Sun , 30/06/2024, 15:36:00 (GMT+7)
Covering 5,000 hectares, Long Thanh International Airport is a significant national transportation project being constructed in Long Thanh district, Dong Nai province. Vinaconex and its partners in the VIETUR Joint Venture are honored to have been selected as the contractors for the Passenger Terminal (Phase 1) of the project.
Began on August 31, 2023, the construction of the passenger terminal is inspired by the lotus, Vietnam's national flower. This is part of package No. 5.10 Construction and equipment installation of passenger terminal Building of Component Project No.3: Airport Essential Facilities under Project: Long Thanh International Airport Construction - Phase 1.
It is considered to be the most intricate package so far as the terminal’s designed to accommodate 25 million passengers annually, featuring a central ground floor and 3 upper floors; total floor area over 376,450 sqm with 40 arranged close parking positions for aircraft. The construction is expected to take 39 months, from September 2023 to November 2026.
Over the past 10 months, the VIETUR contractor joint venture has strived to overcome challenges and adverse weather conditions to ensure the safety, quality, and progress of the Long Thanh International Airport project.
As for Vinaconex, the contractor has deployed numerous workers, machines, and equipment to execute multiple construction sections simultaneously.
As for Vinaconex, the contractor has deployed numerous workers, machines, and equipment to execute multiple construction sections simultaneously.
Regarding the central area, the reinforced concrete work has reached 97% completion for columns on floors 1F and 2F; 100% completion for the 2F floor formwork erection; 83% completion for the reinforcement and concrete construction of 3F floors, etc. The structural steel cutting is at 53.5%, and fabricating is at 42.3% completion.
Following an inspection by Airports Corporation of Vietnam (ACV), the Long Thanh International Airport Construction Investment Project has been confirmed to be on track and in compliance with Government's regulations. This acknowledgment highlights and encourages the dedication of Vinaconex and the other contractors involved in the project.