COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY

Tue , 08/10/2024, 14:00:00 (GMT+7)

After 14 months of construction, the Khanh Binh Bridge—the longest bridge on the Van Phong-Nha Trang Expressway—has been successfully completed.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Located at Km 346+756 of the Van Phong-Nha Trang expressway, the Khanh Binh Bridge has four lanes with a width of 17.5 meters, and a total length of nearly 700 meters, comprising 17 spans. The project was completed at VND 206 billion.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The bridge spans Provincial Road No. 8 and a mountainous valley in the northeast of Khanh Binh Commune, Khanh Vinh District, Khanh Hoa Province. Construction began on July 20, 2023, immediately after the site was handed over. The original contract scheduled a 34-month timeline for the bridge.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Previously, challenges arose due to the difficult terrain and the presence of thousands of square meters of forest, requiring changes in the project scope. Site clearance delays extended the project by 7 months.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The M2 pier's location in high mountains posed transportation difficulties, and geological discrepancies required additional drilling to adjust the bored pile lengths. These complications risked slowing down the overall progress of the Van Phong-Nha Trang Expressway.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Vinaconex contractor worked closely with Project Management Unit No. 7 (project’s investor) and Tram Huong Forestry One Member Co., Ltd. (forest owner) to coordinate site clearance. With approval from the Department of Agriculture and Rural Development and Khanh Hoa’s People’s Committee, the necessary areas were cleared, allowing construction to resume.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The presence of telecommunications infrastructure and a 22KV power line crossing the N2 span also created obstacles. Vinaconex collaborated with Khanh Vinh Power Company to relocate these utilities, ensuring a safe construction environment and minimizing delays.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
As the largest bridge on the expressway and a critical link for the project, the timely completion of Khanh Binh Bridge is expected to boost the overall progress of the Van Phong-Nha Trang Expressway project.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The contractor has deployed multiple teams working around the clock, including nighttime shifts. After 14 months of intensive work, the installation of the 17th-span girder has been completed, marking a major milestone—the completion of Khanh Binh Bridge. Currently, over 90% of the bridge's total construction volume has been achieved.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
According to Engineer Tran Minh Tan, project commander, the contractor has mobilized machinery, equipment, and two teams to construct the bridge deck, one team to install expansion joints, and another for assembly tasks. As the rainy season approaches, all teams have been working simultaneously to maximize productivity.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
Following the completion of Khanh Binh Bridge, the contractor quickly moved on to deck construction, railing installation, and concrete pouring, with plans to begin asphalt paving soon. The aim is to finish the bridge by December 31—10 months ahead of the promised timeline.
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
The Van Phong - Nha Trang Expressway project, spanning 83 kilometers through four districts—Van Ninh, Ninh Hoa, Dien Khanh, and Khanh Vinh—has a total investment of over VND11,800 billion. Construction commenced in January 2023. 
COMPLETION OF THE LONGEST BRIDGE ON THE VAN PHONG–NHA TRANG EXPRESSWAY
At present, 30 construction sections are operational (21 road sections and 9 bridges), employing nearly 1,400 workers and utilizing around 800 pieces of equipment. The project has already achieved 70% of its contracted construction value and is projected for completion by April 30, 2025 (8 months ahead of schedule).
 

baogiaothong.vn

Latest news

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Ngày 24-6, phường Láng tổ chức Hội nghị công bố quyết định chuyển giao, tiếp nhận tổ chức Đảng và đảng viên đối với Đảng bộ Tổng công ty Đầu tư nước và Môi trường Việt Nam Viwaseen . Sự kiện đánh dấu một bước đi cụ thể nhằm kiện toàn tổ chức, tăng ...

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Hội nghị công bố quyết định chuyển giao, tiếp nhận Đảng bộ VIWASEEN về trực thuộc Đảng bộ VINACONEX

Thực hiện Nghị quyết số 1952-QĐ/TU của Ban Thường vụ Thành ủy Hà Nội, ngày 24/6/2026, Ban Thường vụ Đảng ủy phường Láng và Đảng ủy Tổng công ty CP VINACONEX đã tổ chức Hội nghị công bố quyết định chuyển giao Đảng bộ Tổng công ty Đầu tư Nước và Môi ...

Hội nghị công bố quyết định chuyển giao, tiếp nhận Đảng bộ VIWASEEN về trực thuộc Đảng bộ VINACONEX

Nghiên cứu quy hoạch mỏ vật liệu phục vụ riêng dự án cao tốc trọng điểm

Trong bối cảnh nhiều dự án giao thông triển khai đồng loạt, việc quy hoạch, phân định rõ các mỏ vật liệu phục vụ dự án cao tốc trọng điểm quốc gia được đánh giá là cần thiết để đáp ứng tiến độ, chất lượng theo kế hoạch yêu cầu.

Nghiên cứu quy hoạch mỏ vật liệu phục vụ riêng dự án cao tốc trọng điểm

SIGNING CEREMONY MARKS TRANSFER OF VIWASEEN PARTY ORGANIZATION RECORDS TO VINACONEX PARTY COMMITTEE

A formal handover ceremony was held to transfer the Party organization records and membership roster of VIWASEEN's Party Committee to VINACONEX's Party Committee. The move marks an important step in strengthening Party leadership and ensuring unified ...

SIGNING CEREMONY MARKS TRANSFER OF VIWASEEN PARTY ORGANIZATION RECORDS TO VINACONEX PARTY COMMITTEE
Loading...