SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Wed , 14/07/2021, 08:52:21 (GMT+7)

With the aim to complete the entire Ring Road 2, over the past time, the workers at the Vinh Tuy Bridge phase 2 project have been working actively all day and night. 

Vinh Tuy Bridge phase 2 has a total investment of over VND 2,500 billion. The bridge has a total length of more than 3.4 kilometers including the approaches, with a surface width of 19.25 meters (4 lanes), and a static height of 11 meters.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Sharing to the reporters, Mr. Do Viet Thang, Managing Director of Package 5 said: “We’re now working on the T74HL and T76H L pillars in package 5, involving about 30 officers and workers. The construction site has 2 construction sections working in 3 consecutive shifts. It’s estimated that we have reached 25% of the total workload.”

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Due to the complicated evolution of the Covid-19 pandemic, the contractor has added a lot of indicators at the Ministry of Health's request as well as for all propagating to workers not to gather outside the construction site, having meals right inside camps in shifts, and following social distancing.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The hot summer heat had a great impact on the construction work. The contractors assisted the workers by managing extra night shifts, Mr. Thang added.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The bridge was designed with permanent reinforced concrete and prestressed concrete structures with design load HL-93, and could withstand earthquakes of grade 8 in accordance to TCVN11823-2017. Even though the underground construction site was covered up and the pumps were also set up, it would still be very challenging in case of heavy rain causing flooding.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

On the construction site of the Le Van Luong - Khuat Duy Tien underpass, dozens of workers were in rush to deploy pile pressing of pumping station construction before the rainy season arrived.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Le Van Luong - Khuat Duy Tien underpass project was kicked off in October 2020 with a total investment of nearly VND700 billion, and scheduled for completion after months. This 475-meter-long underpass is made of a reinforced concrete structure in the direction of Le Van Luong - To Huu street, including a 95-meter underground tunnel and 380 meters of access and exit ramps (each ramp is 190 meters long).

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Engineer Tran Phuong Nam, in charge of the project site, shared with the reporters that there were 50 – 60 permanent workers working urgently in 9 construction sections to complete two underground culverts for water drainage in the upcoming rainy season.

He also mentioned that every morning, all employees and workers had to measure body temperature, disinfect hands and put on masks before entering the construction site. There was also a monitor group to watch over and record every person entering and departing the site in order to prevent the Covid-19 pandemic.

The underground culverts item, which has been 95% completed, is considered very important to the project.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

As the reporter noted, the narrowing of both sidewalks was executed by workers to broaden the 315-meter length of Le Van Luong street, and the 390-meter length of To Huu street.

Latest news

Phấn đấu thông xe nút giao hiện đại bậc nhất trên cao tốc Cầu Giẽ - Ninh Bình

Tại Công trường xây dựng Nút giao Phú Thứ tỉnh Ninh Bình , hơn 100 cán bộ, kỹ sư và công nhân của liên danh VINACONEX - TRUNG CHÍNH đang làm làm ngày, làm đêm xuyên Lễ tết; phấn đấu hoàn thành dự án vào đầu tháng 9/2025 để chào mừng Đại hội Đảng bộ ...

Phấn đấu thông xe nút giao hiện đại bậc nhất trên cao tốc Cầu Giẽ - Ninh Bình

Hành trình về nguồn của Tổng công ty CP VINACONEX

Chào mừng thành công Đại hội Đảng bộ Tổng công ty CP Vinaconex lần thứ VI, nhiệm kỳ 2025–2030, đồng thời hướng tới kỷ niệm 78 năm Ngày Thương binh – Liệt sĩ 27/7/1947 – 27/7/2025 , Công đoàn Tổng công ty CP VINACONEX đã tổ chức hành trình về nguồn ...

Hành trình về nguồn của Tổng công ty CP VINACONEX

Thông báo VINACONEX không còn mối liên quan nào đến Công ty Cổ phần Đầu tư Xây dựng và Phát triển Hạ tầng Vinaconex (Vinaconex 34)

Thông báo VINACONEX không còn mối liên quan nào đến Công ty Cổ phần Đầu tư Xây dựng và Phát triển Hạ tầng Vinaconex Vinaconex 34

Thông báo VINACONEX không còn mối liên quan nào đến Công ty Cổ phần Đầu tư Xây dựng và Phát triển Hạ tầng Vinaconex (Vinaconex 34)

VINACONEX lọt Top 500 doanh nghiệp lớn nhất Đông Nam Á năm 2025

Trong số 76 đại diện Việt Nam được ghi danh tại bảng xếp hạng Fortune Southeast Asia 500 năm 2025 Fortune SEA 500 , Tổng công ty CP Xuất nhập khẩu và Xây dựng Việt Nam – VINACONEX HOSE VCG lần đầu tiên góp mặt, đánh dấu bước tiến quan trọng trong ...

VINACONEX lọt Top 500 doanh nghiệp lớn nhất Đông Nam Á năm 2025
Loading...