Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

Thu , 12/08/2021, 10:40:00 (GMT+7)

 

As a key project of Hanoi, Vinh Tuy Bridge (phase II) is one of six traffic projects permitted by the city to be constructed during the social distancing period to ensure timely completion. Vinaconex contractor and construction units at the project have been trying their best to race against time to finish the project on schedule.

 By design, Vinh Tuy bridge (phase II) runs parallel to Vinh Tuy bridge, currently downstream of the Red River.

Vinh Tuy bridge construction investment project (phase II) is one of the capital's arterial traffic projects, playing an important role in completing the entire Ring Road 2 of Hanoi, strengthening traffic between the two banks of the Red River, meeting the rapidly increasing transport demand between the center of the capital and the northern and northeastern areas of the city.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing .

Vinh Tuy bridge construction investment project (phase II) seen from above

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.

Execution of bored piles T21HL and T22HL – Package 01/VT2 - XL

At Vinh Tuy Bridge construction investment project (phase II), Vinaconex was honored to be selected as a participant in Package 05/VT2 – XL (Vinaconex Joint Venture – 75 Bridge Construction Joint Stock Company) to construct the bridge. Long Bien direction and path, implementation time is 18 months; Package 01/VT2 - XL (Vinaconex - Trung Chinh Joint Venture) construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing      
 
Ensure safety and techniques at construction items on the water surface
 
On the project site, the contractors mobilized 1,000-2,000-ton barges and 4 drilling rigs with floating systems to prepare for the construction of the pile foundation in the middle of the Red River.
Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing    

 Construction of C6 pile T24 HL                          

Construction of lowering steel cage C6 – T24HL

The project currently has about 500 workers divided into 11 stitches, constructing 3 consecutive shifts at the construction site with strict Covid-19 disease prevention and control conditions. The workers are organized to work, live in a concentrated place, do not contact the outside, do not go out of the construction site, strictly comply with 5K.

     Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

 The Executive Board organizes and directs the implementation of 3 consecutive shifts of construction

Compliance with safety regulations for disease prevention is a mandatory condition at the project
  

 All workers must wear masks during work; arranged at distance, staggered eating and drinking hours to reduce concentration.

Overview of construction of bridge piers on the river.

As planned, the whole project will be completed in the second quarter of 2023.

Latest news

Sôi nổi các hoạt động chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX

Hướng tới kỷ niệm 38 năm thành lập Tổng công ty VINACONEX 27/9/1988 – 27/9/2026 , chuỗi hoạt động văn hóa, thể thao đã chính thức được phát động trên toàn hệ thống. Đây không chỉ là sân chơi giao lưu, gắn kết dành cho cán bộ, người lao động, mà còn ...

Sôi nổi các hoạt động chào mừng kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX

VINACONEX phát động chuỗi hoạt động V-SAFETY: Lan tỏa văn hóa an toàn trên mọi công trường

Hướng tới kỷ niệm 38 năm thành lập Tổng công ty CP VINACONEX 27/9/1988 – 27/9/2026 , từ ngày 01/8/2026, VINACONEX triển khai chuỗi hoạt động V-SAFETY với hành trình 150 ngày an toàn kéo dài đến hết năm 2026. Đây là một trong những chương trình trọng ...

VINACONEX phát động chuỗi hoạt động V-SAFETY: Lan tỏa văn hóa an toàn trên mọi công trường

VINACONEX tham dự chương trình huấn luyện dân quân tự vệ Cụm số 2 - Phường Láng năm 2026

Chương trình huấn luyện lực lượng tự vệ Cụm số 2 do Ban Chỉ huy Quân sự phường Láng tổ chức là hoạt động thường niên nhằm nâng cao bản lĩnh chính trị, trình độ quân sự và khả năng sẵn sàng thực hiện nhiệm vụ của lực lượng tự vệ thuộc VINACONEX và các ...

VINACONEX tham dự chương trình huấn luyện dân quân tự vệ Cụm số 2 - Phường Láng năm 2026

V-SAFETY SỐ 18 | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN

V-SAFETY | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN

V-SAFETY SỐ 18 | NHỮNG ĐIỀU TUYỆT ĐỐI KHÔNG ĐƯỢC LÀM KHI SỬ DỤNG THIẾT BỊ ĐIỆN
Loading...