Investment project on construction & renovation of national highway: Hanoi - Bac Giang (2014-2016)

Name of project:
Investment project on construction, renovation and upgrading of National Highway 1, section Hanoi - Bac Giang (2014-2016)
Investor
Hanoi - Bac Giang BOT Investment Joint Stock Company (Consortium of investors: Ocean Group Joint Stock Company, Vinaconex Corporation, 319 Investment and Trading Joint Stock Company and Van P
Project location
Bac Giang- Hanoi
Research land area
45.8 km
Project Scale
Total estimated investment capital: VND 3,734,227 billion (excluding loan interest)
Total investment length: 45.8 km
Technical design: 4 lanes with allowed speed 100km/h

- Starting point: KM 113+985 - Old National Highway 1 (intersection of National Highway 31) in the territory of Bac Giang city, Bac Giang province;

- End point: Km159+100 – the route to National Highway 1 (former Phu Dong toll station) in Hanoi.

- Total investment length: 45.8 km;

- Technical design: 4 lanes with allowed speed of 100km/h, can be upgraded to 6 lanes in the future.

- It is expected that when completed and put into operation (June 2016), the project will meet the transportation needs, reduce traffic congestion and accidents on National Highway 1, contribute to promoting socio-economic development of the country. northern area. This is one of the first highway projects in Vietnam invested in the form of BOT. To recover capital, investors are allowed to collect fees from July 2016 with an expected period of 18 years and 7 months from the date of fee collection. After this period, the investor will transfer the work without compensation to the competent State agency.