SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON - Trang chủ | Vinaconex

EN

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Wed , 14/07/2021, 08:52:21 (GMT+7)

With the aim to complete the entire Ring Road 2, over the past time, the workers at the Vinh Tuy Bridge phase 2 project have been working actively all day and night. 

Vinh Tuy Bridge phase 2 has a total investment of over VND 2,500 billion. The bridge has a total length of more than 3.4 kilometers including the approaches, with a surface width of 19.25 meters (4 lanes), and a static height of 11 meters.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Sharing to the reporters, Mr. Do Viet Thang, Managing Director of Package 5 said: “We’re now working on the T74HL and T76H L pillars in package 5, involving about 30 officers and workers. The construction site has 2 construction sections working in 3 consecutive shifts. It’s estimated that we have reached 25% of the total workload.”

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Due to the complicated evolution of the Covid-19 pandemic, the contractor has added a lot of indicators at the Ministry of Health's request as well as for all propagating to workers not to gather outside the construction site, having meals right inside camps in shifts, and following social distancing.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The hot summer heat had a great impact on the construction work. The contractors assisted the workers by managing extra night shifts, Mr. Thang added.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The bridge was designed with permanent reinforced concrete and prestressed concrete structures with design load HL-93, and could withstand earthquakes of grade 8 in accordance to TCVN11823-2017. Even though the underground construction site was covered up and the pumps were also set up, it would still be very challenging in case of heavy rain causing flooding.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

On the construction site of the Le Van Luong - Khuat Duy Tien underpass, dozens of workers were in rush to deploy pile pressing of pumping station construction before the rainy season arrived.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Le Van Luong - Khuat Duy Tien underpass project was kicked off in October 2020 with a total investment of nearly VND700 billion, and scheduled for completion after months. This 475-meter-long underpass is made of a reinforced concrete structure in the direction of Le Van Luong - To Huu street, including a 95-meter underground tunnel and 380 meters of access and exit ramps (each ramp is 190 meters long).

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Engineer Tran Phuong Nam, in charge of the project site, shared with the reporters that there were 50 – 60 permanent workers working urgently in 9 construction sections to complete two underground culverts for water drainage in the upcoming rainy season.

He also mentioned that every morning, all employees and workers had to measure body temperature, disinfect hands and put on masks before entering the construction site. There was also a monitor group to watch over and record every person entering and departing the site in order to prevent the Covid-19 pandemic.

The underground culverts item, which has been 95% completed, is considered very important to the project.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

As the reporter noted, the narrowing of both sidewalks was executed by workers to broaden the 315-meter length of Le Van Luong street, and the 390-meter length of To Huu street.

Latest news

CẢNH GIÁC TRƯỚC CHIÊU TRÒ GIẢ MẠO THƯƠNG HIỆU VINACONEX ĐỂ LỪA ĐẢO CHIẾM ĐOẠT TÀI SẢN (KHUYẾN CÁO LẦN 5)

Trong thời gian vừa qua, Tổng công ty cổ phần Xuất nhập khẩu và Xây dựng Việt Nam “VINACONEX” đã phát hiện và tiếp tục nhận được nhiều phản hồi thông tin về hành vi của các đối tượng xấu giả mạo VINACONEX hoặc nhân viên của VINACONEX để thực hiện ...

CẢNH GIÁC TRƯỚC CHIÊU TRÒ GIẢ MẠO THƯƠNG HIỆU VINACONEX ĐỂ LỪA ĐẢO CHIẾM ĐOẠT TÀI SẢN (KHUYẾN CÁO LẦN 5)

Thủ tướng Phạm Minh Chính phát lệnh khởi công, khánh thành đồng loạt các công trình trọng điểm Quốc gia

Sáng 19/4, tại điểm cầu trung tâm Nhà ga T3, Cảng hàng không quốc tế Tân Sơn Nhất, Thành phố Hồ Chí Minh, Thủ tướng Chính phủ Phạm Minh Chính đã chủ trì lễ khởi công, khánh thành đồng loạt 80 công trình, dự án trọng điểm quốc gia và các công trình ...

Thủ tướng Phạm Minh Chính phát lệnh khởi công, khánh thành đồng loạt các công trình trọng điểm Quốc gia

Cao tốc Bãi Vọt - Hàm Nghi sẵn sàng thông xe kỹ thuật

Cao tốc Bắc - Nam phía Đông đoạn Bãi Vọt - Hàm Nghi đã sẵn sàng thông xe kỹ thuật vào ngày 19/4, về đích trước 6 tháng, chào mừng kỷ niệm 50 năm ngày Giải phóng miền Nam, thống nhất đất nước 30/4/1975 - 30/4/2025 .

Cao tốc Bãi Vọt - Hàm Nghi sẵn sàng thông xe kỹ thuật

Hà Nội: Khởi công dự án xây dựng nút giao khác mức giữa đường Vành đai 3,5 với Đại lộ Thăng Long

Sáng 19-4, UBND thành phố Hà Nội đã tổ chức khởi công dự án đầu tư xây dựng nút giao khác mức giữa đường Vành đai 3,5 với Đại lộ Thăng Long huyện Hoài Đức .

Hà Nội: Khởi công dự án xây dựng nút giao khác mức giữa đường Vành đai 3,5 với Đại lộ Thăng Long
Loading...