"ALL-NIGHT SHIFTS" AT THE CONSTRUCTION SITE OF RING ROAD NO. 4 - CAPITAL REGION

Thu , 23/05/2024, 15:00:00 (GMT+7)

At the construction site of Ring Road No. 4’s Package 9, a section running through Hoai Duc district (Hanoi), reporters from VTC News observed a hectic and high-intensity working scene, with workers pushing forward on the project even late into the night. 

Nguyen Hoang Hai, the general site manager of Package No. 9 under Vinaconex contractor, explained that recent heavy rains in Hanoi had slowed progress. As soon as the weather cleared, the team ramped up efforts, working overtime through the night to make up for lost time.

Package No. 9 covers a 23-km section passing through Dan Phuong and Hoai Duc districts and has reached approximately 24% completion.

With a steady supply of sand for filling, the site now operates in three shifts around the clock to accelerate progress.

Currently, Vinaconex contractor has deployed around 200 machines and 300 workers, working continuously to meet the project’s deadlines. 

According to workers, night shifts usually run from 5 PM to 11 PM daily but can extend until 2 AM the next morning when necessary.

Many workers live on-site, eating and resting there to maintain productivity.

Nguyen Hoang Hai, the general site manager, set a goal of completing the project about six months ahead of schedule.

Numerous workers remained at the construction site, not going back home for several months.

Around 9 PM, Le Huy Hoang, the deputy commander of Package No.9’s second team, signaled a break for the workers for supper.

Workers gathered at the newly leveled construction site for a quick meal

The quick meal of bread and milk recharged the night’s labor.

Dao Quy Tham, a road roller driver, noted that while working in the cooler nighttime hours, his productivity increased, making the overtime shifts more manageable. “It’s just a small contribution, but I feel proud seeing this key project for the capital take shape,” he said.

A rare moment of rest for a worker at the construction site.

After only nine months since the groundbreaking ceremony, the shape of Hanoi’s Ring Road 4 is becoming visible. The construction team knows many more sleepless nights lie ahead as they push toward the project’s completion 6 months ahead of schedule.

The 112-kilometer Ring Road No. 4 in the Capital Region passes through Hanoi, Hung Yen, and Bac Ninh, beginning at the Hanoi - Lao Cai Expressway and ending at the Noi Bai - Ha Long Expressway. 

With a total investment exceeding VND 85,000 billion, the project broke ground in June 2023 and is scheduled for completion by 2026, with operations set to begin in 2027.

The project has seven component packages, each implemented independently. In which, Hanoi implements three component projects: Compensation, support, and resettlement; construction of parallel urban roads and investment in building a highway system under a public-private partnership (PPP) model.

Once completed, Ring Road No.4 will ease traffic congestion, enhance connectivity between provinces, and open new development opportunities for Hanoi, Hung Yen, Bac Ninh, and the broader Capital Region.

Source:  vtcnews.vn

Latest news

VINACONEX vượt khó thi công cầu vượt Sông Hồng

Cầu vượt Sông Hồng thuộc Gói thầu B.02, Km46+932, tuyến cao tốc Ninh Bình – Hải Phòng, đoạn qua Nam Định và Thái Bình, đang từng bước hình thành. Trong điều kiện thi công phức tạp trên sông, VINACONEX tập trung nguồn lực, tổ chức đồng thời nhiều mũi ...

VINACONEX vượt khó thi công cầu vượt Sông Hồng

Phó Thủ tướng Thường trực Chính phủ kiểm tra tiến độ Dự án Cảng HKQT Long Thành

Sáng 4/10, Ủy viên Bộ Chính trị, Phó Thủ tướng Thường trực Chính phủ Phạm Gia Túc dẫn đầu Đoàn công tác kiểm tra tiến độ xây dựng Dự án Cảng HKQT Long Thành và các tuyến giao thông kết nối. Tổng Giám đốc Tổng công ty Phạm Thái Dương cùng Ban Điều ...

Phó Thủ tướng Thường trực Chính phủ kiểm tra tiến độ Dự án Cảng HKQT Long Thành

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

38 năm hình thành và phát triển là hành trình được tạo nên bởi bản lĩnh, trí tuệ, sự bền bỉ và tinh thần đoàn kết của nhiều thế hệ người lao động VINACONEX. Từ những giá trị được vun đắp qua năm tháng, Tổng công ty hôm nay tiếp tục đổi mới, nâng cao ...

Lễ kỷ niệm 38 năm thành lập Tổng công ty VINACONEX: Xây những giá trị, dựng những ước mơ

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công

Tổng công ty CP VINACONEX vừa tiếp nhận lô thiết bị máy khoan cọc nhồi SANY SR235 và SANY SR285R, bổ sung nguồn lực thiết bị hiện đại, góp phần nâng cao năng lực thi công nền móng và tăng tính chủ động trong triển khai các dự án quy mô lớn.

VINACONEX tiếp nhận thiết bị máy khoan cọc nhồi, tăng cường năng lực thi công
Loading...