PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS

Tue , 03/12/2024, 17:00:00 (GMT+7)

On the morning of December 3, Politburo member and Prime Minister Pham Minh Chinh conducted an inspection of the Long Thanh International Airport construction site and its connecting traffic infrastructure. 

Joining Prime Minister Pham Minh Chinh at the working session were members of the Party Central Committee, Deputy Prime Ministers Tran Hong Ha and Ho Duc Phoc, along with representatives from central ministries and agencies.
 

PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS
PM Chinh inspected Long Thanh International Airport Construction Progress

At the Long Thanh airport project site in Long Thanh district, Dong Nai province, Prime Minister Chinh and his delegation inspected the progress of package no. 6.12 (construction of two airport connecting roads), package no. 5.10 (passenger terminal construction and equipment installation), and package no. 4.6 (construction of airport runway).

PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS
This marks the fifth on-site inspection of the Long Thanh International Airport project by the Prime Minister
PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS
PM Pham Minh Chinh visited, encouraged and presented gifts to the officers, engineers and workers working at the Long Thanh airport construction site

According to reports at the working session, component project no.2 (Air Traffic Control Tower) has the reinforced concrete structure completed, with ongoing work on the tower extension beyond the 15th floor. As for component project no.3 (Passenger Terminal), the reinforced concrete work is 100% complete, with finishing works now underway. The runway construction progress is reportedly three months ahead of the contractual schedule, etc.

PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS
PM Chinh and the Central working delegation worked on the progress of the Long Thanh airport project.

During the working session, PM Chinh expressed concern over inconsistencies and a lack of synchronization in task execution at the construction site. He urged stakeholders to establish a critical path, adhere to a rolling schedule, and maintain close, rhythmic coordination to accelerate progress.

He also assigned Deputy Prime Minister Tran Hong Ha to directly oversee and conduct monthly inspections to ensure timelines are met. The Ministry of Transport and relevant agencies shall prioritize the implementation of Component Project No. 4 to ensure its completion aligns with Component Project No. 3 and other component projects.

Some photos at package no. 5.10 Construction and installation of equipment for the Passenger Terminal project.

PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS
PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS
PM INSPECTS LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION PROGRESS

At the Long Thanh airport construction project, Vinaconex is honored to be the first contractor to complete the steel roof structure for the Long Thanh terminal steel structure.

Package No. 5.10 Construction and Installation of Passenger Terminal Equipment under the Component No. 3 project of the Long Thanh International Airport (phase 1).

In the assigned work, contractor VINACONEX, under the Vietur consortium, has successfully completed 100% of the underground structure and the reinforced concrete work for floors 1F, 2F, 3F, and 4F

In the central area and the wing area, the fabrication of the basic roof structure has been finalized.

In December, VINACONEX contractor accelerated progress on erecting steel structures, including main trusses, braces, and purlins, in both the central and wing areas of the terminal while simultaneously working on the ground floor slab.

The Long Thanh Airport Passenger Terminal, comprising one ground floor and three upper levels, has a total investment of approximately VND 35 trillion. Construction began on August 31, 2023. Currently, the join venture is operating tirelessly, day and night, with a commitment to rapid construction, aimingto complete the project while ensuring high quality and adherence to the timeline


 


 


 

Latest news

Khởi công Khu công nghiệp Đông Anh, kiến tạo không gian công nghiệp thế hệ mới

Sáng 20/5, Vinaconex phối hợp cùng UBND TP Hà Nội tổ chức lễ khởi công Dự án đầu tư xây dựng và kinh doanh kết cấu hạ tầng Khu công nghiệp Đông Anh.

Khởi công Khu công nghiệp Đông Anh, kiến tạo không gian công nghiệp thế hệ mới

VINACONEX khởi công Khu công nghiệp Đông Anh – Kiến tạo không gian công nghiệp thế hệ mới phía Bắc Thủ đô

Khu công nghiệp Đông Anh quy mô gần 300ha, tổng mức đầu tư hơn 6.300 tỷ đồng sẽ được VINACONEX phát triển theo mô hình khu công nghiệp thế hệ mới sinh thái – thông minh – công nghệ cao, kỳ vọng trở thành động lực tăng trưởng mới phía Bắc Thủ đô và ...

VINACONEX khởi công Khu công nghiệp Đông Anh – Kiến tạo không gian công nghiệp thế hệ mới phía Bắc Thủ đô

HỘI NGHỊ RÀ SOÁT, BỔ SUNG QUY HOẠCH CÁC CHỨC DANH CẤP UỶ ĐẢNG BỘ TỔNG CÔNG TY VINACONEX NHIỆM KỲ 2025 - 2030

Thực hiện Kế hoạch số 32-KH/ĐU của Đảng uỷ phường Láng, ngày 15/5/2026, Đảng uỷ Tổng công ty CP VINACONEX tổ chức Hội nghị rà soát, bổ sung quy hoạch các chức danh cấp uỷ Tổng công ty nhiệm kỳ 2025 - 2030. Đồng chí Trần Đình Tuấn – Phó Bí thư Đảng uỷ ...

HỘI NGHỊ RÀ SOÁT, BỔ SUNG QUY HOẠCH CÁC CHỨC DANH CẤP UỶ ĐẢNG BỘ TỔNG CÔNG TY VINACONEX NHIỆM KỲ 2025 - 2030

VINACONEX cùng Ngành xây dựng hưởng ứng tháng hành động về ATVSLĐ và tháng công nhân năm 2026

Hưởng ứng Tháng hành động về An toàn, vệ sinh lao động ATVSLĐ và Tháng Công nhân năm 2026, Tổng công ty CP VINACONEX tiếp tục khẳng định cam kết xây dựng môi trường làm việc an toàn, lấy người lao động làm trung tâm, hướng tới phát triển bền vững ...

VINACONEX cùng Ngành xây dựng hưởng ứng tháng hành động về ATVSLĐ và tháng công nhân năm 2026
Loading...