Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

Thu , 12/08/2021, 10:40:00 (GMT+7)

 

As a key project of Hanoi, Vinh Tuy Bridge (phase II) is one of six traffic projects permitted by the city to be constructed during the social distancing period to ensure timely completion. Vinaconex contractor and construction units at the project have been trying their best to race against time to finish the project on schedule.

 By design, Vinh Tuy bridge (phase II) runs parallel to Vinh Tuy bridge, currently downstream of the Red River.

Vinh Tuy bridge construction investment project (phase II) is one of the capital's arterial traffic projects, playing an important role in completing the entire Ring Road 2 of Hanoi, strengthening traffic between the two banks of the Red River, meeting the rapidly increasing transport demand between the center of the capital and the northern and northeastern areas of the city.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing .

Vinh Tuy bridge construction investment project (phase II) seen from above

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.

Execution of bored piles T21HL and T22HL – Package 01/VT2 - XL

At Vinh Tuy Bridge construction investment project (phase II), Vinaconex was honored to be selected as a participant in Package 05/VT2 – XL (Vinaconex Joint Venture – 75 Bridge Construction Joint Stock Company) to construct the bridge. Long Bien direction and path, implementation time is 18 months; Package 01/VT2 - XL (Vinaconex - Trung Chinh Joint Venture) construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing      
 
Ensure safety and techniques at construction items on the water surface
 
On the project site, the contractors mobilized 1,000-2,000-ton barges and 4 drilling rigs with floating systems to prepare for the construction of the pile foundation in the middle of the Red River.
Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing    

 Construction of C6 pile T24 HL                          

Construction of lowering steel cage C6 – T24HL

The project currently has about 500 workers divided into 11 stitches, constructing 3 consecutive shifts at the construction site with strict Covid-19 disease prevention and control conditions. The workers are organized to work, live in a concentrated place, do not contact the outside, do not go out of the construction site, strictly comply with 5K.

     Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

 The Executive Board organizes and directs the implementation of 3 consecutive shifts of construction

Compliance with safety regulations for disease prevention is a mandatory condition at the project
  

 All workers must wear masks during work; arranged at distance, staggered eating and drinking hours to reduce concentration.

Overview of construction of bridge piers on the river.

As planned, the whole project will be completed in the second quarter of 2023.

Latest news

Hội nghị sơ kết công tác Công đoàn 6 tháng đầu năm, triển khai nhiệm vụ 6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác

Ngày 31/7, Công đoàn Tổng công ty tổ chức Hội nghị sơ kết công tác công đoàn 6 tháng đầu năm, triển khai nhiệm vụ trọng tâm 6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác. Đồng chí Âu Thị Định, Phó Chủ tịch Công đoàn XDVN đã tham dự và phát ...

Hội nghị sơ kết công tác Công đoàn 6 tháng đầu năm, triển khai nhiệm vụ  6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác

Tập Huấn An Toàn – Vệ Sinh Lao Động và khám sức khoẻ tại Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long

Nhằm tăng cường tuân thủ các quy định pháp luật và nâng cao hiệu quả thi công, ngày 28/7/2025, tại Văn phòng Ban QLDA Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long đã diễn ra buổi Huấn luyện An toàn lao động ...

Tập Huấn An Toàn – Vệ Sinh Lao Động và khám sức khoẻ tại Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

At the construction site of the Phu Thu Interchange Ninh Binh Province , over 100 engineers, technicians, and workers from the VINACONEX–Trung Chinh joint venture are working around the clock, through holidays, striving to complete the project by ...

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

VINACONEX CORPORATION’S “BACK TO THE ROOTS” JOURNEY

In celebration of the successful 6th Party Congress of VINACONEX Corporation for the 2025–2030 term, and in commemoration of the 78th War Invalids and Martyrs Day July 27, 1947 – July 27, 2025 , the VINACONEX Trade Union organized a “Back to the ...

VINACONEX CORPORATION’S “BACK TO THE ROOTS” JOURNEY
Loading...