VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL

Fri , 07/06/2024, 14:00:00 (GMT+7)

On June 6, 2024, Mr. Pham Dinh Nghi, Deputy Secretary of Nam Dinh Provincial Party Committee and Chairman of Provincial People's Committee, led a working group to inspect the construction progress of the Nam Dinh Provincial General Hospital, one of the province's key projects. Accompanying him was Mr. Tran Le Doai, Vice Chairman of the Provincial People's Committee, along with leaders from departments and branches, and the Board of Directors of the Provincial General Hospital. Vinaconex is honored to be the construction contractor for this project. 

Representing Vinaconex were Deputy General Director Nguyen Huu Toi, Deputy Director of Project Management Board No. 1 Pham Thanh Hoai, and members of the Project Executive Board and staff involved.

The investment project for constructing Nam Dinh Provincial General Hospital, funded by the Provincial People's Committee, has a total investment exceeding VND 1,755 billion and a capacity of 700 beds.

VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
Mr. Pham Dinh Nghi, Deputy Secretary of Nam Dinh Provincial Party Committee and Chairman of Provincial People's Committee and the working group inspected construction site.
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL

During the working session, Vinaconex provided an report on the construction status: Construction package of Building No. 1 - Emergency Department, professional techniques and administration zones are 99% complete, with only a small portion remaining due to pending installation of the sample transportation system, which is not part of Vinaconex's construction package;
As for Construction package of Building No. 2, 3, and 6, along with certain technical systems (scheduled for completion from July 28, 2023, to March 30, 2025), the total value of the completed work is estimated at around VND 430 billion (over 55% of contract value).

VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL

Speaking at the project site, Chairman of the Provincial People's Committee, Pham Dinh Nghi, acknowledged and commended the hard work of the Provincial Project Management Board for Construction Investment, functional departments and branches of the province, the design consultants, and especially Vinaconex contractor. He requested the Provincial Project Management Board for Construction Investment to prioritize urging construction contractors and design consultants to coordinate and implement solutions seamlessly to complete the project by April 2025.

VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
Chairman of the Provincial People's Committee, Pham Dinh Nghi asked all units to closely coordinate to complete the project on schedule

Besides he directed the Provincial Project Management Board for Construction Investment to actively collaborate with the Department of Health and the Provincial General Hospital to agree on a plan for installing specialized equipment and to promptly complete the remaining tasks according to the schedule. 

VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL

Deputy General Director Nguyen Huu Toi, representing contractor Vinaconex, extended gratitude for the attentive guidance and supervision from all levels and sectors on the project. He committed that Vinaconex and the project units would ensure safety, quality, and progress, aiming to achieve success to welcome Party Congresses at all levels, leading up to the 21st Provincial Party Congress.

VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
According to the plan, Nam Dinh Provincial General Hospital is set to be completed in April 2025.
The construction investment project of Nam Dinh General Hospital, with a total investment exceeding VND1,755 billion and a capacity of 700 beds, is invested by the People's Committee of Nam Dinh province.
Vinaconex, honored to be selected for the project, is responsible for constructing Building No. 1 - Emergency Department, professional techniques and administration zones. This eight-story building, covering an area of more than 21,000 square meters, is 99% complete, with only a small portion remaining due to pending installation of the sample transportation system, which is not part of Vinaconex's construction package.
Construction package of Building No. 2, 3, 6, and some technical systems, including structural, architectural, electrical and water, air conditioning, ventilation, elevator systems; Moreover, extra low voltage, medical gas, and nurse call systems for the entire project (including Houses 1, 2, 3, 4, 5, 6) has been commenced since July 31, 2023. The Project Management Board is expediting the completion of remaining items including Infection House No. 4, Morgue No. 5, the sample transport system, and various technical infrastructure works. 
In particular, Houses No. 2 and No. 3 have completed the construction of the underground, rough, and renovated structures, as well as newly added ones, reaching 100% completion. The 3D partition wall system is 98% complete, and the tiling of floors and restrooms is about 80% finished. Additionally, systems such as air conditioning, fire protection, electricity, extra low voltage, and medical gas are being constructed simultaneously and are expected to reach 90% completion according to the contract.

Some pictures at the project:

VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
The working group inspected the progress of the investment project to build Nam Dinh Provincial General Hospital
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
The investment project to build the Provincial General Hospital has a total investment of over 1,755 billion VND, with a scale of 700 beds, invested by the People's Committee of Nam Dinh province
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
The general hospital has a modern, synchronous design, complete with specialized functional departments and rooms
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
The construction items are being accelerated by contractor Vinaconex 
VINACONEX CONTRACTOR STRIVES FOR TIMELY COMPLETION OF NAM DINH PROVINCIAL GENERAL HOSPITAL
Promote emulation and response to Workers' Month at the Nam Dinh Provincial General Hospital project as well as at works and projects with the participation of contractor Vinaconex

 

 

Latest news

Hội nghị sơ kết công tác Công đoàn 6 tháng đầu năm, triển khai nhiệm vụ 6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác

Ngày 31/7, Công đoàn Tổng công ty tổ chức Hội nghị sơ kết công tác công đoàn 6 tháng đầu năm, triển khai nhiệm vụ trọng tâm 6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác. Đồng chí Âu Thị Định, Phó Chủ tịch Công đoàn XDVN đã tham dự và phát ...

Hội nghị sơ kết công tác Công đoàn 6 tháng đầu năm, triển khai nhiệm vụ  6 tháng cuối năm 2025 và tập huấn nghiệp vụ công tác

Tập Huấn An Toàn – Vệ Sinh Lao Động và khám sức khoẻ tại Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long

Nhằm tăng cường tuân thủ các quy định pháp luật và nâng cao hiệu quả thi công, ngày 28/7/2025, tại Văn phòng Ban QLDA Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long đã diễn ra buổi Huấn luyện An toàn lao động ...

Tập Huấn An Toàn – Vệ Sinh Lao Động và khám sức khoẻ tại Gói thầu số 28 – Dự án đầu tư xây dựng nút giao thông vành đai 3.5 với Đại lộ Thăng Long

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

At the construction site of the Phu Thu Interchange Ninh Binh Province , over 100 engineers, technicians, and workers from the VINACONEX–Trung Chinh joint venture are working around the clock, through holidays, striving to complete the project by ...

TARGETING EARLY COMPLETION OF THE MOST ADVANCED INTERCHANGE ON THE CAU GIE - NINH BINH EXPRESSWAY

VINACONEX CORPORATION’S “BACK TO THE ROOTS” JOURNEY

In celebration of the successful 6th Party Congress of VINACONEX Corporation for the 2025–2030 term, and in commemoration of the 78th War Invalids and Martyrs Day July 27, 1947 – July 27, 2025 , the VINACONEX Trade Union organized a “Back to the ...

VINACONEX CORPORATION’S “BACK TO THE ROOTS” JOURNEY
Loading...