CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNE...

EN

CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY

Sun , 06/08/2023, 14:00:00 (GMT+7)

Chairman of the Board, Mr. Dao Ngoc Thanh requested that PMU no.1 direct the executive board of the joint venture for package no. 10 to adhere to regulations on quality and technical standards and ensure progress as specified in the contract with the investor. It was also requested that the relevant units review the legal regulations related to the construction work.
On August 5th, a delegation from the Corporation, led by Chairman Dao Ngoc Thanh, paid a visit to review and inspect the construction work of package no. 10 under the project of connecting road from Van Don - Mong Cai Expressway to Van Ninh port (Van Gia), Mong Cai city.

CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Chairman Dao Ngoc Thanh gave a directing speech at the meeting

During the meeting, Chairman Dao Ngoc Thanh emphasized the Corporation's position as a leading enterprise in the construction industry and expressed the responsibility to the authorities, local people, investors. The PMU No. 1 and executive board of the JV for Package No. 10 shall be responsible for implementing the bidding package in strict accordance with regulations on quality and technical standards, ensuring progress stipulated in the contract signed with the investor, and complying with relevant legislation.
Besides, the Chairman asked the Corporation's Department of Foreign Affairs and Legal Affairs closely collaborate with the PMU No. 1 and executive board of the JV to thoroughly review legal issues related to the execution of package 10.
Furthermore, he stressed the importance of PMU No. 1 and the executive board fully following the approved design documents and complying with relevant technical standards. If there are any issues that require changes to the technical documents, they must be reported and approved in writing by the competent authorities before being implemented.

CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Deputy General Director Nguyen Huu Toi provided a report on the construction direction in package no. 10
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Deputy General Director Tran Dinh Tuan delivered his speech at the meeting

The bidding package is currently undergoing the implementation of crucial items, the PMU No. 1 and executive board of the JV are working diligently to expedite the progress, rigorously oversee the construction quality, promptly addressing any project-related issues, and ensuring the project's timely completion, in line with the investor’s design and technical standards, thereby bolstering and maintaining the Corporation's reputation in the construction industry, as well as the Vinaconex brand in the market. 

As one of four long-term growth-driving projects of Quang Ninh province that covers an area of 82.79 hectares, Van Ninh general port invested by Van Ninh International Port JSC, with a total investment of phase 1 of over VND 2,248 billion, is capable of accommodating ships with a tonnage of up to 20,000 DWT, ferries on the sea and inland waterways. It functions as a focal point for gathering and distributing Vietnam’s import and export goods to the Chinese market, forming a logistics service chain to optimize import and export efficiency, while meeting the requirements of national security, sovereignty over sea and islands if needed. Once completed, this project will significantly contribute to the modernization and synchronization of the infrastructure and transportation network, and boost the transportation and import-export activities.
 

Some photos of the inspection at the construction site of package No. 10

CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Transporting and constructing beams
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Placing the beams on the road
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Construction of road base
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
One of the important works, soil compaction is being accelerated
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Construction of pressure berms to mitigate the impact of the stormy season
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Build stone embankment with taluy roof on the route
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Mặt đường bê tông hoàn thiện
CHAIRMAN OF THE BOARD DAO NGOC THANH INSPECTS THE CONSTRUCTION OF PACKAGE NO. 10 UNDER THE PROJECT TO BUILD A ROAD CONNECTING VAN DON - MONG CAI EXPRESSWAY TO VAN NINH PORT (VAN GIA) IN MONG CAI CITY
Material transportation on construction site

 


 

Latest news

Lễ ký kết với các đại lý phân phối dự án Vera Diamond City Quảng Ninh

Các đại lý bất động sản sẽ tham gia phân phối dự án Vera Diamond City cho giai đoạn thương mại hóa dự án. Đây là sự kiện đánh dấu bước khởi đầu cho hành trình mở rộng hợp tác bền vững, kết nối chuỗi giá trị từ chủ đầu tư đến tay khách hàng.

Lễ ký kết với các đại lý phân phối dự án Vera Diamond City Quảng Ninh

Hình ảnh mới nhất dự án “Siêu nút giao” vành đai 3,5 qua Đại lộ Thăng Long

Dự án siêu nút giao gần 2.400 tỷ đồng của đường vành đai 3,5 qua Đại lộ Thăng Long đang bước vào giai đoạn đào hầm chui, dần lộ hình hài sau nhiều tháng khởi công. Nhà thầu VINACONEX cùng Liên danh Thăng Long đang tăng tốc thi công, phấn đấu hoàn ...

Hình ảnh mới nhất dự án “Siêu nút giao” vành đai 3,5 qua Đại lộ Thăng Long

Vinaconex tiên phong đưa học viên ra nước ngoài học tập công nghệ đường sắt hiện đại

Hướng tới mục tiêu phát triển nguồn nhân lực chất lượng cao trong lĩnh vực hạ tầng giao thông, Vinaconex phối hợp cùng Trường Đại học Xây dựng Hà Nội tổ chức khóa học thực tế tại Trung Quốc chuyên ngành Đường sắt cao tốc - Đường sắt đô thị.

Vinaconex tiên phong đưa học viên ra nước ngoài học tập công nghệ đường sắt hiện đại

Dự án vành đai 4 – Vùng Thủ đô: Tăng tốc về đích trước 6 tháng

Những ngày cuối tháng 10/2025, trên đại công trường Dự án Vành đai 4 – Vùng Thủ đô, không khí thi công trở nên sôi động hơn bao giờ hết. Hàng trăm kỹ sư, công nhân VINACONEX đang ngày đêm bám công trường, làm việc với tinh thần “vượt nắng – thắng ...

Dự án vành đai 4 – Vùng Thủ đô: Tăng tốc về đích trước 6 tháng
Loading...