DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT

Sat , 23/05/2026, 17:00:00 (GMT+7)

On May 23, 2026, Politburo member and Permanent Deputy Prime Minister Pham Gia Tuc conducted an inspection of major projects in southern Vietnam, including Long Thanh International Airport, the Ho Chi Minh City - Long Thanh - Dau Giay Expressway, and the operational status of Tan Son Nhat International Airport's T3 Terminal.
At the Long Thanh International Airport project, VINACONEX was represented by Mr. Pham Thai Duong, General Director of the Corporation, along with the project management board and the site engineering teams.

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Deputy PM Pham Gia Tuc inspected the site and listened to a progress report on the Long Thanh International Airport project.

 

After receiving progress reports, the Permanent Deputy Prime Minister emphasized that the final phase of the project is particularly critical. He called on the investor, Airports Corporation of Vietnam (ACV), to strengthen its overall coordination role, guide contractors and construction units to work in sync, and strive to complete the project as soon as possible.

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Mr. Pham Thai Duong, General Director of VINACONEX (far right), and the project management team responsible for executing various work packages attend the working session

 

Across the vast construction site, VINACONEX is accelerating work on multiple key components, including the passenger terminal, runways, aircraft aprons, internal airport roads, and technical infrastructure.

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Permanent Deputy PM Pham Gia Tuc visits and encourages VINACONEX employees and other contractors on site
DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
The Deputy PM took time to meet and encourage the VINACONEX engineers and workers and other contracting units who are working day and night to bring the project to completion on schedule

 

Despite numerous field challenges, VINACONEX and its partners are mobilizing maximum manpower and equipment, maintaining round-the-clock construction, and demonstrating an unwavering commitment to ensure the landmark national project meets its designated timeline.

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
The Deputy Prime Minister warmly presents gifts to encourage the contractors working on the project.

For its assigned work packages, VINACONEX remains firmly on schedule:
Package No. 5.10 (Passenger Terminal construction and equipment installation) has reached 82% completion. Package No. 4.7 (Aircraft apron construction) is expected to be completed by the end of July 2026, ahead of the contract schedule. Package No. 4.8 (Internal airport roads and technical infrastructure) and Package No.4.12 (Runway and second taxiway construction) are both on track for completion by the end of September 2026, in line with contract requirements.

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Inside the passenger terminal, a critical component of the project, VINACONEX is accelerating the installation of metal ceilings
DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Granite flooring installation underway inside the passenger terminal

 

Maintaining a non-stop construction tempo, VINACONEX continues to ensure both progress and quality at Long Thanh International Airport - an infrastructure project that reflects the nation's growing capabilities and aspirations in this new era of development.

DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Quality control inspections are carried out rigorously at the project site
DEPUTY PRIME MINISTER PHAM GIA TUC INSPECTS PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PROJECT
Technical staff inspect granite flooring inside the passenger terminal, ensuring every detail meets the quality standards required at Long Thanh International Airport

 

 

 

 

Latest news

Sôi nổi các hoạt động chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX

Hướng tới kỷ niệm 38 năm thành lập Tổng công ty VINACONEX 27/9/1988 – 27/9/2026 , chuỗi hoạt động văn hóa, thể thao đã chính thức được phát động trên toàn hệ thống. Đây không chỉ là sân chơi giao lưu, gắn kết dành cho cán bộ, người lao động, mà còn ...

Sôi nổi các hoạt động chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX

VINACONEX phát động chuỗi hoạt động V-SAFETY: Lan tỏa văn hóa an toàn trên mọi công trường

Hướng tới kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX 27/9/1988 – 27/9/2026 , từ ngày 01/8/2026, VINACONEX triển khai chuỗi hoạt động V-SAFETY với hành trình 150 ngày an toàn kéo dài đến hết năm 2026. Đây là một trong những chương trình trọng ...

VINACONEX phát động chuỗi hoạt động V-SAFETY: Lan tỏa văn hóa an toàn trên mọi công trường

VINACONEX tham dự chương trình huấn luyện dân quân tự vệ Cụm số 2 - Phường Láng năm 2026

Chương trình huấn luyện lực lượng tự vệ Cụm số 2 do Ban Chỉ huy Quân sự phường Láng tổ chức là hoạt động thường niên nhằm nâng cao bản lĩnh chính trị, trình độ quân sự và khả năng sẵn sàng thực hiện nhiệm vụ của lực lượng tự vệ thuộc VINACONEX và các ...

VINACONEX tham dự chương trình huấn luyện dân quân tự vệ Cụm số 2 - Phường Láng năm 2026

V-SAFETY SỐ 18 | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN

V-SAFETY | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN

V-SAFETY SỐ 18 | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN
Loading...