STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY

Wed , 20/03/2024, 14:00:00 (GMT+7)

That is the commitment of Vinaconex contractor at the inspection conducted on the morning of March 20 by Deputy Minister of Transport Nguyen Duy Lam and his working delegation.
Accompanying the Deputy Minister were Pham Chien Thang, Executive Director of the Bai Vot - Ham Nghi Expressway Project (managed by Thang Long Project Management Board), representatives from construction units and other related parties.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
Deputy Minister of Transport Nguyen Duy Lam inspected the progress of the North-South expressway, the section passing through Ha Tinh province
Representing Vinaconex, the contractor participating in the project construction was Director of Project Management Unit No.1 Pham Thai Duong.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
Deputy Minister of Transport Nguyen Duy Lam oversaw the construction progress at Bai Vot - Ham Nghi expressway.
After over a year of urgent construction, the units have excavated 1.0/1.6 million m3 of the main road base, which is 65% complete; K95 soil embankment has reached 1.1/4.6 million m3 (24% complete); The project has finished installing wick drains in all relevant sections, completed 72% of sand drain installations, and reached 75% completion for soil-cement column treatments. Besides, work is progressing at 24 out of 25 bridge locations, 28 out of 48 culverts and underpasses along the route. Bored pile construction for bridges is nearly finished, with simultaneous work on beam casting, component assembly, and substructure.
STRIVING FOR ACCELERATED CONSTRUCTION OF BAI VOT - HAM NGHI EXPRESSWAY
The contractor strives to complete the construction before schedule, ensuring that the National Highway no. 8A intersection opens in June 2024
Vinaconex contractor has recently deployed a maximum number of human resources, equipment, and machinery, in an attempt to speed up the construction progress of the National Highway 8A intersection adjacent to the Dien Chau - Bai Vot expressway project, which is expected to open to traffic in June 6.
“So far, Vinaconex is confident in completing the intersection's items before June 30; completing the main route by April 2024, and ensuring traffic opening by June 4” - said Mr. Pham Thai Duong, Director of PMU 1.
Deputy Minister Nguyen Duy Lam and the delegation commended the project investors and contractors for their dedication. Despite initial obstacles, the project has begun speeding up, aiming to expedite progress by 3 to 6 months compared to the contract. Contractors are urged to intensify efforts, mobilizing additional human and equipment resources while implementing efficient construction methods to ensure progress across all packages of the project. 
The Bai Vot - Ham Nghi project has a total length of 35.28 kilometers, starting at Km479+117.18 in Thanh Binh Thinh commune, Duc Tho district, Ha Tinh province, and ending at Km514+441.33 in Thach Xuan commune, Thach Ha district, Ha Tinh province. With a total investment of VND7,643 billion, the project commenced on January 1, 2023, implemented by a joint venture of Vietnam Construction and Import-Export Corporation (Vinaconex) and 319 Corporation Ministry Of National Defence. 

Latest news

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Ngày 24-6, phường Láng tổ chức Hội nghị công bố quyết định chuyển giao, tiếp nhận tổ chức Đảng và đảng viên đối với Đảng bộ Tổng công ty Đầu tư nước và Môi trường Việt Nam Viwaseen . Sự kiện đánh dấu một bước đi cụ thể nhằm kiện toàn tổ chức, tăng ...

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Hội nghị công bố quyết định chuyển giao, tiếp nhận Đảng bộ VIWASEEN về trực thuộc Đảng bộ VINACONEX

Thực hiện Nghị quyết số 1952-QĐ/TU của Ban Thường vụ Thành ủy Hà Nội, ngày 24/6/2026, Ban Thường vụ Đảng ủy phường Láng và Đảng ủy Tổng công ty CP VINACONEX đã tổ chức Hội nghị công bố quyết định chuyển giao Đảng bộ Tổng công ty Đầu tư Nước và Môi ...

Hội nghị công bố quyết định chuyển giao, tiếp nhận Đảng bộ VIWASEEN về trực thuộc Đảng bộ VINACONEX

Nghiên cứu quy hoạch mỏ vật liệu phục vụ riêng dự án cao tốc trọng điểm

Trong bối cảnh nhiều dự án giao thông triển khai đồng loạt, việc quy hoạch, phân định rõ các mỏ vật liệu phục vụ dự án cao tốc trọng điểm quốc gia được đánh giá là cần thiết để đáp ứng tiến độ, chất lượng theo kế hoạch yêu cầu.

Nghiên cứu quy hoạch mỏ vật liệu phục vụ riêng dự án cao tốc trọng điểm

SIGNING CEREMONY MARKS TRANSFER OF VIWASEEN PARTY ORGANIZATION RECORDS TO VINACONEX PARTY COMMITTEE

A formal handover ceremony was held to transfer the Party organization records and membership roster of VIWASEEN's Party Committee to VINACONEX's Party Committee. The move marks an important step in strengthening Party leadership and ensuring unified ...

SIGNING CEREMONY MARKS TRANSFER OF VIWASEEN PARTY ORGANIZATION RECORDS TO VINACONEX PARTY COMMITTEE
Loading...