VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE

Sun , 30/06/2024, 15:36:00 (GMT+7)

Covering 5,000 hectares, Long Thanh International Airport is a significant national transportation project being constructed in Long Thanh district, Dong Nai province. Vinaconex and its partners in the VIETUR Joint Venture are honored to have been selected as the contractors for the Passenger Terminal (Phase 1) of the project.

Began on August 31, 2023, the construction of the passenger terminal is inspired by the lotus, Vietnam's national flower. This is part of package No. 5.10 Construction and equipment installation of passenger terminal Building of Component Project No.3: Airport Essential Facilities under Project: Long Thanh International Airport Construction - Phase 1.

VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
The construction of this passenger terminal with lotus-inspired design is accelerated by Vinaconex and its joint venture partners

It is considered to be the most intricate package so far as the terminal’s designed to accommodate 25 million passengers annually, featuring a central ground floor and 3 upper floors; total floor area over 376,450 sqm with 40 arranged close parking positions for aircraft. The construction is expected to take 39 months, from September 2023 to November 2026.

VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Once completed, the passenger terminal would have a design capacity of 25 million passengers peryear; total floor area is over 376,450 sqm with 40 arranged close parking positions for aircraft

Over the past 10 months, the VIETUR contractor joint venture has strived to overcome challenges and adverse weather conditions to ensure the safety, quality, and progress of the Long Thanh International Airport project. 

As for Vinaconex, the contractor has deployed numerous workers, machines, and equipment to execute multiple construction sections simultaneously.

VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
On the mega construction site, Vinaconex and joint venture partners have deployed numerous construction workers working 24/7 in shifts and crews, even during holidays.

As for Vinaconex, the contractor has deployed numerous workers, machines, and equipment to execute multiple construction sections simultaneously.

VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
A view of the terminal from gate 12

Regarding the central area, the reinforced concrete work has reached 97% completion for columns on floors 1F and 2F; 100% completion for the 2F floor formwork erection; 83% completion for the reinforcement and concrete construction of 3F floors, etc. The structural steel cutting is at 53.5%, and fabricating is at 42.3% completion.

VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Erecting reinforced for the 2F floor in the wings area; setting up scaffolding erection & formwork for the 3F floor in the central area
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Setting up scaffolding erection & formwork for the construction
As for the wings area: Key progress includes the completion of concrete work for columns and beams on 1F floor; columns from floors 1F to 2F; scaffolding erection & formwork on the 2F floor. The construction and erection of steel and concrete on the 2F floor reach 82% completion, etc
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Concrete 2F floor reinforcement
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Preparations for pouring concrete on the 2F floor are being finalized urgently
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Construction work of pouring concrete on the 2F floor
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
The progress of pouring concrete on the 2F floor reached 82%

Following an inspection by Airports Corporation of Vietnam (ACV), the Long Thanh International Airport Construction Investment Project has been confirmed to be on track and in compliance with Government's regulations. This acknowledgment highlights and encourages the dedication of Vinaconex and the other contractors involved in the project. 

VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Inspecting structural steel construction work at the project
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Steel fabrication and erection reinforcement on the 3F floor
VINACONEX CONTRACTOR ON LONG THANH INTERNATIONAL AIRPORT CONSTRUCTION SITE
Vinaconex contractor and its joint venture partners remain committed to ensuring safety, quality, and timely progress throughout the project's execution