CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY - Trang chủ | Vinaconex

EN

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

Wed , 30/08/2023, 18:10:00 (GMT+7)

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

On the morning of August 30, the Vinh Tuy 2 bridge across the Red River in Hanoi was officially opened to traffic. In photo: Prime Minister Pham Minh Chinh and other leaders of the Central and Municipal Committee were present for the ribbon-cutting ceremony.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
This project has garnered appreciation from Government leaders, as it not only surpassed the expected completion timeline by 4 months but also remained within the allocated budget. However, what few people are aware of is the challenging journey that the contractor had to endure during the construction process regardless of the scorching sun and relentless rain.
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
The Vinh Tuy bridge construction project phase 2 (Vinh Tuy 2 bridge) had a total investment of over VND 2,500 billion and was managed by the Construction Investment Project Management Board of Traffic Works and the Hanoi People's Committee.
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
 Commencing its construction in January 2021 during the height of the COVID-19 epidemic and social distancing measures, all 5 bidding packages were implemented simultaneously with great enthusiasm on the mega construction site.
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

Out of the 5 bidding packages, the construction package for the main span of the bridge over the river stands out as the most complex and important one. To build the main bridge, the contractors had to use multiple barges that served as a floating road, deploying excavators and cranes to excavate and drill in the river bed, as well as installing sheet piles around the perimeter of the foundation work. The main span crossing the river has a total of 4 concrete piers located on the riverbed and 2 other piers on each side, bordering the banks.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

At the construction site, there were 11 contractors working on 11 different construction sections. The entire site had over 500 engineers, technical staff, and construction workers, working in shifts and crews around the clock.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

By July 2021, the Covid-19 pandemic had become complicated and prolonged. The cost of materials, especially iron and steel, increased by 40% from the initial estimate, causing difficulties in resource mobilization and progress for the project.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

Reflecting on that time, Mr. Pham Van Tan, the representative of the supervision consultant unit for package No. 1, stated that Package No. 1, commencing in May 2021, was the most complicated item of the Vinh Tuy 2 Bridge project. It involved constructing 4 bridge piers spanning the Red River bed.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

The project involves building 4 piers over the Red River. For each pier, the contractor needed to move 24 steel casing pipes with a diameter of D1,200 using barges. The Red River has a depth of 12m and a fast flow. To work in these conditions, the contractor used large casings to drive into the river bed and then filled with concrete to create sturdy bored piles. By December 2021, after all the bored pile items were done, the contractor started working on the pile footings and part of the pier at the same time to ensure the project would be completed on schedule, before the rainy season.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

The Red River bed’s geological conditions are intricate, with lots of changes in the river's morphology. In light of this, the construction units, who are renowned nationwide for their expertise in building bridges and roads, are well-prepared for the challenges and uncertainties that may arise during the construction process. They've arranged a highly skilled team in place to handle the construction of the section over the river.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

The Vinh Tuy 2 bridge has been built right next to Vinh Tuy 1 bridge, necessitating limitations on the materials and equipment hoisting in the river to ensure safety and minimize any impact on the initial bridge. 

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

Additionally, the construction beneath and in the Red River which has a lot of waterway traffic was also a safety issue. However, the construction units have taken steps to regulate and ensure the safety of waterway traffic, mitigating the possibility of collisions with boats.
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY Mr. Pham Van Luong, the representative from Vinaconex contractor (package No. 1), mentioned that the construction site on the river was executed during the hottest time of the year, resulting in an extremely hot working environment. During the winter, the workers had to face tough conditions due to the strong and cold wind on the river.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

On the morning of May 30, the final section of Vinh Tuy 2 Bridge crossing Red River was successfully joined, marking a significant milestone for the project.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

Vinh Tuy Bridge - Phase 2 connects two cantilever bridge girders on the banks of Hai Ba Trung district and Long district, completing the main girder across the Red River and the entire bridge from the right bank to the left bank.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

Under the scorching summer sun, workers were constructing asphalt concrete pavement for the bridge deck to ensure the project's progress.

CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY
CONSTRUCTING THE VINH TUY 2 BRIDGE: A CHALLENGING JOURNEY

The project was carried out entirely by Vietnamese engineers and workers, using advanced construction techniques and technologies saving about 1.5 years compared to the construction of Vinh Tuy bridge - phase 1. That success demonstrates the outstanding expertise of the engineers and workers involved and provides valuable lessons for contractors in future public investment projects.
 

Follow by baogiaothong

Latest news

VINACONEX và Trường Đại học Xây dựng Hà Nội khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị

Ngày 18 tháng 12 năm 2024, Tổng công ty cổ phần VINACONEX và Trường Đại học Xây dựng Hà Nội đã tổ chức lễ khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị. Đây là bước ...

VINACONEX và Trường Đại học Xây dựng Hà Nội khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị

Hội nghị nghiên cứu, quán triệt tư tưởng chỉ đạo, định hướng lớn của Đảng và Tổng Bí thư Tô Lâm về kỷ nguyên mới - Kỷ nguyên vươn mình của dân tộc

Thực hiện chỉ đạo của Trung ương, Kế hoạch 284 - KH/TU ngày 29/11/2024 của Ban Thường vụ Thành uỷ Hà Nội, ngày 16/12/2024, Ban Thường vụ Đảng ủy Tổng công ty tổ chức Hội nghị nghiên cứu, quán triệt tư tưởng chỉ đạo, định hướng lớn của Đảng và Tổng ...

Hội nghị nghiên cứu, quán triệt tư tưởng chỉ đạo, định hướng lớn của Đảng và Tổng Bí thư Tô Lâm về kỷ nguyên mới - Kỷ nguyên vươn mình của dân tộc

Vinaconex được bình chọn Top 2 nơi làm việc tốt nhất Việt Nam 2024 - Ngành xây dựng

Chiều 12/12/2024, tại Hà Nội, trong khuôn khổ Lễ công bố Bảng xếp hạng Top 500 doanh nghiệp tạo giá trị hàng đầu Việt Nam, VINACONEX tiếp tục được bình chọn và vinh danh TOP 2 nơi làm việc tốt nhất Việt Nam 2024 VBW10 – Ngành Xây dựng

Vinaconex được bình chọn Top 2 nơi làm việc tốt nhất Việt Nam 2024 - Ngành xây dựng

Vinaconex vinh dự là đơn vị đầu tiên hoàn thành cất nóc kết cấu thép mái nhà ga cảng HKQT Long Thành

Đã gần 4 năm kể từ ngày khởi công Cảng hàng không Quốc tế Long Thành, Nhà ga hành khách - “trái tim” của siêu dự án đang ngày một hoàn thiện và lộ rõ hình hài. Trên công trường, Vinaconex cùng các nhà thầu thuộc Liên danh VIETUR đang khẩn trương ...

Vinaconex vinh dự là đơn vị đầu tiên hoàn thành cất nóc kết cấu thép mái nhà ga cảng HKQT Long Thành
Loading...