EN

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

Thu , 12/08/2021, 10:40:00 (GMT+7)

 

As a key project of Hanoi, Vinh Tuy Bridge (phase II) is one of six traffic projects permitted by the city to be constructed during the social distancing period to ensure timely completion. Vinaconex contractor and construction units at the project have been trying their best to race against time to finish the project on schedule.

 By design, Vinh Tuy bridge (phase II) runs parallel to Vinh Tuy bridge, currently downstream of the Red River.

Vinh Tuy bridge construction investment project (phase II) is one of the capital's arterial traffic projects, playing an important role in completing the entire Ring Road 2 of Hanoi, strengthening traffic between the two banks of the Red River, meeting the rapidly increasing transport demand between the center of the capital and the northern and northeastern areas of the city.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing .

Vinh Tuy bridge construction investment project (phase II) seen from above

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.

Execution of bored piles T21HL and T22HL – Package 01/VT2 - XL

At Vinh Tuy Bridge construction investment project (phase II), Vinaconex was honored to be selected as a participant in Package 05/VT2 – XL (Vinaconex Joint Venture – 75 Bridge Construction Joint Stock Company) to construct the bridge. Long Bien direction and path, implementation time is 18 months; Package 01/VT2 - XL (Vinaconex - Trung Chinh Joint Venture) construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing      
 
Ensure safety and techniques at construction items on the water surface
 
On the project site, the contractors mobilized 1,000-2,000-ton barges and 4 drilling rigs with floating systems to prepare for the construction of the pile foundation in the middle of the Red River.
Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing    

 Construction of C6 pile T24 HL                          

Construction of lowering steel cage C6 – T24HL

The project currently has about 500 workers divided into 11 stitches, constructing 3 consecutive shifts at the construction site with strict Covid-19 disease prevention and control conditions. The workers are organized to work, live in a concentrated place, do not contact the outside, do not go out of the construction site, strictly comply with 5K.

     Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

 The Executive Board organizes and directs the implementation of 3 consecutive shifts of construction

Compliance with safety regulations for disease prevention is a mandatory condition at the project
  

 All workers must wear masks during work; arranged at distance, staggered eating and drinking hours to reduce concentration.

Overview of construction of bridge piers on the river.

As planned, the whole project will be completed in the second quarter of 2023.

Latest news

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Ngày 24-6, phường Láng tổ chức Hội nghị công bố quyết định chuyển giao, tiếp nhận tổ chức Đảng và đảng viên đối với Đảng bộ Tổng công ty Đầu tư nước và Môi trường Việt Nam Viwaseen . Sự kiện đánh dấu một bước đi cụ thể nhằm kiện toàn tổ chức, tăng ...

Phường Láng: Tiếp nhận tổ chức Đảng và đảng viên Tổng công ty Đầu tư nước và Môi trường Việt Nam

Hội nghị công bố quyết định chuyển giao, tiếp nhận Đảng bộ VIWASEEN về trực thuộc Đảng bộ VINACONEX

Thực hiện Nghị quyết số 1952-QĐ/TU của Ban Thường vụ Thành ủy Hà Nội, ngày 24/6/2026, Ban Thường vụ Đảng ủy phường Láng và Đảng ủy Tổng công ty CP VINACONEX đã tổ chức Hội nghị công bố quyết định chuyển giao Đảng bộ Tổng công ty Đầu tư Nước và Môi ...

Hội nghị công bố quyết định chuyển giao, tiếp nhận Đảng bộ VIWASEEN về trực thuộc Đảng bộ VINACONEX

Nghiên cứu quy hoạch mỏ vật liệu phục vụ riêng dự án cao tốc trọng điểm

Trong bối cảnh nhiều dự án giao thông triển khai đồng loạt, việc quy hoạch, phân định rõ các mỏ vật liệu phục vụ dự án cao tốc trọng điểm quốc gia được đánh giá là cần thiết để đáp ứng tiến độ, chất lượng theo kế hoạch yêu cầu.

Nghiên cứu quy hoạch mỏ vật liệu phục vụ riêng dự án cao tốc trọng điểm

SIGNING CEREMONY MARKS TRANSFER OF VIWASEEN PARTY ORGANIZATION RECORDS TO VINACONEX PARTY COMMITTEE

A formal handover ceremony was held to transfer the Party organization records and membership roster of VIWASEEN's Party Committee to VINACONEX's Party Committee. The move marks an important step in strengthening Party leadership and ensuring unified ...

SIGNING CEREMONY MARKS TRANSFER OF VIWASEEN PARTY ORGANIZATION RECORDS TO VINACONEX PARTY COMMITTEE
Loading...