EN

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

Thu , 12/08/2021, 10:40:00 (GMT+7)

 

As a key project of Hanoi, Vinh Tuy Bridge (phase II) is one of six traffic projects permitted by the city to be constructed during the social distancing period to ensure timely completion. Vinaconex contractor and construction units at the project have been trying their best to race against time to finish the project on schedule.

 By design, Vinh Tuy bridge (phase II) runs parallel to Vinh Tuy bridge, currently downstream of the Red River.

Vinh Tuy bridge construction investment project (phase II) is one of the capital's arterial traffic projects, playing an important role in completing the entire Ring Road 2 of Hanoi, strengthening traffic between the two banks of the Red River, meeting the rapidly increasing transport demand between the center of the capital and the northern and northeastern areas of the city.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing .

Vinh Tuy bridge construction investment project (phase II) seen from above

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.

Execution of bored piles T21HL and T22HL – Package 01/VT2 - XL

At Vinh Tuy Bridge construction investment project (phase II), Vinaconex was honored to be selected as a participant in Package 05/VT2 – XL (Vinaconex Joint Venture – 75 Bridge Construction Joint Stock Company) to construct the bridge. Long Bien direction and path, implementation time is 18 months; Package 01/VT2 - XL (Vinaconex - Trung Chinh Joint Venture) construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing      
 
Ensure safety and techniques at construction items on the water surface
 
On the project site, the contractors mobilized 1,000-2,000-ton barges and 4 drilling rigs with floating systems to prepare for the construction of the pile foundation in the middle of the Red River.
Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing    

 Construction of C6 pile T24 HL                          

Construction of lowering steel cage C6 – T24HL

The project currently has about 500 workers divided into 11 stitches, constructing 3 consecutive shifts at the construction site with strict Covid-19 disease prevention and control conditions. The workers are organized to work, live in a concentrated place, do not contact the outside, do not go out of the construction site, strictly comply with 5K.

     Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

 The Executive Board organizes and directs the implementation of 3 consecutive shifts of construction

Compliance with safety regulations for disease prevention is a mandatory condition at the project
  

 All workers must wear masks during work; arranged at distance, staggered eating and drinking hours to reduce concentration.

Overview of construction of bridge piers on the river.

As planned, the whole project will be completed in the second quarter of 2023.

Latest news

Đại hội Công đoàn Xây dựng Việt Nam lần thứ XV nhiệm kỳ 2025 - 2030 thành công tốt đẹp

Ngày 25/12/2025, Công đoàn Xây dựng Việt Nam đã tổ chức Đại hội công đoàn Xây dựng Việt Nam lần thứ XV, nhiệm kỳ 2025-2030, dự đại hội có 285 đại biểu chính thức được triệu tập, đại diện cho hơn 130 nghìn đoàn viên, công nhân, viên chức, người lao ...

Đại hội Công đoàn Xây dựng Việt Nam lần thứ XV nhiệm kỳ 2025 - 2030 thành công tốt đẹp

DẤU ẤN VINACONEX TRÊN HÀNH TRÌNH 1.800 NGÀY HÓA ĐẤT ĐỎ LONG THÀNH TRỞ THÀNH “SIÊU SÂN BAY”

Ngày 25/6/2015, Quốc hội chính thức thông qua Dự án Cảng hàng không quốc tế Long Thành – công trình mang tầm vóc thế kỷ, hiện thực hóa chủ trương đột phá chiến lược về xây dựng hệ thống hạ tầng đồng bộ, hiện đại theo tinh thần Đại hội XIII của Đảng.

DẤU ẤN VINACONEX TRÊN  HÀNH TRÌNH 1.800 NGÀY HÓA ĐẤT ĐỎ LONG THÀNH TRỞ THÀNH “SIÊU SÂN BAY”

Đảng uỷ Phường Láng kiểm tra và làm việc với Đảng uỷ Tổng công ty VINACONEX

Thực hiện Chương trình công tác kiểm tra, giám định kỳ 06 tháng cuối năm 2025 của Ban Chấp hành Đảng bộ Phường Láng, ngày 23/12/2025, Đoàn công tác số 1 của Đảng uỷ Phường Láng do đồng chí Nguyễn Hồng Dân – Bí thư Đảng uỷ, Chủ tịch HĐND Phường Láng ...

Đảng uỷ Phường Láng kiểm tra và làm việc với Đảng uỷ Tổng công ty VINACONEX

Vinaconex chung tay hỗ trợ đồng bào miền Trung khắc phục hậu quả thiên tai, lũ lụt

Tiếp nối truyền thống tương thân tương ái của dân tộc và thực hiện trách nhiệm xã hội của doanh nghiệp, VINACONEX đã phối hợp với Ủy ban MTTQ Việt Nam tổ chức chuỗi hoạt động hỗ trợ, kịp thời sẻ chia khó khăn với người dân các tỉnh miền Trung chịu ...

Vinaconex chung tay hỗ trợ đồng bào miền Trung khắc phục hậu quả thiên tai, lũ lụt
Loading...