TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

Thu , 17/07/2025, 09:32:00 (GMT+7)

At the construction site of the Phu Thu Interchange (Ninh Binh Province), over 100 engineers, technicians, and workers from the VINACONEX–Trung Chinh joint venture are working around the clock, through holidays, striving to complete the project by early September 2025, in celebration of the 21st Party Congress of Ninh Binh Province.

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
Phu Thu Interchange the most advanced traffic infrastructure project on Cau Gie to Ninh Binh section under the North - South Expressway, with a total investment of VND 1.4 trillion. It is being built by the joint venture of Vietnam Import-Export and Construction Corporation (VINACONEX) and Trung Chinh Trading and Construction Co., Ltd.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
The interchange is designed as a three-level grade-separated interchange. Level 1 consists of a tunnel on the Cau Gie – Ninh Binh expressway with six lanes, designed speed of up to 120 km/h. Level 2 features a roundabout with a 40-meter radius and four standard branch roads (Class-III delta roads). Level 3 is an overpass for the Ring Road No. 5 - Hanoi Capital Region crossing above the expressway.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
Construction began in May 2023, due to the high traffic volume on the Phap Van - Cau Gie Expressway, the project has been divided into three phases (Phase 1 involved building two temporary highway ramps to facilitate tunnel construction; Phase 2 focuses on the tunnel itself; and Phase 3 includes completion of all remaining components). According to the contract, the entire project is slated for completion by the end of 2025. However, construction progress has significantly accelerated, the tunnel is expected to open to traffic by July 2025 (marking the end of Phase 2), and all remaining works - including 04 toll stations, the roundabout, utility trench, road signs, and landscaping are projected to be completed by September 2025, three months ahead of schedule.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
As of early July, both the closed and open-cut tunnel sections of the project have been completed. Final works such as road surface finishing, guardrail installation, road marking, and lighting systems are being carried out in parallel to enable vehicle access through the tunnel in this month.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
At both tunnel entrances, VINACONEX’s two construction teams are paving the surface simultaneously from each end toward the center.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
Mr. Cao Van Hung, on-site engineer of VINACONEX, shared: “Our remaining tasks include paving the entrances and the tunnel interior, painting road markings, and installing traffic safety systems. We have completed asphalt layers C25, C19, and C12.5, and are now applying the anti-skid top layer on both the tunnel entrances and within the tunnel. If the weather holds, paving should be finished by mid-July. We aim to complete all works by July 30, meeting all technical requirements for traffic opening. To meet this milestone, we currently have four teams with over 50 engineers and workers working nonstop 24/7.”
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
While contractors are ramping up manpower and machinery to accelerate progress, Construction Investment Project Management Board – Ha Nam province is simultaneously preparing necessary documents for submission to the Department for Roads of Vietnam, the Ministry of Construction, aiming for timely inspection and approval to open the tunnel to traffic within July. Given the current pace, the investor and contractors are confident the project will be completed 3 - 4 months ahead of schedule, opening to traffic in July and reaching full completion by September 2025. The interchange is a key infrastructure project to welcome the 21st Party Congress of Ninh Binh province.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
As for Trung Chinh’s scope of work, the contractor has completed four tunnel segments totaling 320 meters of closed tunnel and 260 meters of open-cut tunnel. Teams are now painting tunnel walls, shaping slopes on the northern approach, and installing lighting systems and steel guardrails in preparation for road surfacing.
TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY
Upon completion, Phu Thu Interchange will connect to the Cau Gie - Ninh Binh expressway (part of the planned Ring Road No. 5) at the northern gateway of Phu Ly City. The project plays a critical role in forming the eastern-western backbone of the province, contributing to the development of inter-regional transport networks, and enhancing economic cooperation between Ninh Binh and neighboring provinces.

 

 

 

Latest news

Phấn đấu đưa tuyến chính cao tốc La Sơn - Hòa Liên vào khai thác từ giữa tháng 8 năm 2026

Bám sát chỉ đạo của Bộ trưởng Bộ Xây dựng Trần Hồng Minh về việc hoàn thành toàn bộ các hạng mục trên tuyến chính cao tốc La Sơn – Hòa Liên trước ngày 15/8/2026, VINACONEX đang tập trung nhân lực, thiết bị, tổ chức nhiều mũi thi công liên tục, quyết ...

Phấn đấu đưa tuyến chính cao tốc La Sơn - Hòa Liên vào khai thác từ giữa tháng 8 năm 2026

Nút giao Vành đai 3,5 - Đại lộ Thăng Long: Giữ vững mạch giao thông, tăng tốc về đích

Giữa dòng phương tiện không ngừng lưu thông trên Đại lộ Thăng Long, công trường nút giao Vành đai 3,5 vẫn sôi động bất kể ngày đêm. VINACONEX và Liên danh Thăng Long đang tập trung mọi nguồn lực thi công dự án bảo đảm an toàn, chất lượng, đưa dự án ...

Nút giao Vành đai 3,5 - Đại lộ Thăng Long: Giữ vững mạch giao thông, tăng tốc về đích

VINACONEX tăng tốc thi công cao tốc Hòa Bình

Với tinh thần trách nhiệm và quyết tâm cao nhất, cán bộ, kỹ sư và người lao động VINACONEX đang ngày đêm bám sát công trường, duy trì tiến độ tích cực, phấn đấu đưa cao tốc Hoà Bình - Mộc Châu về đích đúng kế hoạch.

VINACONEX tăng tốc thi công cao tốc Hòa Bình

VINACONEX đua tiến độ trên cao tốc Tuyên Quang – Hà Giang

Sau gần 3 năm nỗ lực triển khai, các gói thầu do Tổng công ty VINACONEX đảm nhận tại Dự án cao tốc Tuyên Quang – Hà Giang giai đoạn 1 , đoạn qua tỉnh Hà Giang đang bứt phá tiến độ. Nhiều hạng mục quan trọng đã hoàn thành, tạo tiền đề để dự án về ...

VINACONEX đua tiến độ trên cao tốc Tuyên Quang – Hà Giang
Loading...