DAU GIAY – PHAN THIET EXPRESSWAY BEFORE THE TECHNICAL TRAFFIC DATE OF DECEMBER 21, 2022

Wed , 28/12/2022, 10:35:00 (GMT+7)

The date for the technical traffic clearance, inauguration, and operation of the Phan Thiet - Dau Giay Expressway remains the same. That is a requirement of the Ministry of Transport and Communications for contractors and units implementing the Dau Giay - Phan Thiet Expressway project, a component project of the eastern North-South expressway in the 2017-2020 period. In order to keep up with the committed progress, over the past time, machines have always bustled, and workers have been working urgently to finish the remaining items on the large construction site in order to stick to the schedule. The reporter from Dong Nai's report on a new day is as follows. The following are the notes of Dong Nai new day’s reporter.

The 51.3 km section of the Dau Giay-Phan Thiet Expressway project that passes through the Dong Nai province was formally kicked off at the end of 2020. It was expected to be completed after 24 months and was divided into two bidding packages - 3-XL and 4-XL, in which Vinaconex-Trung Chinh joint venture was the construction unit of the entire route over 35km in package 3-XL. On the big construction site, three shifts of hundreds of workers, machines, and equipment have been working all day and night in the urgent atmosphere, the product so far has reached nearly 70%.
According to the construction units, the deadline for technical traffic is drawing near, therefore, they have added lines of concrete mixer and crushed aggregate base course as well as mobilized all resources to concentrate on implementing the construction. In order to guarantee technical traffic clearance by the end of December, contractors have been attempting to work overtime and increasing construction shifts to complete other items.

DAU GIAY – PHAN THIET EXPRESSWAY BEFORE THE TECHNICAL TRAFFIC DATE OF DECEMBER 21, 2022
Dau Giay - Phan Thiet Expressway before the technical traffic date of Dec 31, 2022

As for package 4 with a length of 16km implemented by Thang Long Corporation and CIENCO 6 joint venture, its shape has been gradually and continually formed up to this point, and the construction product has reached over 70% of the package value. Taking advantage of favorable weather, the unit has constructed the main items such as: filling the ground with more than 80% completion, hot asphalt concrete pavements of mixed layers with 10 out of 16 km entire route complete and over 90% completion of bridge construction work. Moreover, the contractors have gathered construction materials for casting concrete components, in which, more than 5km of median strips and highway fence posts have been completed. At the same time, they also focused on completing the foundation and road surface works as quickly as possible to meet the progress.
Minister of Transport – Mr. Nguyen Van Thang recently underlined at the actual survey on the progress of the Phan Thiet - Dau Giay Expressway project that this project shall be technically open to traffic by the end of 2022 and shall be put into operation on April 30, 2023. The Minister also requested that any contractors including supervision consultants, who do not fulfill the requirements of progress and quality at this time shall be replaced and not allowed to work on any future projects deployed by the Ministry, including those involving private investment units. consultation on monitoring. Since there is not much time left for implementation on the construction site while the workload is still huge, the investors must instruct and motivate the contractors to focus all of their available resources, workforces, materials, machinery, and equipment to execute as quickly and dramatically as possible in order to complete the project at committed progress.
 

Theo ĐNRTV

Latest news

VINACONEX thúc đẩy hợp tác đào tạo, nghiên cứu và ứng dụng công nghệ

Các đơn vị trong hệ sinh thái VINACONEX ký kết Biên bản hợp tác với Đại học Thái Nguyên, mở rộng liên kết trong đào tạo nguồn nhân lực, nghiên cứu khoa học thuộc lĩnh vực Y tế, năng lượng…

VINACONEX thúc đẩy hợp tác đào tạo, nghiên cứu và ứng dụng công nghệ

Thủy điện Ngòi Phát chính thức cán mốc 5 tỷ Kwh điện

Sau 12 năm vận hành, Nhà máy Thủy điện Ngòi Phát đã đóng góp vào hệ thống điện quốc gia 5 tỷ kWh điện, khẳng định hiệu quả đầu tư, năng lực quản lý vận hành và sự bền bỉ của đội ngũ cán bộ, kỹ sư, người lao động.

Thủy điện Ngòi Phát chính thức cán mốc 5 tỷ Kwh điện

VINACONEX tiếp tục ghi danh Top 10 nơi làm việc tốt nhất Việt Nam 2026 – Ngành Xây dựng

VINACONEX tiếp tục được vinh danh trong Top 10 Nơi làm việc tốt nhất Việt Nam 2026 – Ngành Xây dựng, ghi dấu nhiều năm liên tiếp góp mặt trong bảng xếp hạng uy tín, khẳng định nỗ lực xây dựng môi trường làm việc chuyên nghiệp và phát triển nguồn nhân ...

VINACONEX tiếp tục ghi danh Top 10 nơi làm việc tốt nhất Việt Nam 2026 – Ngành Xây dựng

VIWASEEN ký kết biên bản ghi nhớ hợp tác vớI K-WATER

Ngày 21/10/2026, Tổng công ty Đầu tư nước và Môi trường Việt Nam – CTCP VIWASEEN và Tổng công ty Tài nguyên nước Hàn Quốc K-Water tổ chức Lễ ký kết Biên bản ghi nhớ hợp tác MOU , mở ra cơ hội tăng cường kết nối, chia sẻ kinh nghiệm và thúc đẩy ...

VIWASEEN ký kết biên bản ghi nhớ hợp tác vớI K-WATER
Loading...