Recently, a delegation led by the Secretary of the Party Committee and Chairman of Vinaconex’s Board of Directors, Dao Ngoc Thanh, visited and inspected the progress of several key projects.
The delegation visited the Van Phong-Nha Trang section of the North-South Expressway Construction Investment Project (2021-2025) that Vinaconex is a contractor in charge of Package No. XL02.
After more than a year of intensive work, Vinaconex has completed 60.8% of the in-charge work and achieved an acceptance value of 48.2%. The contractor aims to complete and hand over the package by December 31, 2024, ten months ahead of schedule.
Mr. Dao Ngoc Thanh, Chairman of the Board of Directors and Secretary of the Party Committee commended Vinaconex employees for their sense of responsibility, efforts to overcome challenges, and commitment to completing the package ahead of schedule while maintaining safety and quality standards.
As part of the scheduled work plan, Mr. Dao Ngoc Thanh, Secretary of the Party Committee and Chairman of the BOD, accompanied by Mr. Nguyen Manh Cuong, President of the Corporation's Trade Union, and the delegation, paid an inspection visit to the Thanh Cong Viet Hung Automobile Factory Complex Project in Ha Long city, Quang Ninh province. This project has the participation of Construction Joint Stock Company No. 1 (VC1), a member unit of Vinaconex Corporation.
Chairman Thanh highly appreciated VC1 for its proactive attitude to improve competitiveness and job search efforts. He emphasized the significance of prioritizing labor safety, maintaining high-quality standards, and ensuring the timely completion of the project to uphold VC1's reputation within the Vinaconex family.