Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing - Trang chủ | Vinaconex

EN

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

Thu , 12/08/2021, 10:40:00 (GMT+7)

 

As a key project of Hanoi, Vinh Tuy Bridge (phase II) is one of six traffic projects permitted by the city to be constructed during the social distancing period to ensure timely completion. Vinaconex contractor and construction units at the project have been trying their best to race against time to finish the project on schedule.

 By design, Vinh Tuy bridge (phase II) runs parallel to Vinh Tuy bridge, currently downstream of the Red River.

Vinh Tuy bridge construction investment project (phase II) is one of the capital's arterial traffic projects, playing an important role in completing the entire Ring Road 2 of Hanoi, strengthening traffic between the two banks of the Red River, meeting the rapidly increasing transport demand between the center of the capital and the northern and northeastern areas of the city.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing .

Vinh Tuy bridge construction investment project (phase II) seen from above

Vinh Tuy Bridge (phase II) has a length of bridge and path of about 3,473m; The first point intersects with Nguyen Khoai and Minh Khai streets, the end point intersects with Long Bien - Thach Ban and Co Linh streets. Bridge cross section 19.25m (4 lanes); static height 11m. The bridge has a total investment of 2,538 billion VND; implementation period 2020-2022.

Execution of bored piles T21HL and T22HL – Package 01/VT2 - XL

At Vinh Tuy Bridge construction investment project (phase II), Vinaconex was honored to be selected as a participant in Package 05/VT2 – XL (Vinaconex Joint Venture – 75 Bridge Construction Joint Stock Company) to construct the bridge. Long Bien direction and path, implementation time is 18 months; Package 01/VT2 - XL (Vinaconex - Trung Chinh Joint Venture) construction of main bridge over main stream, including service road, pontoon bridge, overhanging abutment for construction.

Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing      
 
Ensure safety and techniques at construction items on the water surface
 
On the project site, the contractors mobilized 1,000-2,000-ton barges and 4 drilling rigs with floating systems to prepare for the construction of the pile foundation in the middle of the Red River.
Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing    

 Construction of C6 pile T24 HL                          

Construction of lowering steel cage C6 – T24HL

The project currently has about 500 workers divided into 11 stitches, constructing 3 consecutive shifts at the construction site with strict Covid-19 disease prevention and control conditions. The workers are organized to work, live in a concentrated place, do not contact the outside, do not go out of the construction site, strictly comply with 5K.

     Vinh Tuy bridge construction investment project phase II: Ensuring progress in social distancing

 The Executive Board organizes and directs the implementation of 3 consecutive shifts of construction

Compliance with safety regulations for disease prevention is a mandatory condition at the project
  

 All workers must wear masks during work; arranged at distance, staggered eating and drinking hours to reduce concentration.

Overview of construction of bridge piers on the river.

As planned, the whole project will be completed in the second quarter of 2023.

Latest news

“BỮA CƠM CÔNG ĐOÀN” - ẤM ÁP VÀ GẮN KẾT

Thực hiện Hướng dẫn số 02/HD-TLĐ ngày 4/7/2025 của Tổng Liên đoàn Lao động Việt Nam và Hướng dẫn số 441/HD-CĐXD ngày 18/7/2025 của Công đoàn Xây dựng Việt Nam, chương trình “Bữa cơm Công đoàn” được tổ chức nhân dịp kỷ niệm 37 năm ngày thành lập ...

“BỮA CƠM CÔNG ĐOÀN” - ẤM ÁP VÀ GẮN KẾT

VINACONEX gặp gỡ đại diện tạp chí Fortune - Tạp chí kinh doanh hàng đầu thế giới

Ngày 7/10/2025, tại Hà Nội, Tổng công ty VINACONEX đã có buổi làm việc với Tạp chí Fortune – ấn phẩm kinh tế, tài chính hàng đầu thế giới, trực thuộc Tập đoàn Time Inc. Hoa Kỳ .

VINACONEX gặp gỡ đại diện tạp chí Fortune - Tạp chí kinh doanh hàng đầu thế giới

Khánh thành nút giao Phú Thứ - Biểu tượng hạ tầng mới của Ninh Bình

Ngày 27/9/2025, công trình xây dựng Nút giao Phú Thứ và tuyến đường kết nối tại phường Hà Nam đã chính thức được khánh thành và gắn biển, chào mừng Đại hội Đại biểu Đảng bộ tỉnh Ninh Bình lần thứ I, nhiệm kỳ 2025-2030.

Khánh thành nút giao Phú Thứ -  Biểu tượng hạ tầng mới của Ninh Bình

Khởi công Tổ hợp chăm sóc sức khỏe quốc tế AEGIS - Tổ hợp y tế tư nhân quy mô lớn bậc nhất Việt Nam

Sáng 25/9/2025, tại cửa ngõ phía Nam Thủ đô, Công ty TNHH T’Hospital phối hợp cùng Tổng công ty CP VINACONEX tổ chức Lễ khởi công Bệnh viện Quốc tế AEGIS – tổ hợp y tế tư nhân hiện đại, quy mô hàng đầu Việt Nam.

Khởi công Tổ hợp chăm sóc sức khỏe quốc tế AEGIS - Tổ hợp y tế tư nhân quy mô lớn bậc nhất Việt Nam
Loading...