EN

STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY

Wed , 20/03/2024, 14:00:00 (GMT+7)

That is the commitment of Vinaconex contractor at the inspection conducted on the morning of March 20 by Deputy Minister of Transport Nguyen Duy Lam and his working delegation.
Accompanying the Deputy Minister were Pham Chien Thang, Executive Director of the Bai Vot - Ham Nghi Expressway Project (managed by Thang Long Project Management Board), representatives from construction units and other related parties.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
Deputy Minister of Transport Nguyen Duy Lam inspected the progress of the North-South expressway, the section passing through Ha Tinh province
Representing Vinaconex, the contractor participating in the project construction was Director of Project Management Unit No.1 Pham Thai Duong.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
Deputy Minister of Transport Nguyen Duy Lam oversaw the construction progress at Bai Vot - Ham Nghi expressway.
After over a year of urgent construction, the units have excavated 1.0/1.6 million m3 of the main road base, which is 65% complete; K95 soil embankment has reached 1.1/4.6 million m3 (24% complete); The project has finished installing wick drains in all relevant sections, completed 72% of sand drain installations, and reached 75% completion for soil-cement column treatments. Besides, work is progressing at 24 out of 25 bridge locations, 28 out of 48 culverts and underpasses along the route. Bored pile construction for bridges is nearly finished, with simultaneous work on beam casting, component assembly, and substructure.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
The contractor strives to complete the construction before schedule, ensuring that the National Highway no. 8A intersection opens in June 2024
Vinaconex contractor has recently deployed a maximum number of human resources, equipment, and machinery, in an attempt to speed up the construction progress of the National Highway 8A intersection adjacent to the Dien Chau - Bai Vot expressway project, which is expected to open to traffic in June 6.
“So far, Vinaconex is confident in completing the intersection's items before June 30; completing the main route by April 2024, and ensuring traffic opening by June 4” - said Mr. Pham Thai Duong, Director of PMU 1.
Deputy Minister Nguyen Duy Lam and the delegation commended the project investors and contractors for their dedication. Despite initial obstacles, the project has begun speeding up, aiming to expedite progress by 3 to 6 months compared to the contract. Contractors are urged to intensify efforts, mobilizing additional human and equipment resources while implementing efficient construction methods to ensure progress across all packages of the project. 
The Bai Vot - Ham Nghi project has a total length of 35.28 kilometers, starting at Km479+117.18 in Thanh Binh Thinh commune, Duc Tho district, Ha Tinh province, and ending at Km514+441.33 in Thach Xuan commune, Thach Ha district, Ha Tinh province. With a total investment of VND7,643 billion, the project commenced on January 1, 2023, implemented by a joint venture of Vietnam Construction and Import-Export Corporation (Vinaconex) and 319 Corporation Ministry Of National Defence. 

Latest news

Sôi nổi các hoạt động chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX

Hướng tới kỷ niệm 38 năm thành lập Tổng công ty VINACONEX 27/9/1988 – 27/9/2026 , chuỗi hoạt động văn hóa, thể thao đã chính thức được phát động trên toàn hệ thống. Đây không chỉ là sân chơi giao lưu, gắn kết dành cho cán bộ, người lao động, mà còn ...

Sôi nổi các hoạt động chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX

VINACONEX phát động chuỗi hoạt động V-SAFETY: Lan tỏa văn hóa an toàn trên mọi công trường

Hướng tới kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX 27/9/1988 – 27/9/2026 , từ ngày 01/8/2026, VINACONEX triển khai chuỗi hoạt động V-SAFETY với hành trình 150 ngày an toàn kéo dài đến hết năm 2026. Đây là một trong những chương trình trọng ...

VINACONEX phát động chuỗi hoạt động V-SAFETY: Lan tỏa văn hóa an toàn trên mọi công trường

VINACONEX tham dự chương trình huấn luyện dân quân tự vệ Cụm số 2 - Phường Láng năm 2026

Chương trình huấn luyện lực lượng tự vệ Cụm số 2 do Ban Chỉ huy Quân sự phường Láng tổ chức là hoạt động thường niên nhằm nâng cao bản lĩnh chính trị, trình độ quân sự và khả năng sẵn sàng thực hiện nhiệm vụ của lực lượng tự vệ thuộc VINACONEX và các ...

VINACONEX tham dự chương trình huấn luyện dân quân tự vệ Cụm số 2 - Phường Láng năm 2026

V-SAFETY SỐ 18 | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN

V-SAFETY | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN

V-SAFETY SỐ 18 | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN
Loading...