EN

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

Thu , 12/08/2021, 10:40:00 (GMT+7)

 

As a key project of Hanoi, Vinh Tuy Bridge (phase II) is one of six traffic projects permitted by the city to be constructed during the social distancing period to ensure timely completion. Vinaconex contractor and construction units at the project have been trying their best to race against time to finish the project on schedule.

 By design, Vinh Tuy bridge (phase II) runs parallel to Vinh Tuy bridge, currently downstream of the Red River.

Vinh Tuy bridge construction investment project (phase II) is one of the capital's arterial traffic projects, playing an important role in completing the entire Ring Road 2 of Hanoi, strengthening traffic between the two banks of the Red River, meeting the rapidly increasing transport demand between the center of the capital and the northern and northeastern areas of the city.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing .

Vinh Tuy bridge construction investment project (phase II) seen from above

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.

Execution of bored piles T21HL and T22HL – Package 01/VT2 - XL

At Vinh Tuy Bridge construction investment project (phase II), Vinaconex was honored to be selected as a participant in Package 05/VT2 – XL (Vinaconex Joint Venture – 75 Bridge Construction Joint Stock Company) to construct the bridge. Long Bien direction and path, implementation time is 18 months; Package 01/VT2 - XL (Vinaconex - Trung Chinh Joint Venture) construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing      
 
Ensure safety and techniques at construction items on the water surface
 
On the project site, the contractors mobilized 1,000-2,000-ton barges and 4 drilling rigs with floating systems to prepare for the construction of the pile foundation in the middle of the Red River.
Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing    

 Construction of C6 pile T24 HL                          

Construction of lowering steel cage C6 – T24HL

The project currently has about 500 workers divided into 11 stitches, constructing 3 consecutive shifts at the construction site with strict Covid-19 disease prevention and control conditions. The workers are organized to work, live in a concentrated place, do not contact the outside, do not go out of the construction site, strictly comply with 5K.

     Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

 The Executive Board organizes and directs the implementation of 3 consecutive shifts of construction

Compliance with safety regulations for disease prevention is a mandatory condition at the project
  

 All workers must wear masks during work; arranged at distance, staggered eating and drinking hours to reduce concentration.

Overview of construction of bridge piers on the river.

As planned, the whole project will be completed in the second quarter of 2023.

Latest news

Công đoàn Xây dựng Việt Nam thăm, động viên và tặng quà CBCNV Vinaconex tại dự án Vành đai 4 - Vùng Thủ đô

Trong không khí thi đua lao động sôi nổi trên công trường Dự án Vành đai 4 – Vùng Thủ đô, Công đoàn Xây dựng Việt Nam đã tới thăm, động viên và trao quà cho cán bộ, đoàn viên, người lao động VINACONEX đang trực tiếp thi công dự án.

Công  đoàn Xây dựng Việt Nam thăm, động viên và tặng quà CBCNV Vinaconex tại dự án Vành đai 4 - Vùng Thủ đô

VIWASEEN RESHAPES LEADERSHIP AT 2026 EXTRAORDINARY SHAREHOLDERS’ MEETING

On March 5, 2026, Vietnam Water and Environment Investment Corporation VIWASEEN held its Extraordinary General Meeting of Shareholders in Hanoi. With strong backing from shareholders, the meeting approved key resolutions on organizational structure ...

VIWASEEN RESHAPES LEADERSHIP AT 2026 EXTRAORDINARY SHAREHOLDERS’ MEETING

Khởi công nâng cấp Cảng hàng không quốc tế Liên Khương

Ngày 04/3/2026, Tổng công ty Cảng hàng không Việt Nam ACV phối hợp với UBND tỉnh Lâm Đồng tổ chức Lễ khởi công dự án “Sửa chữa đường cất hạ cánh, đường lăn Cảng HKQT Liên Khương”. VINACONEX vinh dự là nhà thầu tham gia thi công Gói thầu số 9 Thi ...

Khởi công nâng cấp Cảng hàng không quốc tế Liên Khương

VINACONEX CHÚC MỪNG NGÀY QUỐC TẾ PHỤ NỮ 8/3: TỎA SÁNG THEO CÁCH RIÊNG CỦA BẠN

Trong không khí ấm áp và trang trọng, chương trình kỷ niệm Ngày Quốc tế Phụ nữ 8/3 với chủ đề “Tỏa sáng theo cách riêng của bạn” đã được VINACONEX tổ chức dành cho nữ CBCNV khối cơ quan TCT, như một lời tri ân và tôn vinh những đóng góp bền bỉ của ...

VINACONEX CHÚC MỪNG NGÀY QUỐC TẾ PHỤ NỮ 8/3:   TỎA SÁNG THEO CÁCH RIÊNG CỦA BẠN
Loading...