COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY - Trang chủ | Vinaconex

EN

COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY

Tue , 08/10/2024, 14:00:00 (GMT+7)

After 14 months of construction, the Khanh Binh Bridge—the longest bridge on the Van Phong-Nha Trang Expressway—has been successfully completed.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Located at Km 346+756 of the Van Phong-Nha Trang expressway, the Khanh Binh Bridge has four lanes with a width of 17.5 meters, and a total length of nearly 700 meters, comprising 17 spans. The project was completed at VND 206 billion.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The bridge spans Provincial Road No. 8 and a mountainous valley in the northeast of Khanh Binh Commune, Khanh Vinh District, Khanh Hoa Province. Construction began on July 20, 2023, immediately after the site was handed over. The original contract scheduled a 34-month timeline for the bridge.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Previously, challenges arose due to the difficult terrain and the presence of thousands of square meters of forest, requiring changes in the project scope. Site clearance delays extended the project by 7 months.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The M2 pier's location in high mountains posed transportation difficulties, and geological discrepancies required additional drilling to adjust the bored pile lengths. These complications risked slowing down the overall progress of the Van Phong-Nha Trang Expressway.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Vinaconex contractor worked closely with Project Management Unit No. 7 (project’s investor) and Tram Huong Forestry One Member Co., Ltd. (forest owner) to coordinate site clearance. With approval from the Department of Agriculture and Rural Development and Khanh Hoa’s People’s Committee, the necessary areas were cleared, allowing construction to resume.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The presence of telecommunications infrastructure and a 22KV power line crossing the N2 span also created obstacles. Vinaconex collaborated with Khanh Vinh Power Company to relocate these utilities, ensuring a safe construction environment and minimizing delays.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
As the largest bridge on the expressway and a critical link for the project, the timely completion of Khanh Binh Bridge is expected to boost the overall progress of the Van Phong-Nha Trang Expressway project.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The contractor has deployed multiple teams working around the clock, including nighttime shifts. After 14 months of intensive work, the installation of the 17th-span girder has been completed, marking a major milestone—the completion of Khanh Binh Bridge. Currently, over 90% of the bridge's total construction volume has been achieved.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
According to Engineer Tran Minh Tan, project commander, the contractor has mobilized machinery, equipment, and two teams to construct the bridge deck, one team to install expansion joints, and another for assembly tasks. As the rainy season approaches, all teams have been working simultaneously to maximize productivity.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Following the completion of Khanh Binh Bridge, the contractor quickly moved on to deck construction, railing installation, and concrete pouring, with plans to begin asphalt paving soon. The aim is to finish the bridge by December 31—10 months ahead of the promised timeline.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The Van Phong - Nha Trang Expressway project, spanning 83 kilometers through four districts—Van Ninh, Ninh Hoa, Dien Khanh, and Khanh Vinh—has a total investment of over VND11,800 billion. Construction commenced in January 2023. 
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
At present, 30 construction sections are operational (21 road sections and 9 bridges), employing nearly 1,400 workers and utilizing around 800 pieces of equipment. The project has already achieved 70% of its contracted construction value and is projected for completion by April 30, 2025 (8 months ahead of schedule).
 

baogiaothong.vn

Latest news

VINACONEX và Trường Đại học Xây dựng Hà Nội khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị

Ngày 18 tháng 12 năm 2024, Tổng công ty cổ phần VINACONEX và Trường Đại học Xây dựng Hà Nội đã tổ chức lễ khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị. Đây là bước ...

VINACONEX và Trường Đại học Xây dựng Hà Nội khai giảng lớp đào tạo kỹ sư ngành kỹ thuật xây dựng công trình giao thông, chuyên ngành đường sắt tốc độ cao và đường sắt đô thị

Hội nghị nghiên cứu, quán triệt tư tưởng chỉ đạo, định hướng lớn của Đảng và Tổng Bí thư Tô Lâm về kỷ nguyên mới - Kỷ nguyên vươn mình của dân tộc

Thực hiện chỉ đạo của Trung ương, Kế hoạch 284 - KH/TU ngày 29/11/2024 của Ban Thường vụ Thành uỷ Hà Nội, ngày 16/12/2024, Ban Thường vụ Đảng ủy Tổng công ty tổ chức Hội nghị nghiên cứu, quán triệt tư tưởng chỉ đạo, định hướng lớn của Đảng và Tổng ...

Hội nghị nghiên cứu, quán triệt tư tưởng chỉ đạo, định hướng lớn của Đảng và Tổng Bí thư Tô Lâm về kỷ nguyên mới - Kỷ nguyên vươn mình của dân tộc

Vinaconex được bình chọn Top 2 nơi làm việc tốt nhất Việt Nam 2024 - Ngành xây dựng

Chiều 12/12/2024, tại Hà Nội, trong khuôn khổ Lễ công bố Bảng xếp hạng Top 500 doanh nghiệp tạo giá trị hàng đầu Việt Nam, VINACONEX tiếp tục được bình chọn và vinh danh TOP 2 nơi làm việc tốt nhất Việt Nam 2024 VBW10 – Ngành Xây dựng

Vinaconex được bình chọn Top 2 nơi làm việc tốt nhất Việt Nam 2024 - Ngành xây dựng

Vinaconex vinh dự là đơn vị đầu tiên hoàn thành cất nóc kết cấu thép mái nhà ga cảng HKQT Long Thành

Đã gần 4 năm kể từ ngày khởi công Cảng hàng không Quốc tế Long Thành, Nhà ga hành khách - “trái tim” của siêu dự án đang ngày một hoàn thiện và lộ rõ hình hài. Trên công trường, Vinaconex cùng các nhà thầu thuộc Liên danh VIETUR đang khẩn trương ...

Vinaconex vinh dự là đơn vị đầu tiên hoàn thành cất nóc kết cấu thép mái nhà ga cảng HKQT Long Thành
Loading...