06/08/2023
06/08/2023
Chairman of the Board, Mr. Dao Ngoc Thanh requested that PMU no.1 direct the executive board of the joint venture for package no. 10 to adhere to regulations on quality and technical standards and ensure progress as specified in the contract with the investor
26/05/2023
26/05/2023
After 2 years of construction, a number of items under Vinh Tuy bridge project phase 2 has been completed. The KN5, the final and most important section spanning the main stream is expected to be joined on May 30, 2023 as scheduled. That serves as the basis for the Vinh Tuy Bridge project phase 2 to be put into operation in October 2023.
18/05/2023
18/05/2023
Due to the significant impact of the COVID-19 epidemic and certain external factors, there has been an increase in the price of materials compared to the time of bidding. However, through relentless efforts to overcome all obstacles, Vinaconex and the contractor joint venture have managed to maintain the progress of the Ialy hydropower project.
06/04/2023
06/04/2023
The goal of putting Vinh Hao - Phan Thiet and Phan Thiet - Dau Giay expressways into operation by April 30, 2023, remains unchanged and is the latest requirement from The Ministry of Transport to the relevant contractors and units. In order to meet the set progress, Vinaconex contractor has been deploying all available human resources, machinery, and equipment to complete the remaining items.
18/03/2023
18/03/2023
From the beginning of the year, the contractors have carried out all construction and installation packages of the Vung Ang 2 Thermal Power Plant construction project concurrently. Especially, the items of package B in Vinaconex’s charge are always accelerated with the aim to be completed and handed over by April 2024 as scheduled.
22/02/2023
22/02/2023
Green Diamond high-class apartment and office complex building locates at 93 Lang Ha Street, a prime location in Dong Da District, Hanoi. Green Diamond offers not just elegantly built, modern apartments, but also fully 5-star quality facilities & services.
07/01/2023
07/01/2023
On the Long Thanh airport construction site, the Vinaconex contractor had been deploying over 600 specilized vehicles & machinery, 735 workers and engineers to routinely perform in three shifts, taking advantage of favourable weather and 24-hour overtime to accelerate progress.
19/11/2022
19/11/2022
To ensure that the Long Thanh International Airport project progresses as planned, the leaders of the Ministry of Transport asked the People's Committee of Dong Nai province to give special attention to supporting and accelerating the execution of Long Thanh international airport project - Phase 1.
>