SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON - Trang chủ | Vinaconex

EN

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Wed , 14/07/2021, 08:52:21 (GMT+7)

With the aim to complete the entire Ring Road 2, over the past time, the workers at the Vinh Tuy Bridge phase 2 project have been working actively all day and night. 

Vinh Tuy Bridge phase 2 has a total investment of over VND 2,500 billion. The bridge has a total length of more than 3.4 kilometers including the approaches, with a surface width of 19.25 meters (4 lanes), and a static height of 11 meters.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Sharing to the reporters, Mr. Do Viet Thang, Managing Director of Package 5 said: “We’re now working on the T74HL and T76H L pillars in package 5, involving about 30 officers and workers. The construction site has 2 construction sections working in 3 consecutive shifts. It’s estimated that we have reached 25% of the total workload.”

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Due to the complicated evolution of the Covid-19 pandemic, the contractor has added a lot of indicators at the Ministry of Health's request as well as for all propagating to workers not to gather outside the construction site, having meals right inside camps in shifts, and following social distancing.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The hot summer heat had a great impact on the construction work. The contractors assisted the workers by managing extra night shifts, Mr. Thang added.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The bridge was designed with permanent reinforced concrete and prestressed concrete structures with design load HL-93, and could withstand earthquakes of grade 8 in accordance to TCVN11823-2017. Even though the underground construction site was covered up and the pumps were also set up, it would still be very challenging in case of heavy rain causing flooding.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

On the construction site of the Le Van Luong - Khuat Duy Tien underpass, dozens of workers were in rush to deploy pile pressing of pumping station construction before the rainy season arrived.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Le Van Luong - Khuat Duy Tien underpass project was kicked off in October 2020 with a total investment of nearly VND700 billion, and scheduled for completion after months. This 475-meter-long underpass is made of a reinforced concrete structure in the direction of Le Van Luong - To Huu street, including a 95-meter underground tunnel and 380 meters of access and exit ramps (each ramp is 190 meters long).

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Engineer Tran Phuong Nam, in charge of the project site, shared with the reporters that there were 50 – 60 permanent workers working urgently in 9 construction sections to complete two underground culverts for water drainage in the upcoming rainy season.

He also mentioned that every morning, all employees and workers had to measure body temperature, disinfect hands and put on masks before entering the construction site. There was also a monitor group to watch over and record every person entering and departing the site in order to prevent the Covid-19 pandemic.

The underground culverts item, which has been 95% completed, is considered very important to the project.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

As the reporter noted, the narrowing of both sidewalks was executed by workers to broaden the 315-meter length of Le Van Luong street, and the 390-meter length of To Huu street.

Latest news

VINACONEX và Trường Đại học Xây dựng Hà Nội khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị

Ngày 18 tháng 12 năm 2024, Tổng công ty cổ phần VINACONEX và Trường Đại học Xây dựng Hà Nội đã tổ chức lễ khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị. Đây là bước ...

VINACONEX và Trường Đại học Xây dựng Hà Nội khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị

Vinaconex được bình chọn Top 2 nơi làm việc tốt nhất Việt Nam 2024 - Ngành xây dựng

Chiều 12/12/2024, tại Hà Nội, trong khuôn khổ Lễ công bố Bảng xếp hạng Top 500 doanh nghiệp tạo giá trị hàng đầu Việt Nam, VINACONEX tiếp tục được bình chọn và vinh danh TOP 2 nơi làm việc tốt nhất Việt Nam 2024 VBW10 – Ngành Xây dựng

Vinaconex được bình chọn Top 2 nơi làm việc tốt nhất Việt Nam 2024 - Ngành xây dựng

Vinaconex vinh dự là đơn vị đầu tiên hoàn thành cất nóc kết cấu thép mái nhà ga cảng HKQT Long Thành

Đã gần 4 năm kể từ ngày khởi công Cảng hàng không Quốc tế Long Thành, Nhà ga hành khách - “trái tim” của siêu dự án đang ngày một hoàn thiện và lộ rõ hình hài. Trên công trường, Vinaconex cùng các nhà thầu thuộc Liên danh VIETUR đang khẩn trương ...

Vinaconex vinh dự là đơn vị đầu tiên hoàn thành cất nóc kết cấu thép mái nhà ga cảng HKQT Long Thành

Thủ Tướng kiểm tra tiến độ sân bay Long Thành

Sáng 3/12, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính kiểm tra thi công dự án Cảng hàng không Quốc tế Long Thành và hệ thống giao thông kết nối với Cảng hàng không Quốc tế Long Thành.

Thủ Tướng kiểm tra tiến độ sân bay Long Thành
Loading...