INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL

Fri , 30/08/2024, 10:03:00 (GMT+7)

The joint venture of contractors is currently working on the steel frame roof for Phase 1 of Long Thanh International Airport, a critical component of the Long Thanh Airport project, which has the largest amount of capital funding in Vietnam. Nhan Dan Newspaper reporters captured the bustling construction activity at the Long Thanh Airport mega construction site today, August 29. 

INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
According to a representative from the Airports Corporation of Vietnam (ACV), the steel roof structure for the passenger terminal is valued at around VND 3.5 trillion, accounting for approximately 10% of the total contract value for the terminal project.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The construction requires about 32,000 tons of steel for the roof frame of Long Thanh Airport passenger terminal phase 1.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Workers and engineers lifted steel structures to install the roof of the Long Thanh Airport passenger terminal.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Workers carried out the assembly process after the steel components had been transported to the roof site.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Installation is progressing on the steel frame for the terminal's two wings, with completion of the main roof structure expected by this September. 
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The passenger terminal is considered the “heart” of Long Thanh Airport Phase 1. In addition to the steel roof installation, the construction units are constructing the terminal's concrete floor and main pillars.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Meanwhile, Package no.4 & 6, which covers the runway runway and the aircraft parking lot is under construction of the finishing concrete layer.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Long Thanh Airport runway package is expected to be completed by April 30, 2025, three months ahead of schedule.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Control Tower project, part of Component No. 2 and invested by the Vietnam Air Traffic Management Corporation, is also under accelerated construction.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
According to ACV, the first phase of Long Thanh International Airport is expected to be completed and enter trial operations before August 31, 2026, and is scheduled to welcome its first commercial flight on September 2, 2026.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Long Thanh Airport project, located in Long Thanh District, Dong Nai Province, is a major national investment, with a total estimated cost exceeding $16 billion, divided into three phases. Phase 1 alone represents over $5.4 billion in investment.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
The Long Thanh Airport project, located in Long Thanh District, Dong Nai Province, is a major national investment, with a total estimated cost exceeding $16 billion, divided into three phases. Phase 1 alone represents over $5.4 billion in investment.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Long Thanh Airport Phase 1 is a key national project critical to the country's socio-economic development. It includes the construction of 1 runway, 1 passenger terminal, and auxiliary works capable of handling 25 million passengers and 1.2 million tons of cargo annually.
INSTALLATION OF STEEL FRAME ROOF FOR LONG THANH AIRPORT TERMINAL
Upon completion of all three phases, Long Thanh Airport is expected to accommodate up to 100 million passengers per year, becoming the largest airport in Vietnam and aiming to become one of the centers of international aviation hubs in the region.

Source: nhandan.vn

Latest news

10 DẤU ẤN NỔI BẬT CỦA VINACONEX TRONG NĂM 2024

Bước sang năm 2024, năm bản lề, chuyển mình của giai đoạn mới, dưới sự chỉ đạo, lãnh đạo toàn diện của Đảng uỷ TCT, sự quyết liệt trong công tác quản trị, điều hành của HĐQT và Ban Tổng giám đốc, VINACONEX xác định đẩy mạnh hơn nữa công tác nghiên ...

10 DẤU ẤN NỔI BẬT CỦA VINACONEX TRONG NĂM 2024

Tổng kết hoạt động SXKD năm 2024 và định hướng triển khai nhiệm vụ năm 2025

Năm 2024, đối mặt với vô vàn thách thức, VINACONEX vẫn vững vàng vượt khó, tăng trưởng quy mô và duy trì hoạt động hiệu quả trên cả ba trụ cột là Xây dựng – Bất động sản – Đầu tư tài chính, tích cực đóng góp nhiều hơn nữa vì cộng đồng.

Tổng kết hoạt động SXKD năm 2024 và định hướng triển khai nhiệm vụ năm 2025

Hội nghị tổng kết công tác Đảng, Công đoàn, Đoàn thanh niên Tổng công ty năm 2024; triển khai nhiệm vụ trọng tâm năm 2025

Ngày 17/01/2025, Tổng công ty đã tổ chức Hội nghị Tổng kết công tác Đảng, hoạt động Công đoàn, Đoàn Thanh niên năm 2024 và triển khai nhiệm vụ trọng tâm năm 2025. Đ/c Đồng chí Đào Ngọc Thanh, Bí thư Đảng ủy chủ trì, điều hành hội nghị.

Hội nghị tổng kết công tác Đảng, Công đoàn, Đoàn thanh niên Tổng công ty năm 2024; triển khai nhiệm vụ trọng tâm năm 2025

Tổng bí thư Tô Lâm biểu dương nhà thầu Vinaconex tại dự án xây dựng Bệnh viện đa khoa tỉnh Nam Định

Sáng ngày 16/1/2025,trong khuôn khổ chuyến công tác tại tỉnh Nam Định, Tổng Bí thư Tô Lâm và Đoàn công tác Trung ương đã đến thăm và làm việc tại Dự án xây dựng Bệnh viện đa khoa tỉnh Nam Định.Dự án do UBND tỉnh Nam Định làm chủ đầu tư và TCT ...

Tổng bí thư Tô Lâm biểu dương nhà thầu Vinaconex tại dự án xây dựng Bệnh viện đa khoa tỉnh Nam Định
Loading...