PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE

Tue , 13/02/2024, 16:00:00 (GMT+7)

On February 13, Prime Minister Pham Minh Chinh, accompanied by Deputy Prime Minister Tran Hong Ha and leaders from various central and Dong Nai provincial ministries and departments, inspected the Long Thanh airport project.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
PM Pham Minh Chinh inspected the runway item (photo: LE LAM)

During the inspection, PM Chinh inspected two pivotal components of the project—the passenger terminal and the runway. Initiated on August 31, 2023, these are the two largest, most important, and most complex items in phase 1.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Extending New Year greetings to contractors (photo: LE LAM)

Reporting to PM Chinh, leaders of the Airports Corporation of Vietnam (ACV - Investor) stated that the runway spans 4,000 meters in length and 75 meters in width, with the taxiway system (including parallel taxiways, rapid exit taxiways, and connecting taxiways) measuring 44 meters wide.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Prime Minister gave lucky money to engineers and workers at the construction site (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Runway and passenger terminal at Long Thanh Airport project (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
PM Pham Minh Chinh inspected the runway construction project (photo: LE LAM)

Immediately following the groundbreaking ceremony, the contractor joint venture swiftly mobilized thousands of personnel, along with a plethora of equipment and machinery, to expedite the project's construction. Even during the Lunar New Year, the contractors maintained a workforce of nearly 300 personnel on-site.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
The Prime Minister encouraged and motivated the staff working on the construction site (photo: LE LAM)

In the interview with Thanh Nien newspaper, Mr. Nguyen Hoai Giang, General Director of Vietnam Construction Investment Development Joint Stock Company (VINADIC), a key member of the contractor joint venture, stated that they have allocated all resources, including experts, technical staff, workers, machinery, and equipment, to meet and exceed the project schedule required by the investor.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
The runway work is going to be completed by June 2025, as stated in the plan. (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
The lotus-shaped design of the passenger terminal has gradually emerged. (photo: LE LAM)
PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Lotus-shaped design of Long Thanh airport terminal (photo: LE LAM)

In the project, 24 tower cranes are working non-stop to handle all the materials & equipment transfers throughout the entire project site.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
PM Pham Minh Chinh visited the passenger terminal to encourage contractors and workers (photo: LE LAM).

ACV and the Contractor Joint Venture have strived to finish all construction by December 2025, completed facade installation by March 2026, and installed trial operation equipment starting in early 2026.

PRIME MINISTER PHAM MINH CHINH'S NEW YEAR INSPECTION AT THE LONG THANH AIRPORT CONSTRUCTION SITE
Deputy Prime Minister Tran Hong Ha gave lucky money to engineers and workers at the construction site of Long Thanh Airport’s passenger terminal.

The airport spans 5,000 hectares in Long Thanh district, Dong Nai province, and its phase 1 construction began in January 2021. It is expected that Long Thanh Airport would be operational by 2026, able to cater to 25 million passengers and handle 1.2 million tons of cargo each year.

(Source: thanhnien.vn)


 

Latest news

VINACONEX vượt khó thi công cầu vượt Sông Hồng

Cầu vượt Sông Hồng thuộc Gói thầu B.02, Km46+932, tuyến cao tốc Ninh Bình – Hải Phòng, đoạn qua Nam Định và Thái Bình, đang từng bước hình thành. Trong điều kiện thi công phức tạp trên sông, VINACONEX tập trung nguồn lực, tổ chức đồng thời nhiều mũi ...

VINACONEX vượt khó thi công cầu vượt Sông Hồng

Phó Thủ tướng Thường trực Chính phủ kiểm tra tiến độ Dự án Cảng HKQT Long Thành

Sáng 4/10, Ủy viên Bộ Chính trị, Phó Thủ tướng Thường trực Chính phủ Phạm Gia Túc dẫn đầu Đoàn công tác kiểm tra tiến độ xây dựng Dự án Cảng HKQT Long Thành và các tuyến giao thông kết nối. Tổng Giám đốc Tổng công ty Phạm Thái Dương cùng Ban Điều ...

Phó Thủ tướng Thường trực Chính phủ kiểm tra tiến độ Dự án Cảng HKQT Long Thành

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

38 năm hình thành và phát triển là hành trình được tạo nên bởi bản lĩnh, trí tuệ, sự bền bỉ và tinh thần đoàn kết của nhiều thế hệ người lao động VINACONEX. Từ những giá trị được vun đắp qua năm tháng, Tổng công ty hôm nay tiếp tục đổi mới, nâng cao ...

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

Tổng công ty CP VINACONEX vừa tiếp nhận lô thiết bị máy khoan cọc nhồi SANY SR235 và SANY SR285R, bổ sung nguồn lực thiết bị hiện đại, góp phần nâng cao năng lực thi công nền móng và tăng tính chủ động trong triển khai các dự án quy mô lớn.

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công
Loading...