.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Long Thanh Airport project, located in Long Thanh District, Dong Nai Province, is a major national investment, with a total estimated cost exceeding $16 billion, divided into three phases. Phase 1 alone represents over $5.4 billion in investment.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Long Thanh Airport project, located in Long Thanh District, Dong Nai Province, is a major national investment, with a total estimated cost exceeding $16 billion, divided into three phases. Phase 1 alone represents over $5.4 billion in investment.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Long Thanh Airport Phase 1 is a key national project critical to the country's socio-economic development. It includes the construction of 1 runway, 1 passenger terminal, and auxiliary works capable of handling 25 million passengers and 1.2 million tons of cargo annually.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Upon completion of all three phases, Long Thanh Airport is expected to accommodate up to 100 million passengers per year, becoming the largest airport in Vietnam and aiming to become one of the centers of international aviation hubs in the region.

Source: nhandan.vn

Latest news

Phó Thủ tướng Thường trực Chính phủ Phạm Gia Túc thăm và kiểm tra tiến độ dự án cảng HKQT Long Thành

Ngày 23/5/2026, Ủy viên Bộ Chính trị, Phó Thủ tướng Thường trực Chính phủ Phạm Gia Túc đã kiểm tra tình hình triển khai các dự án trọng điểm phía Nam, bao gồm dự án Cảng hàng không quốc tế Long Thành, dự án cao tốc TPHCM-Long Thành-Dầu Giây và tình ...

Phó Thủ tướng Thường trực Chính phủ Phạm Gia Túc thăm và kiểm tra tiến độ dự án cảng HKQT Long Thành

Khởi công Khu công nghiệp Đông Anh, kiến tạo không gian công nghiệp thế hệ mới

Sáng 20/5, Vinaconex phối hợp cùng UBND TP Hà Nội tổ chức lễ khởi công Dự án đầu tư xây dựng và kinh doanh kết cấu hạ tầng Khu công nghiệp Đông Anh.

Khởi công Khu công nghiệp Đông Anh, kiến tạo không gian công nghiệp thế hệ mới

VINACONEX khởi công Khu công nghiệp Đông Anh – Kiến tạo không gian công nghiệp thế hệ mới phía Bắc Thủ đô

Khu công nghiệp Đông Anh quy mô gần 300ha, tổng mức đầu tư hơn 6.300 tỷ đồng sẽ được VINACONEX phát triển theo mô hình khu công nghiệp thế hệ mới sinh thái – thông minh – công nghệ cao, kỳ vọng trở thành động lực tăng trưởng mới phía Bắc Thủ đô và ...

VINACONEX khởi công Khu công nghiệp Đông Anh – Kiến tạo không gian công nghiệp thế hệ mới phía Bắc Thủ đô

HỘI NGHỊ RÀ SOÁT, BỔ SUNG QUY HOẠCH CÁC CHỨC DANH CẤP UỶ ĐẢNG BỘ TỔNG CÔNG TY VINACONEX NHIỆM KỲ 2025 - 2030

Thực hiện Kế hoạch số 32-KH/ĐU của Đảng uỷ phường Láng, ngày 15/5/2026, Đảng uỷ Tổng công ty CP VINACONEX tổ chức Hội nghị rà soát, bổ sung quy hoạch các chức danh cấp uỷ Tổng công ty nhiệm kỳ 2025 - 2030. Đồng chí Trần Đình Tuấn – Phó Bí thư Đảng uỷ ...

HỘI NGHỊ RÀ SOÁT, BỔ SUNG QUY HOẠCH CÁC CHỨC DANH CẤP UỶ ĐẢNG BỘ TỔNG CÔNG TY VINACONEX NHIỆM KỲ 2025 - 2030
Loading...