SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Wed , 14/07/2021, 08:52:21 (GMT+7)

With the aim to complete the entire Ring Road 2, over the past time, the workers at the Vinh Tuy Bridge phase 2 project have been working actively all day and night. 

Vinh Tuy Bridge phase 2 has a total investment of over VND 2,500 billion. The bridge has a total length of more than 3.4 kilometers including the approaches, with a surface width of 19.25 meters (4 lanes), and a static height of 11 meters.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Sharing to the reporters, Mr. Do Viet Thang, Managing Director of Package 5 said: “We’re now working on the T74HL and T76H L pillars in package 5, involving about 30 officers and workers. The construction site has 2 construction sections working in 3 consecutive shifts. It’s estimated that we have reached 25% of the total workload.”

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Due to the complicated evolution of the Covid-19 pandemic, the contractor has added a lot of indicators at the Ministry of Health's request as well as for all propagating to workers not to gather outside the construction site, having meals right inside camps in shifts, and following social distancing.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The hot summer heat had a great impact on the construction work. The contractors assisted the workers by managing extra night shifts, Mr. Thang added.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

The bridge was designed with permanent reinforced concrete and prestressed concrete structures with design load HL-93, and could withstand earthquakes of grade 8 in accordance to TCVN11823-2017. Even though the underground construction site was covered up and the pumps were also set up, it would still be very challenging in case of heavy rain causing flooding.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

On the construction site of the Le Van Luong - Khuat Duy Tien underpass, dozens of workers were in rush to deploy pile pressing of pumping station construction before the rainy season arrived.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Le Van Luong - Khuat Duy Tien underpass project was kicked off in October 2020 with a total investment of nearly VND700 billion, and scheduled for completion after months. This 475-meter-long underpass is made of a reinforced concrete structure in the direction of Le Van Luong - To Huu street, including a 95-meter underground tunnel and 380 meters of access and exit ramps (each ramp is 190 meters long).

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

Engineer Tran Phuong Nam, in charge of the project site, shared with the reporters that there were 50 – 60 permanent workers working urgently in 9 construction sections to complete two underground culverts for water drainage in the upcoming rainy season.

He also mentioned that every morning, all employees and workers had to measure body temperature, disinfect hands and put on masks before entering the construction site. There was also a monitor group to watch over and record every person entering and departing the site in order to prevent the Covid-19 pandemic.

The underground culverts item, which has been 95% completed, is considered very important to the project.

SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON
SPEEDING UP THE KEY UNDERGROUND TRAFFIC WORKS IN HANOI BEFORE THE RAINY SEASON

As the reporter noted, the narrowing of both sidewalks was executed by workers to broaden the 315-meter length of Le Van Luong street, and the 390-meter length of To Huu street.

Latest news

VINACONEX thúc đẩy hợp tác đào tạo, nghiên cứu và ứng dụng công nghệ

Các đơn vị trong hệ sinh thái VINACONEX ký kết Biên bản hợp tác với Đại học Thái Nguyên, mở rộng liên kết trong đào tạo nguồn nhân lực, nghiên cứu khoa học thuộc lĩnh vực Y tế, năng lượng…

VINACONEX thúc đẩy hợp tác đào tạo, nghiên cứu và ứng dụng công nghệ

Thủy điện Ngòi Phát chính thức cán mốc 5 tỷ Kwh điện

Sau 12 năm vận hành, Nhà máy Thủy điện Ngòi Phát đã đóng góp vào hệ thống điện quốc gia 5 tỷ kWh điện, khẳng định hiệu quả đầu tư, năng lực quản lý vận hành và sự bền bỉ của đội ngũ cán bộ, kỹ sư, người lao động.

Thủy điện Ngòi Phát chính thức cán mốc 5 tỷ Kwh điện

VINACONEX tiếp tục ghi danh Top 10 nơi làm việc tốt nhất Việt Nam 2026 – Ngành Xây dựng

VINACONEX tiếp tục được vinh danh trong Top 10 Nơi làm việc tốt nhất Việt Nam 2026 – Ngành Xây dựng, ghi dấu nhiều năm liên tiếp góp mặt trong bảng xếp hạng uy tín, khẳng định nỗ lực xây dựng môi trường làm việc chuyên nghiệp và phát triển nguồn nhân ...

VINACONEX tiếp tục ghi danh Top 10 nơi làm việc tốt nhất Việt Nam 2026 – Ngành Xây dựng

VIWASEEN ký kết biên bản ghi nhớ hợp tác vớI K-WATER

Ngày 21/10/2026, Tổng công ty Đầu tư nước và Môi trường Việt Nam – CTCP VIWASEEN và Tổng công ty Tài nguyên nước Hàn Quốc K-Water tổ chức Lễ ký kết Biên bản ghi nhớ hợp tác MOU , mở ra cơ hội tăng cường kết nối, chia sẻ kinh nghiệm và thúc đẩy ...

VIWASEEN ký kết biên bản ghi nhớ hợp tác vớI K-WATER
Loading...