EN

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Wed , 14/07/2021, 08:52:21 (GMT+7)

With the aim to complete the entire Ring Road 2, over the past time, the workers at the Vinh Tuy Bridge phase 2 project have been working actively all day and night. 

Vinh Tuy Bridge phase 2 has a total investment of over VND 2,500 billion. The bridge has a total length of more than 3.4 kilometers including the approaches, with a surface width of 19.25 meters (4 lanes), and a static height of 11 meters.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Sharing to the reporters, Mr. Do Viet Thang, Managing Director of Package 5 said: “We’re now working on the T74HL and T76H L pillars in package 5, involving about 30 officers and workers. The construction site has 2 construction sections working in 3 consecutive shifts. It’s estimated that we have reached 25% of the total workload.”

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Due to the complicated evolution of the Covid-19 pandemic, the contractor has added a lot of indicators at the Ministry of Health's request as well as for all propagating to workers not to gather outside the construction site, having meals right inside camps in shifts, and following social distancing.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The hot summer heat had a great impact on the construction work. The contractors assisted the workers by managing extra night shifts, Mr. Thang added.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The bridge was designed with permanent reinforced concrete and prestressed concrete structures with design load HL-93, and could withstand earthquakes of grade 8 in accordance to TCVN11823-2017. Even though the underground construction site was covered up and the pumps were also set up, it would still be very challenging in case of heavy rain causing flooding.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

On the construction site of the Le Van Luong - Khuat Duy Tien underpass, dozens of workers were in rush to deploy pile pressing of pumping station construction before the rainy season arrived.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Le Van Luong - Khuat Duy Tien underpass project was kicked off in October 2020 with a total investment of nearly VND700 billion, and scheduled for completion after months. This 475-meter-long underpass is made of a reinforced concrete structure in the direction of Le Van Luong - To Huu street, including a 95-meter underground tunnel and 380 meters of access and exit ramps (each ramp is 190 meters long).

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Engineer Tran Phuong Nam, in charge of the project site, shared with the reporters that there were 50 – 60 permanent workers working urgently in 9 construction sections to complete two underground culverts for water drainage in the upcoming rainy season.

He also mentioned that every morning, all employees and workers had to measure body temperature, disinfect hands and put on masks before entering the construction site. There was also a monitor group to watch over and record every person entering and departing the site in order to prevent the Covid-19 pandemic.

The underground culverts item, which has been 95% completed, is considered very important to the project.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

As the reporter noted, the narrowing of both sidewalks was executed by workers to broaden the 315-meter length of Le Van Luong street, and the 390-meter length of To Huu street.

Latest news

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

38 năm hình thành và phát triển là hành trình được tạo nên bởi bản lĩnh, trí tuệ, sự bền bỉ và tinh thần đoàn kết của nhiều thế hệ người lao động VINACONEX. Từ những giá trị được vun đắp qua năm tháng, Tổng công ty hôm nay tiếp tục đổi mới, nâng cao ...

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

Tổng công ty CP VINACONEX vừa tiếp nhận lô thiết bị máy khoan cọc nhồi SANY SR235 và SANY SR285R, bổ sung nguồn lực thiết bị hiện đại, góp phần nâng cao năng lực thi công nền móng và tăng tính chủ động trong triển khai các dự án quy mô lớn.

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

KHỞI CÔNG CỤM CÔNG NGHIỆP SƠN ĐÔNG - Không gian sản xuất mới phía Tây thủ đô

Hướng tới chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX, ngày 17/9/2026, Cụm công nghiệp Sơn Đông đã chính thức được khởi công tại xã Đoài Phương, TP. Hà Nội, mở thêm không gian sản xuất tập trung, hiện đại phía Tây Thủ đô.

KHỞI CÔNG CỤM CÔNG NGHIỆP SƠN ĐÔNG - Không gian sản xuất mới phía Tây thủ đô

JICA và FiinGroup thăm và làm việc tại VINACONEX

Sáng 11/9/2026, Đoàn công tác Cơ quan Hợp tác Quốc tế Nhật Bản JICA và Công ty Cổ phần FiinGroup Việt Nam đã đến thăm và làm việc tại Tổng công ty CP VINACONEX, trao đổi về các cơ chế hỗ trợ tài chính và khả năng hợp tác trong thời gian tới.

JICA và FiinGroup thăm và làm việc tại VINACONEX
Loading...