GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE

Thu , 05/03/2026, 16:07:00 (GMT+7)

On March 4, 2026, the Airports Corporation of Vietnam (ACV), in collaboration with the Lam Dong Provincial People's Committee, held a groundbreaking ceremony for “the Runway and Taxiway Rehabilitation Project at Lien Khuong International Airport”. VINACONEX is honored to participate as the contractor for Package No. 9, covering construction and equipment supply and installation.
The ceremony was attended by representatives from central government agencies, the Lam Dong Provincial People's Committee, the Airports Corporation of Vietnam (ACV), contractors, and other stakeholders.
Representing VINACONEX at the event was Mr. Pham Thai Duong, Deputy General Director of the Corporation and Director of Project Management Board No. 1.

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE

Mr. Pham Thai Duong, Deputy General Director and Director of Project Management Board No. 1 (first from left), joins delegates in the groundbreaking ceremony

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE
The ceremony brought together representatives from central agencies, Lam Dong provincial leadership, investor ACV, contractors, and other stakeholders

In his remarks, Mr. Nguyen Cao Cuong, Deputy General Director of ACV, emphasized the critical need to upgrade Lien Khuong Airport. He noted that the project demonstrates a strong commitment to enhancing operational safety and ensuring the sustainable development of this international airport in Lam Dong and the wider region.

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE
Mr. Nguyen Cao Cuong, Deputy General Director of ACV, addresses the groundbreaking ceremony

The Lien Khuong International Airport project is a Grade I aviation infrastructure undertaking with a total investment of VND 1,032 billion. The scope includes complete repair of the runway, taxiways, runway end safety areas, and technical infrastructure systems supporting flight operations.

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE

Lien Khuong International Airport serves as a vital transportation artery, driving socio-economic development in Lam Dong province and the Central Highlands region

With the vision of “Enhancing Operational Capacity - Connecting the Future”, the project not only restores the airfield's structural integrity but also serves as a strategic stepping stone toward realizing the master plan for Lien Khuong International Airport to achieve 4E classification, capable of accommodating modern wide-body aircraft such as the Airbus A350 and Boeing 787. This lays a solid foundation for reaching 5 million passengers annually by 2030 and 7 million passengers by 2050.
To facilitate construction, Lien Khuong International Airport will suspend all operations from 00:00 on March 4, 2026, to 23:59 on August 25, 2026.
Drawing on extensive experience implementing large-scale infrastructure projects, VINACONEX is committed to working closely with the investor and relevant parties, mobilizing resources to ensure timely, high-quality, and safe construction. VINACONEX aims to contribute to the early commissioning of the upgraded facility, boosting economic and tourism development in Lam Dong province and the Central Highlands region.

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE

VINACONEX is honored to participate in Package No. 9 “Construction and equipment supply and installation for the Lien Khuong International Airport runway and taxiway repair project”

 

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE

Equipment and machinery are mobilized at the groundbreaking ceremony, ready for the Lien Khuong International Airport upgrade project

GROUNDBREAKING HELD FOR LIEN KHUONG INTERNATIONAL AIRPORT UPGRADE

To facilitate construction, Lien Khuong International Airport will suspend all operations from 00:00 on March 4, 2026, to 23:59 on August 25, 2026.

 

 

 

 

 

 

 

 

 

Latest news

VINACONEX tiếp tục thăng hạng trong Top 500 doanh nghiệp lớn nhất Đông Nam Á năm 2026

VINACONEX tiếp tục ghi dấu ấn trên bản đồ doanh nghiệp khu vực khi được xếp vị trí 402 trong Bảng xếp hạng 500 doanh nghiệp lớn nhất Đông Nam Á năm 2026, tăng 32 bậc so với năm trước. Đây là là bảng xếp hạng được công bố thường niên bởi tạp chí ...

VINACONEX tiếp tục thăng hạng trong Top 500 doanh nghiệp lớn nhất Đông Nam Á năm 2026

VINACONEX đón đoàn sinh viên thực tập lớp K67 kỹ sư hạ tầng - Đại học Xây dựng Hà Nội

Khóa sinh viên đầu tiên được đào tạo chuyên ngành Kỹ thuật công trình hạ tầng theo nhu cầu doanh nghiệp, đoàn sinh viên lớp K67 Kỹ sư hạ tầng – Chương trình Kỹ sư Chất lượng cao của Trường Đại học Xây dựng Hà Nội sẽ bắt đầu chương trình thực tập tại ...

VINACONEX đón đoàn sinh viên thực tập lớp K67 kỹ sư hạ tầng  - Đại học Xây dựng Hà Nội

VINACONEX tăng tốc thi công cao tốc Hòa Bình

Với tinh thần trách nhiệm và quyết tâm cao nhất, cán bộ, kỹ sư và người lao động VINACONEX đang ngày đêm bám sát công trường, duy trì tiến độ tích cực, phấn đấu đưa cao tốc Hoà Bình - Mộc Châu về đích đúng kế hoạch.

VINACONEX tăng tốc thi công cao tốc Hòa Bình

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Ngày 24-6, phường Láng tổ chức Hội nghị công bố quyết định chuyển giao, tiếp nhận tổ chức Đảng và đảng viên đối với Đảng bộ Tổng công ty Đầu tư nước và Môi trường Việt Nam Viwaseen . Sự kiện đánh dấu một bước đi cụ thể nhằm kiện toàn tổ chức, tăng ...

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam
Loading...